You are the planner for a distribution company.
You observe an increase in planned orders for item C0001. You must track the source for
these planned
orders and break them out based on their demand. You are not concerned with safety
stock maximums for this
item.
You need to ensure that the master planning batch job will create a unique planned
purchase order for every
new demand requirement for C0001.
Which coverage code should you use?
Show answerHide answer
Correct answer: D
Requirement
Explanation
https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/coveragesettings