A high-performance Agile team:
Show answerHide answer
Correct answer: C
is self-organizing, empowered to make decisions, and consensus-driven, with
constructive disagreement.
PMI Agile Certified Practitioner
Free PMI-ACP mock exam questions 31–40, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
A high-performance Agile team:
Correct answer: C
is self-organizing, empowered to make decisions, and consensus-driven, with
constructive disagreement.
The term ¡°last responsible moment¡± refers to the moment at which:
Correct answer: B
failing to make a decision eliminates an important alternative.
The primary purpose of a Sprint Review is for the team to:
Correct answer: A
Demonstrate what was accomplished during the sprint.
Team A is producing 61 points per iteration and Team B is producing 20 points per
iteration. Team A has more senior engineers. A manager demands that Team B match
Team A’s points in the next iteration. Based on this information, it is reasonable to tell the
manager that:
Correct answer: A
it is impossible to compare two separate teams on points alone.
The purpose of a project burndown chart is to:
Correct answer: D
Display the remaining work across time.
Based on the following figure, during Iteration 5, there was an increase in story point value
(shown on the graph); however, the team completed all of the work it promised to deliver in
the iteration and existing estimates were not changed. From this information, one can
inferthat:
Correct answer: B
Work was added to the Product Backlog.
A ScrumMaster:
Correct answer: C
provides leadership, guidance, and coaching.
Which management style does Agile advocate?
Correct answer: B
Team
What is one of the benefits of incremental delivery?
Correct answer: A
Value is delivered more quickly, as software can be released after every iteration.
During iteration planning, the team is discussing the design for a user story. A team
member states that a design document should be started since the system is complex in
nature. Another team member responds that in Agile there is no documentation. How
should the ScrumMaster respond?
Correct answer: B
Explain that interactions are valued over documentation, but documentation is not
forbidden.
Full-length mocks with the same number of questions and the same time limit as the real PMI-ACP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full PMI-ACP mock exam