Show answerHide answer
Correct answer: B Concept
Explanation
Summary:Analogous estimating, also known as top-down estimating, uses historical data from a similar past project to provide a high-level estimate. It is less accurate but quicker and cheaper than other methods. This approach is most valuable in the early phases of a project life cycle when detailed information is scarce, but a rough estimate of cost or duration is needed for initial decision-making and feasibility checks.
Correct Option:
B. Concept:
This is the correct answer. During the concept phase, the project is just being initiated. There is minimal detail available about deliverables, resources, or specific activities. Analogous estimating provides a swift, high-level estimate based on analogous past projects, which is perfectly suited for this stage to evaluate the project's viability and secure initial approval without investing significant time in detailed planning.
Incorrect Option:
A. Transition:
This phase typically involves handing over the final project deliverables to the operational teams. By this late stage, detailed estimates based on actual project data should already be established and used, making high-level analogous estimates irrelevant.
C. Deployment:
This is part of the project's execution and closure stages, where the project's product is being implemented. Detailed bottom-up estimates and actual cost tracking are used here, not high-level analogous estimates.
D. Definition:
In the definition phase, detailed project planning occurs. While an analogous estimate from the concept phase might be a starting point, this phase requires more accurate estimating techniques, like bottom-up or parametric estimating, which rely on the detailed scope information developed during this stage.
Reference:
APM Body of Knowledge 7th Edition, Section 3.5 (Estimating).