Show answerHide answer
Correct answer: D Reduction in contingency reserves are achieved.
Explanation
SummaryRe-estimating throughout the project life cycle refines cost, time, and resource predictions as new information emerges. This improves accuracy and reduces uncertainty, allowing for better resource allocation. Option D is correct, as re-estimating often leads to a reduction in contingency reserves by aligning estimates with actual progress, per APM’s framework. Other options, like economic viability or duration reduction, are not directly tied to re-estimating’s primary benefit.
Correct Option:
D - Reduction in contingency reserves are achieved
Option D is correct as re-estimating refines predictions, reducing uncertainty and the need for large contingency reserves.
APM’s framework highlights that ongoing estimation adjusts forecasts based on actual data, minimizing over-allocated reserves.
This ensures resources are used efficiently, aligning budgets and schedules with reality, making it a key benefit of re-estimating compared to other options that are less directly impacted.
Incorrect Option:
A - The project will be much more economically viable
Option A is incorrect as economic viability depends on the business case, not directly on re-estimating.
APM notes that re-estimating improves accuracy but does not inherently make the project more viable.
Viability is determined by benefits versus costs, whereas re-estimating primarily reduces contingency reserves, making Option D a more precise benefit of the process.
B - The business case is justified to a greater degree
Option B is incorrect as re-estimating refines estimates, not the business case’s justification.
APM’s guidance states that the business case is established early and validated separately, while re-estimating focuses on cost or time accuracy.
Reduced contingency reserves (Option D) are a direct outcome, whereas business case justification is a broader strategic concern not primarily tied to re-estimating.
C - Overall project duration is reduced
Option C is incorrect as re-estimating does not directly reduce project duration.
APM emphasizes that re-estimating improves accuracy of time and cost forecasts, potentially optimizing contingency reserves.
Duration reduction depends on scheduling or scope changes, not re-estimating, making Option D’s focus on reducing contingency reserves the more accurate benefit of the process.
Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/