APM certification · Exam APM-PFQ

APM-PFQ Mock Exam Page 5

APM Project Fundamentals Qualification (PFQ)

Free APM-PFQ mock exam questions 41–50, each with the answer and an explanation.

20 questions · 30 minutes · free, no sign-up

Free APM-PFQ questions

41–50 of 78 free
Question 41 Choose 1
Stakeholder analysis considers three aspects for each stakeholder. which are:
Show answerHide answer

Correct answer: A their interest in the project. whether or not they Can influence the project and whether their attitude to the project is for or against.

Explanation

Summary:
Stakeholder analysis is a systematic process used to identify and understand the key people, groups, or organizations that may impact or be impacted by a project. The most common and fundamental model for this analysis assesses stakeholders based on three core dimensions: their level of interest in the project's outcome, their power or ability to influence the project, and their overall attitude (supportive or opposed). This helps in developing appropriate engagement strategies.

Correct Option:

A. their interest in the project, whether or not they can influence the project and whether their attitude to the project is for or against.
This is the classic and correct trio for stakeholder analysis. It directly corresponds to the widely used "Power/Interest" or "Power/Influence" grid, with the added critical dimension of attitude (supportive, neutral, or resistant). This combination provides a comprehensive view for effective stakeholder management.

Incorrect Option:

B. their level of technical knowledge, whether or not they are able to act as sponsor and if they are available.
While technical knowledge, sponsorship capability, and availability are practical considerations, they are not the three universal, defining aspects used in a standard stakeholder analysis. These are more specific attributes assessed for particular roles, not the high-level analytical framework.

C. their experience, position in the organizational hierarchy and number of resources managed.
Experience and hierarchical position can be proxies for influence, and resources managed can indicate power. However, this is an incomplete and indirect list. The standard model explicitly focuses on interest and attitude, which are not captured here.

D. their interest in the project, whether or not they are a member of the steering group and if they are likely to resist changes.
While interest is correct and "likely to resist changes" relates to attitude, "membership of the steering group" is just one specific example of influence. The standard model uses the broader concept of "influence" itself, not a single indicator of it.

Reference:
APM Body of Knowledge 7th Edition, Section 2.4 (Stakeholder Management). It describes stakeholder analysis as identifying stakeholders and "understanding their interests, influence and attitude." This directly confirms the three aspects listed in option A.
Question 42 Choose 1
Which of the following responsibilities lies with the project management office?
Show answerHide answer

Correct answer: D Supporting the project sponsor.

Explanation

Summary:
A Project Management Office (PMO) is an organisational structure that standardises project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques. Its responsibilities are centred on support, governance, and ensuring consistency across projects. It operates at a different level than an individual project manager, focusing on organisational enablement rather than day-to-day project execution.

Correct Option:

D. Supporting the project sponsor.
This is a key responsibility of a PMO. The PMO supports sponsors by providing them with consolidated reporting, ensuring projects align with strategy, facilitating governance procedures, and offering guidance on project management standards. This enables the sponsor to make better-informed decisions.

Incorrect Option:

A. Liaising with end users.
Direct liaison with end users is typically the responsibility of the project team, business analysts, or product owners. The PMO's role is supportive and governance-focused, not usually involving direct operational engagement with end-users.

B. Managing suppliers.
Supplier management is an operational activity conducted by the project manager and the project team within the framework of a specific project. The PMO may provide standard contract templates or vendor management procedures, but it does not directly manage suppliers for a project.

C. Providing technical support.
The PMO provides project management support (e.g., scheduling tools, risk management frameworks), not technical or specialist support related to the project's deliverables (e.g., IT infrastructure, engineering solutions). Technical support is the domain of specialist team members.

Reference:
APM Body of Knowledge 7th Edition, Section 2.7 (Project Management Office). It states that a PMO provides "a coordinated and consistent approach to the delivery of the organisation’s projects" and can provide "support and guidance" to project sponsors and managers, which aligns with option D.
Question 43 Choose 1
What is the likely decision to arise from the response stage of the risk management process?
Show answerHide answer

Correct answer: C Whether to proactively invest to bring the exposure to risk within tolerable levels.

Explanation

Summary:
The risk management process consists of several stages: identification, assessment, and response. The response stage, also known as risk treatment, is where actions are decided upon and planned to address the risks that have been identified and prioritised. The core decision at this point is what to do about significant risks to modify the project's exposure to an acceptable level.

Correct Option:

C. Whether to proactively invest to bring the exposure to risk within tolerable levels.
This is the essence of the risk response stage. After assessing a risk's probability and impact, the team must decide on a strategy (e.g., avoid, mitigate, transfer, accept). Mitigation often involves proactively investing resources (time, cost, effort) to reduce the probability or impact of a threat, thereby bringing the overall risk exposure down to a level the project can tolerate.

Incorrect Option:

A. Whether to proceed with the project or recommend termination.
This is a major strategic decision, typically informed by the overall risk exposure revealed by the process, but it is not a specific output of the response stage for individual risks. This is more likely a decision for the project board or sponsor based on the business case.

B. Whether the process being used is robust enough for the project being undertaken.
This is a question of process quality and governance, which would be part of a project audit or health check. It is not a decision that arises from the response stage itself.

D. Whether to use brainstorming or a workshop to decide on the best response.
This describes a technique or method to conduct the response planning. It is a procedural choice, not the substantive decision about how to treat a specific risk that results from that activity.

Reference:
APM Body of Knowledge 7th Edition, Section 3.11 (Risk Management). It defines risk response as the "process of developing options and determining actions to enhance opportunities and reduce threats to project objectives," which directly aligns with the decision to invest resources to control risk exposure.
Question 44 Choose 1
Key performance indicators (KPIs) are used for measuring how a project is progressing towards success and are monitored by project managers:
Show answerHide answer

Correct answer: C throughout the project.

Explanation

Summary:
Key Performance Indicators (KPIs) are quantifiable measures used to evaluate a project's performance against its critical success factors and objectives. To be effective for management and control, they must be monitored regularly and proactively. This allows the project manager to track trends, identify deviations from the plan early, and take corrective action while there is still time to influence the project's outcome, rather than just recording past performance.

Correct Option:

C. throughout the project.
This is the correct answer. KPIs are a vital part of ongoing project monitoring and control. They are tracked from the baseline establishment during planning, through the execution phase, and up to project closure. This continuous monitoring provides a real-time or near-real-time view of project health, enabling proactive management.

Incorrect Option:

A. at the post-project review.
The post-project review is a retrospective activity conducted after the project has finished. While KPIs can be analysed then for lessons learned, the primary value of KPIs is for active management during the project when corrective action is still possible.

B. not more frequently than monthly.
The frequency of monitoring KPIs depends on the project's nature and the specific KPI. For many projects, critical metrics like cost and schedule variance may need to be monitored weekly or even daily, especially during intense phases. Mandating a maximum frequency like "not more than monthly" would render them ineffective for control.

D. only when assessing project risk.
Risk assessment is a specific process within the broader context of project management. KPIs are used for overall performance monitoring, which includes but is not limited to risk. A change in a KPI might trigger a risk assessment, but they are monitored continuously, not just during formal risk reviews.

Reference:
APM Body of Knowledge 7th Edition, Section 3.7 (Monitoring and Control). This section describes the ongoing process of tracking, reviewing, and reporting project performance against agreed plans, which is the fundamental purpose of using KPIs throughout the project life cycle.
Question 45 Choose 1
A project is typically defined in terms of scope, time, cost and which other parameter?
Show answerHide answer

Correct answer: B Quality.

Explanation

Summary:
The fundamental definition of a project is often based on the "triple constraint" or "iron triangle," which outlines the key competing dimensions that a project manager must balance. While traditionally Scope, Time, and Cost are the three core parameters, the APM Body of Knowledge explicitly defines a project by its output, outcomes, or benefits, and the constraints of scope, time, cost, and quality. Quality is the fourth, integral parameter.

Correct Option:

B. Quality.
This is the correct answer. Quality is the fourth fundamental parameter in the project definition. It represents the standards, requirements, and specifications that the project's deliverables must meet. A project is not successful if it delivers the scope on time and within budget but the output is of poor quality and unusable.

Incorrect Option:

A. Benefits.
Benefits are the strategic justification for the project (as defined in the business case) and are an outcome, not a core constraint parameter used in the project's baseline definition alongside scope, time, and cost.

C. Tolerance.
Tolerance is a specific management control concept, representing the permissible deviation allowed in a project objective (e.g., cost tolerance). It is not one of the fundamental defining parameters of the project itself.

D. Controls.
Controls are the processes, procedures, and systems (like reporting and change control) put in place to manage the project parameters. They are how the project is managed, not what defines it.

Reference:
APM Body of Knowledge 7th Edition, Section 1.1 (What is a Project?). It states: "A project is a unique, transient endeavour, undertaken to achieve planned objectives, which could be defined in terms of outputs, outcomes or benefits... A project is usually deemed to be a success if it achieves the objectives according to their acceptance criteria, within an agreed timescale and budget." The acceptance criteria are the quality parameter.
Question 46 Choose 1
A project communication plan identifies the relevant information that should be communicated to:
Show answerHide answer

Correct answer: B the project stakeholders.

Explanation

Summary:
A communication plan is a comprehensive document that outlines the strategy for information exchange throughout the project lifecycle. Its purpose is to ensure that the right information reaches the right people at the right time. While it includes specific details for groups like the team, board, and sponsor, its overarching scope encompasses all parties with an interest in or influence over the project, which is the definition of stakeholders.

Correct Option:

B. the project stakeholders.
This is the correct and most complete answer. Stakeholders are defined as any individual, group, or organization that can affect, be affected by, or perceive itself to be affected by the project. The communication plan is designed to address the information needs of all these parties, not just a single group.

Incorrect Option:

A. the project team.
The project team is a key audience, but the communication plan's scope is much broader. It also includes external stakeholders, users, and governance bodies. Defining it only for the team is too narrow.

C. the project board.
The project board is a crucial stakeholder group with specific communication needs (e.g., highlight reports, stage-end reports). However, the plan must also address communication with other stakeholders like end-users, suppliers, and regulatory bodies.

D. the project sponsor.
The sponsor is a single, albeit very important, stakeholder. A communication plan that only identified information for the sponsor would be critically incomplete and fail to manage the wider stakeholder community effectively.

Reference:
APM Body of Knowledge 7th Edition, Section 4.6 (Communication). It states that communication management involves "systematic planning, implementing... of the parties to be communicated with." The term "parties" refers to all stakeholders, confirming that the plan's audience is the entire stakeholder community.
Question 47 Choose 1
A responsibility assignment matrix (RAM) allows the project manager to cross reference:
Show answerHide answer

Correct answer: A the work breakdown structure (WBS) with the organisational breakdown structure (OBS) to match resources to the tasks.

Explanation

Summary:
A Responsibility Assignment Matrix (RAM), often displayed as a RACI chart, is a project management tool used to clarify roles and responsibilities. Its primary function is to create a clear link between the work that needs to be done and the people or teams who are accountable for doing it. This ensures there is no confusion about who is responsible for each specific task within the project.

Correct Option:

A. the work breakdown structure (WBS) with the organisational breakdown structure (OBS) to match resources to the tasks.
This is the precise purpose of a RAM. The WBS defines all the work packages and tasks (the "what"), and the OBS defines the teams, roles, or individuals (the "who"). The RAM cross-references these two structures to assign responsibility for each task, ensuring clear accountability.

Incorrect Option:

B. the organisational breakdown structure (OBS) with the cost breakdown structure (CBS) to assign a cost to each resource.
This describes a function of project budgeting or cost control, not the RAM. While resource costs are important, the RAM is focused on responsibility for work, not the financial cost of that work.

C. the product breakdown structure (PBS) with the work breakdown structure (WBS) to assign activities to the products.
This describes the relationship between the project's deliverables (PBS) and the work required to create them (WBS). This is a fundamental planning step, but it does not involve assigning human resources, which is the specific role of the RAM.

D. the organisational breakdown structure (OBS) with the product breakdown structure (PBS) to assign resources to deliverables.
While this seems close, it is less precise than option A. The PBS defines the deliverables, but the WBS defines the specific tasks needed to produce those deliverables. The RAM is most effectively used at the task/work package level (WBS) rather than the higher-level deliverable (PBS) to ensure clarity of action.

Reference:
APM Body of Knowledge 7th Edition, Section 3.2 (Scope Management). It discusses the WBS and the importance of assigning responsibility for work packages, which is the core function of a Responsibility Assignment Matrix.
Question 48 Choose 1
Which one of the following best describes a project stakeholder?
Show answerHide answer

Correct answer: B A party with an interest or role in the project or is impacted by the project.

Explanation

Summary:
A project stakeholder is defined in the broadest terms to encompass anyone who can affect or is affected by the project. This definition is intentionally inclusive, covering not only those with a direct interest or role but also those who might be passively impacted by the project's outcome or execution. It is a foundational concept for ensuring all relevant parties are identified and managed.

Correct Option:

B. A party with an interest or role in the project or is impacted by the project.
This is the most accurate and comprehensive definition. It captures the three key aspects: having an interest (e.g., a regulator), playing a role (e.g., the project manager), or being impacted (e.g., an end-user or local community). This aligns perfectly with the official APM definition.

Incorrect Option:

A. A party who is concerned about the project going ahead.
This is too narrow. It excludes stakeholders who are supportive, neutral, or unaware of the project but are still impacted by it. It also omits team members who have a role but may not be "concerned" in the way the term implies.

C. A party who has a vested interest in the outcome of the project.
While many stakeholders have a vested interest, this is not the defining characteristic for all. For example, a supplier providing a standard component has a role and is impacted (they get a contract), but may not have a deep "vested interest" in the project's ultimate success.

D. A party who has a financial stake in the organisation managing the project.
This describes a shareholder or investor in the parent company, which is a specific type of stakeholder. It excludes the vast majority of project stakeholders, such as team members, customers, and end-users, who may have no financial stake in the organisation

Reference:
APM Body of Knowledge 7th Edition, Section 2.4 (Stakeholder Management). It defines a stakeholder as "a person, group or organisation that has an interest in, or can affect, be affected by, or perceive itself to be affected by, any aspect of the project." This directly corresponds to option B.
Question 49 Choose 1
Which of the following statements about scheduling is false?
Show answerHide answer

Correct answer: C Provides a baseline for safety considerations.

Explanation

Summary:
This question asks you to identify the statement that is not a true function or characteristic of project scheduling. Scheduling is the process of determining the order and timing of project activities to create a timeline. While it integrates with many project management areas, one of the listed options is not a direct or primary purpose of the schedule itself.

Correct Option:

C. Provides a baseline for safety considerations.
This is the false statement. While a schedule can indicate when high-risk activities occur, safety considerations are primarily managed through dedicated risk assessments, method statements, and a health & safety plan. The schedule baseline is for measuring time performance, not for establishing safety protocols or acting as a primary reference for safety.

Incorrect Option:

A. Defines the sequence of activities.
This is a true and fundamental purpose of scheduling. It involves identifying dependencies (e.g., finish-to-start) between tasks to determine the logical order in which work must be performed.

B. Considers work calendars and time contingency.
This is true. Schedules must account for non-working days (holidays, weekends) via work calendars. Furthermore, schedule contingency (or buffer) is a standard technique to account for uncertainty and is included in the overall project timeline.

D. Quantifies the required resources.
This is true. The scheduling process involves resource estimation and levelling. The schedule quantifies the amount and type of resources (people, equipment) needed for each activity and when they are required, often leading to resource histograms.

Reference:
APM Body of Knowledge 7th Edition, Section 3.6 (Scheduling). It describes scheduling as defining "the sequence of activities and their start and finish dates," and integrating resources, which confirms options A and D. It does not list providing a baseline for safety as a function of the schedule.
Question 50 Choose 1
Which one of the following best describes users?
Show answerHide answer

Correct answer: B Those intended to receive benefits or operate outputs.

Explanation

Summary:
In project management terminology, "users" are a specific category of stakeholder. They are distinct from the project team, sponsors, or managers. The definition of a user is directly tied to the project's outputs and outcomes; they are the individuals or groups who will ultimately utilize the project's deliverables to realize the intended benefits in their day-to-day work or operations.

Correct Option:

B. Those intended to receive benefits or operate outputs.
This is the most accurate description. Users are the recipients of the project's final product, service, or result. They are the ones who will use the output, and their effective use is what leads to the realization of the project's intended benefits. They are key stakeholders for defining requirements and acceptance criteria.

Incorrect Option:

A. Providers of both strategic and tactical direction to the project.
This describes the roles of the project sponsor (strategic) and potentially the project manager (tactical). Users may provide input on requirements, but they do not typically provide the project's strategic direction.

C. Facilitators of an appropriate issue resolution procedure.
This describes a role within project governance, such as a project manager or a member of a change control board. While users may raise issues, they are not typically responsible for facilitating the resolution process.

D. Those providing full-time commitment to the project.
This describes the core project team members. Users are often representatives from the business who provide part-time input on requirements and testing but return to their business-as-usual roles after the project is delivered.

Reference:
APM Body of Knowledge 7th Edition, Section 2.4 (Stakeholder Management). While it does not have a separate entry for "users," it defines stakeholders by their interest or impact, and users are clearly those impacted by the output and who receive the operational benefits.
Full mock exam

Sit the APM-PFQ exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real APM-PFQ exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.