Question 71 Choose 1
The primary purpose of a gate review is to decide:
Show answerHide answer

Correct answer: D whether to continue with the project.

Explanation

Summary:
A gate review, also known as a stage-gate or kill-point, is a key governance event in a phased project life cycle. It is held at the end of a project phase and is conducted by the project board or sponsor. Its primary function is to make a strategic, go/no-go decision about the project's future before authorizing the commitment of further resources to the next phase.

Correct Option:

D. whether to continue with the project.
This is the fundamental purpose of a gate review. It is a formal decision point to assess the project's continued viability based on its performance to date, the updated business case, and the plan for the next phase. The decision can be to proceed, to terminate, or to repeat the current phase.

Incorrect Option:

A. whether the project manager and team are performing well.
While team performance may be discussed, this is a secondary concern. The gate review focuses on the project's health and strategic alignment, not individual performance appraisals.

B. if the project is on schedule and within budget.
While schedule and budget performance are critical pieces of information reviewed at the gate, they are inputs to the decision, not the decision itself. The primary purpose is to use this data to decide on the project's continuation.

C. if stakeholders are satisfied.
Stakeholder satisfaction is an important success factor, but it is not the sole purpose of a gate review. The review considers a wider set of criteria, including business justification, risks, and benefits, to make the continuation decision.

Reference:
APM Body of Knowledge 7th Edition, Section 2.2 (Project Life Cycle). It describes phases and governance decision points, stating that the end of a phase "provides a natural break point to review progress and to approve the start of the next phase," which is the definition of a gate review to decide on continuation.
Question 72 Choose 1
What might be considered a disadvantage of virtual communication?
Show answerHide answer

Correct answer: B Communication being misunderstood.

Explanation

Summary:
Virtual communication, while offering flexibility and reach, lacks many of the non-verbal cues present in face-to-face interaction, such as body language, tone of voice, and immediate context. This reduction in communication bandwidth significantly increases the risk of the message being interpreted incorrectly, leading to misunderstandings, errors, and conflict, which is a fundamental disadvantage of the medium.

Correct Option:

B. Communication being misunderstood.
This is a well-documented and primary disadvantage. The absence of non-verbal cues and the potential for technical delays can strip nuance from a message. Written messages can seem blunt, and video calls can still miss subtle facial expressions, making it easier for recipients to misinterpret the intent or urgency behind the communication.

Incorrect Option:

A. Digital communication links never seem to work as required.
While technical issues are a common frustration, they are a practical challenge that can often be resolved with better technology or contingency plans. They are not a fundamental, inherent disadvantage of the communication method itself in the way that the increased potential for misunderstanding is.

C. There is no method for providing feedback.
This is false. Most virtual communication tools (email, chat, video conferencing) have built-in feedback mechanisms like reply functions, reaction emojis, and chat boxes. The issue is often the quality or timeliness of the feedback, not its complete absence.

D. This method of communication tends to be time consuming.
Virtual communication can actually be more time-efficient by reducing travel. While poorly run virtual meetings can be inefficient, this is not an inherent disadvantage of the medium itself but rather a result of how it is managed.

Reference:
APM Body of Knowledge 7th Edition, Section 4.6 (Communication). It discusses the importance of choosing the appropriate method and medium for communication, noting that factors like complexity and sensitivity must be considered. This implies an awareness that some mediums (like virtual) are less rich and carry a higher risk of misunderstanding for certain types of messages.
Question 73 Choose 1
The project management plan:
Show answerHide answer

Correct answer: B describes the success criteria for the project.

Explanation

Summary:
The project management plan (PMP) is the single, integrated document that defines how the project will be executed, monitored, controlled, and closed. It is a comprehensive blueprint that consolidates all subsidiary plans (scope, schedule, cost, quality, risk, etc.) and establishes the baseline against which project performance is measured. A key function of this document is to define what constitutes project success.

Correct Option:

B. describes the success criteria for the project.
This is correct. The project management plan documents the specific, measurable criteria that will be used to judge whether the project is successful. This includes not just time and cost targets, but also scope, quality, and benefit realization criteria, providing a complete picture of what "done" and "successful" means.

Incorrect Option:

A. justifies undertaking the project.
This is the purpose of the business case. The business case provides the justification and reason for the project's existence, while the project management plan describes how it will be delivered.

C. focuses primarily on time related issues.
This is incorrect. While the schedule is a critical component, the PMP is a comprehensive document that covers all aspects of the project, including scope, cost, quality, risk, resources, and communications. It does not focus primarily on one area.

D. describes the success factor for the project.
This is a subtle but important distinction. Success factors are the elements necessary to achieve success (e.g., effective sponsorship, clear requirements). Success criteria are the measures used to judge success. The PMP formally documents the success criteria.

Reference:
APM Body of Knowledge 7th Edition, Section 3.3 (Scheduling) and 2.5 (Project Management). It refers to the project management plan as the key document that defines the project's objectives and how they will be achieved, which inherently includes defining the success criteria.
Question 74 Choose 1
In which phase of the project should the Procurement Strategy be written?
Show answerHide answer

Correct answer: B Definition

Explanation

Summary:
The project life cycle consists of distinct phases, each with a specific purpose. The Procurement Strategy is a high-level plan defining how, when, and from whom goods and services will be acquired. It must be developed early enough to inform major project decisions and budgeting, but only after there is a clear enough understanding of the project's needs to make sound strategic choices.

Correct Option:

B. Definition.
This is the correct phase. During the Definition phase, the project's scope, objectives, and deliverables are detailed. This clarity is a prerequisite for creating a meaningful Procurement Strategy, as it defines what needs to be procured. The strategy can then be developed to determine how to procure it, forming a key part of the overall project management plan before execution begins.

Incorrect Option:

A. Concept.
The Concept phase is too early. At this stage, the project's feasibility and high-level justification are being explored. The detailed requirements necessary to formulate a procurement strategy are not yet known.

C. Deployment.
The Deployment (or Implementation) phase is too late. This is when the project's deliverables are being built and executed. The Procurement Strategy must be in place before this phase to guide the actual procurement activities, such as tendering and contract awarding.

D. Transition.
The Transition phase involves handing over the final project deliverables to the operational teams. By this point, all significant procurement should be complete, making the development of a procurement strategy irrelevant.

Reference:
APM Body of Knowledge 7th Edition, Section 3.10 (Procurement). It discusses procurement within the context of project planning and delivery. The strategy is a planning document, and the primary planning occurs during the Definition phase of the project life cycle.
Question 75 Choose 1
Which of the following is not a purpose of milestones?
Show answerHide answer

Correct answer: A Adjusting resource requirements.

Explanation

Summary:
Milestones are significant events in a project schedule that represent a point of achievement, such as the completion of a major phase or a key decision point. They are used as markers for progress control, setting major deadlines, and often for triggering payments. They are not used for the detailed, day-to-day adjustment of resources, which is managed at the activity level.

Correct Option:

A. Adjusting resource requirements.
This is not a purpose of milestones. Milestones are zero-duration markers that signify a point in time; they do not consume resources themselves. Resource requirements are adjusted based on the detailed tasks and work packages leading up to a milestone, not by the milestone event.

Incorrect Option:

B. Controlling project progress.
This is a primary purpose. Milestones serve as key checkpoints to measure progress against the plan. Reaching a milestone on time indicates the project is on track, while a missed milestone signals a potential problem that needs management attention.

C. Scheduling payments for deliverables.
This is a common purpose, especially in contracts. A milestone can be linked to the completion and acceptance of a key deliverable, which then triggers a pre-agreed payment from the client to the contractor.

D. Setting major deadlines.
This is a fundamental purpose. Milestones are used to establish and communicate the project's most critical dates, such as the end of a phase, a go-live date, or a crucial review meeting.

Reference:
APM Body of Knowledge 7th Edition, Section 3.6 (Scheduling). It describes milestones as "significant points or events in the project" used for reporting progress, which aligns with their purposes for controlling progress and setting deadlines.
Question 76 Choose 1
Which of the following statements about risks and issues is correct?
Show answerHide answer

Correct answer: C Issues must be dealt with by the governance board.

Explanation

Summary:
This question tests the understanding of governance and escalation paths for risks and issues. A key principle is that the project manager is responsible for managing risks and issues within agreed-upon tolerances. However, when a problem cannot be resolved at the project level or exceeds the project manager's authority, it must be escalated to the governing body for a decision.

Correct Option:

C. Issues must be dealt with by the governance board.
This is the most correct statement among the options. While not all issues must go to the governance board, a core principle is that issues which cannot be resolved by the project manager, or which breach agreed tolerances, must be escalated to the project's governance board (e.g., Project Board) for a decision. The board has the ultimate accountability for the project and must deal with major problems.

Incorrect Option:

A. Issues must be escalated to the project sponsor.
This is incorrect because it is too specific. While the sponsor is often a key member of the governance board, the formal escalation path is to the collective governance board, not just to the sponsor individually. The board as a whole deals with the issue.

B. Risks must be escalated to the project sponsor.
This is incorrect. Most risks are managed by the project manager and team. Only major risks that exceed the project manager's authority or agreed risk thresholds are escalated, and they are escalated to the governance board, not necessarily directly and solely to the sponsor.

D. Risks must be dealt with by the governance board.
This is incorrect. The project manager owns the risk management process. The governance board's role is to set risk tolerances and make decisions on escalated risks, but they do not deal with all risks directly.

Reference:
APM Body of Knowledge 7th Edition, Section 3.9 (Issue and Problem Management). It states that an issue management process should define how issues are "reported, analyzed, managed, and escalated," confirming that escalation to the governance board is the correct path for unresolved or significant issues.
Question 77 Choose 1
Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3) Deployment 4) Development
Show answerHide answer

Correct answer: D 2, 3 and 4

Explanation

Summary:
An iterative life cycle involves repeating cycles of development to progressively elaborate and deliver the project's scope. While specific phase names can vary, the core of this lifecycle is the repetition of development work. The Concept and Feasibility phases are typically sequential, initial phases that occur before the iterative cycles begin. The iterative cycle itself consists of repeated Development and Deployment phases.

Correct Option:

D. 2, 3 and 4 (Feasibility, Deployment, Development).
This is the correct set for an iterative lifecycle. The process often begins with a Feasibility phase. The core iterative loop then consists of repeated Development (building a feature or increment) and Deployment (releasing that increment) phases. This "Develop-Deploy" cycle repeats until the final product is complete.

Incorrect Option:

A. 3 and 4 only (Deployment and Development).
This is incomplete. While Development and Deployment form the core iterative loop, a preliminary Feasibility phase is typically needed to determine if the project is viable before committing to the iterative development cycles.

B. 1, 2 and 3 (Concept, Feasibility, Deployment).
This is incorrect because it omits the Development phase, which is the fundamental activity within any iterative cycle. You cannot have a deployment without development.

C. 1 and 2 only (Concept and Feasibility).
This describes only the initial, pre-project sequential phases. It completely omits the iterative delivery phases (Development and Deployment) that define this type of life cycle.

Reference:
APM Body of Knowledge 7th Edition, Section 3.4 (Development Approaches). It describes iterative and hybrid lifecycles as those where "scope is delivered in successive groups of features or products," which aligns with the repeated sequence of Development and Deployment phases following initial feasibility.
Question 78 Choose 1
Which of the following are not considered by quality planning?
Show answerHide answer

Correct answer: A Contingency budget for remedial work.

Explanation

Summary:
Quality planning is a proactive process that defines the quality standards for the project and determines how they will be met. It focuses on establishing processes, resources, and criteria to prevent defects and ensure deliverables are correct. It does not involve planning for the financial consequences of failure, which is a reactive measure handled by other planning areas.

Correct Option:

A. Contingency budget for remedial work.
This is not considered by quality planning. A contingency budget for rework or remedial work is part of cost or risk management planning. Quality planning is focused on "getting it right the first time" (prevention over inspection). Budgeting for failure assumes defects will occur, which contradicts the proactive purpose of quality planning.

Incorrect Option:

B. Equipment required for quality testing.
This is a direct concern of quality planning. The plan must identify the tools, equipment, and resources needed to perform the required quality control activities, such as testing and inspection.

C. Staff qualified to undertake inspections.
This is considered by quality planning. The plan must specify the skills, competencies, and roles needed to perform quality-related activities, which directly influences training needs and resource acquisition.

D. Processes to obtain stakeholder approvals.
This is a key part of quality planning. The plan defines the acceptance criteria for deliverables and the specific processes (e.g., reviews, sign-offs) for obtaining formal stakeholder approval, which is a critical quality gate.

Reference:
APM Body of Knowledge 7th Edition, Section 3.12 (Quality Management). It describes quality planning as identifying quality standards and determining how to satisfy them, which involves processes, resources, and criteria—not the budget for fixing failures. Cost contingency is addressed in Section 3.5 (Estimating).

That's the last free question

You've seen the free 30% (78 of 260 questions). Full access unlocks every question and full-length APM-PFQ mock exams, a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the APM-PFQ exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real APM-PFQ exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full APM-PFQ mock exam
  • —questions per mock
  • —time limit
  • 260questions in the bank
  • Newmock on every attempt