Question 1

You need to configure quality controls.
Which solution objects should you configure? To answer, drag the appropriate solution
objects to the correct configurations. Each solution object may be used once, more than
once, or not at all. You may need to drag the split bar between panes or scroll to view
content.
NOTE: Each correct selection is worth one point.

Show answerHide answer

Explanation

Explanation:

Box 1: Test groups
Requirement 1: 100 percent of all nutritional supplements and 50 percent of all energy
drinks must be tested when production orders are completed. After a product is in testing,
100 percent of all tests must be completed.
You use the Test groups page to set up, edit, and view test groups and the individual tests
that are assigned to them. The upper part of the page shows the test groups, and the lower part shows the tests that are assigned to a selected test group.
You assign several policies to a test group, such as a sampling plan, an acceptable quality
level (AQL), and the requirement for destructive testing. Then, when you assign an
individual test to a test group, you define additional information, such as the sequence,
documents, and validity dates. For a quantitative test, the information that you define also
includes the acceptable measurement values. For a qualitative test, the information
includes the test variable and default outcome.
The test group that is assigned to a quality order defines the default set of tests that must
be performed on the specified item. However, you can add, delete, or change tests for the
quality order. Test results are reported for each test on a quality order.
Box 2: Quality groups
Requirement 2: 75 percent of all nutritional supplements and energy drinks should be
tested against their required tests during an outbound process.
Quality groups
A quality group represents common testing requirements for items.
Use and create item quality groups to logically group products so that they can be assigned
to quality associations for the automatic generation of quality orders.
Example of an item quality group
A manufacturing company purchases various raw materials that have the same testing
requirements for incoming inspection. Therefore, the company defines a quality group and
then assigns the item numbers that are associated with the raw materials to that group.
Later, the company purchases a new type of raw material that has the same testing
requirements. Instead of setting up new testing requirements for the new material, the
company adds the item number for the new material to the existing quality group.

Question 2 Choose 1

You need to configure the system for the customer tier B pricing.
What should you do?

Show answerHide answer

Correct answer: E

Approve and confirm the trade allowance agreement.

Explanation

Explanation:
Note: Customers are categorized into four pricing tiers (A, B, C, and D) based on sales
volume over the past 12 months.
Promotional fund and Trade allowance agreement
A trade allowance agreement is an incentive program where pay-for-performance monetary
rewards are offered to customers that achieve specific volume targets and/or behavioral
goals. Promotional funds are budgeted expenditures. In that way, the promotional
campaigns can be captured.
Reference: https://docs.microsoft.com/en-us/dynamics365/supply-chain/salesmarketing/
trade-allowance#promotional-fund-and-trade-allowance-agreement

Question 3 Choose 1

Trey Research is now live on Dynamics 365 Supply Chain Management.
You need to apply the new cost model for the apparel items.
What should you do?

Show answerHide answer

Correct answer: A

Run Inventory close.

Explanation

Explanation:
Apparel items will not be upgraded to the new costing method until after the go-live date
due to resourcing and implementation limitations from the apparel team. The inventory close process settles issue transactions to receipt transactions, based on the
inventory valuation method that is selected in the item’s item model group. As part of the
settlement process, you can specify that the general ledger should be updated, so that it
reflects the adjustments that have been made. However, until inventory close or
recalculation has been run, issue transactions are posted at the calculated running average
cost price.
After inventory close, you can no longer post in periods that are before the inventory
closing date that you set, unless you reverse a completed inventory close process. For
example, if inventory close is run for the period that ends on January 31, you can't post
transactions that have a date that is earlier than January 31.
Reference: https://docs.microsoft.com/en-us/dynamics365/supply-chain/costmanagement/
backflush-costing
https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/bomcalculations

That's the last free question in Topic 5: Trey Research

You've seen the free 30% (3 of 12 questions). Full access unlocks every question and full-length MB-330 mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the MB-330 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real MB-330 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full MB-330 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 403questions in the bank