Question 11 Choose 1

Project managers use velocity to determine:

Show answerHide answer

Correct answer: A

If the team is committing to an appropriate amount of work for the iteration.

Question 12 Choose 1

Which of the following best represents both a principle of the Agile manifesto and a Lean
method of simplicity?

Show answerHide answer

Correct answer: A

Maximizing the amount of work not done

Question 13 Choose 1

When interacting with team members, the Agile project manager should:

Show answerHide answer

Correct answer: A

Ask team members to do things by phrasing the statement as a request rather than as a
demand.

Question 14 Choose 1

Applying the Pareto rule when prioritizing the Product Backlog means that:

Show answerHide answer

Correct answer: D

a small percentage of the work will provide a large percentage of the value.

Question 15 Choose 1

The advantage of face-to-face collaboration emphasized in eXtreme Programming (XP) is
that it:

Show answerHide answer

Correct answer: C

eliminates communication delays and misunderstandings.

Question 16 Choose 1

Retrospectives provide an opportunity for the team to:

Show answerHide answer

Correct answer: A

Reflect at the end of every iteration and identify improvements that will increase the
quality of the product.

Question 17 Choose 1

For the best results in an Agile project, customers should:

Show answerHide answer

Correct answer: A

set priorities and identify product features.

Question 18 Choose 1

A project team estimates that they should complete 30 story points in the current iteration.
Partway through the iteration they realize that they will complete 50 story points at their
current rate. The team should:

Show answerHide answer

Correct answer: D

Release members to meet the estimated velocity.

Question 19 Choose 1

What key benefits might stakeholders realize from an Agile approach?

Show answerHide answer

Correct answer: B

The early and continuous delivery of valuable software, providing increased visibility and
the opportunity for more frequent adjustments

Question 20 Choose 1

The velocity chart, storyboard, burndown chart, and impediment list are often
communicated using:

Show answerHide answer

Correct answer: B

Information radiators.

Full mock exam

Sit the PMI-ACP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMI-ACP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMI-ACP mock exam
  • 65questions per mock
  • 105 mintime limit
  • 208questions in the bank
  • Newmock on every attempt