Question 21 Choose 1
The purpose of a risk register is to provide a:
Show answerHide answer

Correct answer: D record of risks, their impact and the actions taken to manage them.

Explanation

Summary
A risk register is a tool used in project management to document and manage risks throughout the project lifecycle. It records details of identified risks, their potential impact, and the actions taken to mitigate or manage them. Option D is correct, as it accurately describes the risk register’s purpose as a comprehensive record of risks, their impacts, and management actions, aligning with APM’s risk management framework.

Correct Option:

D - Record of risks, their impact and the actions taken to manage them
Option D is correct as the risk register serves as a centralized document capturing identified risks, their potential impacts, and mitigation actions.

APM’s framework emphasizes that it tracks risk details, including probability, impact, and response strategies, to support effective risk management.

This ensures stakeholders have a clear overview of risks and actions, facilitating proactive management throughout the project lifecycle.

Incorrect Option:

A - Structured process for risk identification
Option A is incorrect as the risk register is not a process but a tool for recording risks.

APM notes that risk identification is part of the risk management process, while the register documents the outcomes.

It captures risks after identification, not the process itself, making this option less accurate than Option D, which correctly defines the register’s purpose.

B - Record of the ownership of risk and issue management actions
Option B is incorrect as it focuses only on ownership, which is just one element of the risk register.

APM’s guidance states that the register includes risks, impacts, and actions, not just ownership details.

While ownership is recorded, the primary purpose is broader, making Option D’s comprehensive description of risks, impacts, and actions more accurate.

C - Means of assessing the likelihood and impact of all of the risks
Option C is incorrect as the risk register records assessments, not performs them.

APM emphasizes that likelihood and impact assessments occur during risk analysis, with results documented in the register.

The register’s purpose is to store this information, not to conduct assessments, making Option D’s focus on recording risks, impacts, and actions the correct choice.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 22 Choose 1
Which activity is not utilised by scope management?
Show answerHide answer

Correct answer: C Delivering

Explanation

Summary
Scope management involves defining, identifying, controlling, and verifying the project’s scope to ensure deliverables align with objectives. It focuses on what is included and excluded in the project. Option C, delivering, is not a core scope management activity, as it pertains to execution and delivery processes, not scope definition or control. Option C is correct, as scope management does not include delivering, unlike defining, identifying, and controlling.

Correct Option:

C - Delivering
Option C is correct as delivering is not a scope management activity but part of project execution or delivery processes.

APM’s framework emphasizes scope management as defining, identifying, controlling, and verifying scope, not implementing deliverables.

Delivery involves producing outputs, managed through other processes like schedule or resource management, making it distinct from scope management’s focus on establishing and maintaining scope boundaries.

Incorrect Option:

A - Defining
Option A is incorrect as defining the scope is a core activity of scope management.

APM notes that defining involves specifying deliverables, objectives, and boundaries in the project scope statement.

This ensures clarity on what is included or excluded, making it a fundamental part of scope management, unlike delivering, which focuses on execution rather than scope establishment.

B - Identifying
Option B is incorrect because identifying requirements and deliverables is a key scope management activity.

APM’s guidance highlights that identifying involves gathering stakeholder needs and detailing work packages.

This process ensures all necessary elements are included in the scope, distinguishing it from delivering, which is about producing outputs, not identifying what constitutes the project’s scope.

D - Controlling
Option D is incorrect as controlling is a critical scope management activity.

APM emphasizes that scope control involves monitoring and managing changes to prevent scope creep.

It ensures the project remains aligned with the agreed scope, unlike delivering, which focuses on producing deliverables and is managed through other project processes, not scope management.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 23 Choose 1
Which of the following are documented in a risk register? 1) Analysis 2) Priority 3) Ownership 4) Responses
Show answerHide answer

Correct answer: D 2, 3 and 4

Explanation

Summary
A risk register is a tool that documents key details about identified project risks to support effective risk management. It includes information such as risk priority, ownership, and response strategies to ensure risks are tracked and mitigated. Option D is correct, as it lists priority (2), ownership (3), and responses (4) as documented elements, aligning with APM’s guidance, while analysis is part of the process, not a recorded item.

Correct Option:

D - 2, 3 and 4
Option D is correct as the risk register documents priority (2), ownership (3), and responses (4).

APM’s framework states that priority ranks risks by likelihood and impact, ownership assigns responsibility, and responses outline mitigation strategies.

These elements ensure risks are systematically tracked and managed, providing a clear record for stakeholders to monitor and address risks throughout the project lifecycle.

Incorrect Option:

A - 1, 3 and 4
Option A is incorrect because analysis (1) is a process, not a documented item in the risk register.

APM notes that analysis (assessing likelihood and impact) informs the register’s content, like priority and responses, but is not recorded itself.

Ownership (3) and responses (4) are included, but omitting priority (2) makes this option less accurate than Option D.

B - 1, 2 and 4
Option B is incorrect as analysis (1) is not documented in the risk register.

APM’s guidance emphasizes that the register records outcomes like priority (2) and responses (4), not the analysis process itself.

While priority and responses are valid, excluding ownership (3), a key element for accountability, makes this option incomplete compared to Option D’s comprehensive list.

C - 1, 2 and 3
Option C is incorrect because analysis (1) is not a documented item in the risk register.

APM highlights that priority (2) and ownership (3) are recorded, but analysis is a process informing these entries.

Excluding responses (4), which detail mitigation actions, makes this option less accurate than Option D, which correctly includes priority, ownership, and responses.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 24 Choose 1
For successful risk identification to take place what must the project team know as a minimum?
Show answerHide answer

Correct answer: B Project objectives.

Explanation

Summary
Successful risk identification requires understanding the project’s goals to pinpoint potential threats and opportunities effectively. Knowing the project objectives allows the team to align risk identification with what the project aims to achieve. Option B is correct, as it emphasizes the importance of project objectives as the minimum knowledge needed, per APM’s risk management framework, unlike other options, which are secondary or unrelated to effective risk identification.

Correct Option:

B - Project objectives
Option B is correct as knowing project objectives is essential for effective risk identification.

APM’s framework emphasizes that objectives provide context to identify risks that could impact deliverables, scope, or success.

Understanding objectives ensures the team focuses on relevant threats and opportunities, making it the minimum knowledge required to align risk identification with project goals, unlike other options that are less critical.

Incorrect Option:

A - Skills of the team delivering the project
Option A is incorrect as team skills, while important for execution, are not the minimum requirement for risk identification.

APM notes that risk identification focuses on project objectives, not team capabilities, which are assessed separately.

Skills may influence risk response but are secondary to understanding objectives, which provide the context for identifying relevant risks, making this option less essential than Option B.

C - Amount of time allowed for risk identification to take place
Option C is incorrect as the time allowed for risk identification is a logistical detail, not a minimum requirement.

APM’s guidance prioritizes understanding project objectives to identify risks effectively, not time constraints.

While time management aids the process, it does not provide the context needed for risk identification, unlike objectives, which are critical for aligning risks with project goals.

D - Location of the venue where risk identification will take place
Option D is incorrect as the venue location is irrelevant to effective risk identification.

APM emphasizes that risk identification depends on understanding project objectives, not physical settings.

The location may facilitate meetings but does not influence the ability to identify risks, making it far less critical than knowing the project objectives, which provide the necessary context for risk assessment.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 25 Choose 1
The value of a risk log lies in its ability to provide:
Show answerHide answer

Correct answer: A A. record of all risks, their impact and the actions taken to manage them.

Explanation

Summary
A risk log, also known as a risk register, is a critical tool in project management that documents risks, their impacts, and mitigation actions. Its value lies in providing a comprehensive record to track and manage risks effectively throughout the project. Option A is correct, as it accurately describes the risk log’s purpose of recording all risks, their impacts, and management actions, aligning with APM’s risk management framework.

Correct Option:

A - Record of all risks, their impact and the actions taken to manage them
Option A is correct as the risk log’s primary value is documenting all identified risks, their potential impacts, and mitigation actions.

APM’s framework highlights that the risk log ensures transparency and traceability, enabling effective risk monitoring and response.

This comprehensive record supports stakeholders in managing risks systematically, ensuring alignment with project objectives throughout the lifecycle, unlike the more limited or process-focused options.

Incorrect Option:

B - Record of the ownership of risk and issue management actions
Option B is incorrect as it only captures risk ownership, a subset of the risk log’s content.

APM notes that while ownership is recorded, the log’s value lies in documenting risks, impacts, and actions comprehensively.

Focusing solely on ownership omits critical elements like impact and response strategies, making this option less accurate than Option A’s broader scope.

C - Means of assessing the likelihood and impact of risks
Option C is incorrect as the risk log records assessment outcomes, not the assessment process itself.

APM’s guidance states that likelihood and impact are analyzed during risk management, with results documented in the log.

The log’s value is in storing this information for tracking, not performing assessments, making Option A’s focus on recording risks and actions more accurate.

D - Structured process for risk management
Option D is incorrect because the risk log is a tool, not a process.

APM emphasizes that risk management processes (e.g., identification, assessment) are supported by the log, which records outcomes.

The log’s value lies in its comprehensive documentation of risks, impacts, and actions, not in defining the process, making Option A the correct choice for its focus on the log’s content.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 26 Choose 1
The main objective of stakeholder management is to establish stakeholder:
Show answerHide answer

Correct answer: D engagement.

Explanation

Summary
Stakeholder management focuses on identifying, analyzing, and actively involving stakeholders to ensure project success. Its main objective is to establish stakeholder engagement, fostering collaboration and support to align with project goals. Option D is correct, as engagement encompasses building relationships and ensuring stakeholders are committed, unlike interests, expectations, or influence, which are components of analysis but not the primary goal of stakeholder management per APM’s framework.

Correct Option:

D - Engagement
Option D is correct as stakeholder management aims to establish engagement, ensuring stakeholders are actively involved and supportive.

APM’s framework emphasizes engagement through communication, consultation, and collaboration to align stakeholders with project objectives.

Effective engagement builds trust, mitigates resistance, and ensures stakeholder commitment, making it the primary objective, unlike the other options, which are secondary aspects of stakeholder analysis or management.

Incorrect Option:

A - Interests
Option A is incorrect as identifying stakeholder interests is part of stakeholder analysis, not the main objective.

APM notes that understanding interests informs engagement strategies, but the goal is to actively involve stakeholders.

Interests are a means to tailor communication, not the end goal, making engagement (Option D) the more accurate focus of stakeholder management’s purpose.

B - Expectations
Option B is incorrect because managing expectations is a component of stakeholder management, not its primary objective.

APM’s guidance highlights that while aligning expectations is important, the main goal is fostering engagement to ensure stakeholder support.

Expectations are addressed to facilitate engagement, making Option D’s focus on active involvement more accurate than this secondary aspect.

C - Influence
Option C is incorrect as assessing stakeholder influence is part of analysis, not the main objective of stakeholder management.

APM emphasizes that understanding influence helps prioritize engagement efforts, but the goal is active stakeholder involvement.

Influence is a factor in planning, not the end goal, making Option D’s emphasis on engagement the correct primary objective.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 27 Choose 1
Which of the following is a reason for scheduling?
Show answerHide answer

Correct answer: A To establish what work needs to be performed.

Explanation

Summary
Scheduling in project management involves planning the sequence and timing of tasks to achieve project objectives efficiently. It focuses on determining what work needs to be done, when, and in what order. Option A is correct, as scheduling establishes the work to be performed, aligning with APM’s emphasis on creating a timeline for tasks, unlike the other options, which relate to different project management processes.

Correct Option:

A - To establish what work needs to be performed
Option A is correct as scheduling identifies and sequences the work required to deliver project deliverables.

APM’s framework highlights that scheduling defines tasks, their durations, and dependencies to create a project timeline.

This ensures clarity on what needs to be done and when, supporting effective resource allocation and progress tracking, making it the primary reason for scheduling.

Incorrect Option:

B - To establish the roles and responsibilities of the project team
Option B is incorrect as roles and responsibilities are defined in organizational structures or resource management, not scheduling.

APM notes that scheduling focuses on task sequencing and timing, not team assignments.

Roles are outlined in documents like the project management plan, making this option unrelated to the primary purpose of scheduling, which is to establish work tasks.

C - To produce the quality acceptance criteria
Option C is incorrect as quality acceptance criteria are defined during quality planning, not scheduling.

APM’s guidance emphasizes that scheduling determines task timing and sequence, not quality standards.

Quality criteria are part of scope or quality management processes, making this option irrelevant to scheduling’s focus on establishing the work to be performed.

D - To produce a project management plan
Option D is incorrect as the project management plan is a broader document encompassing multiple processes, not the outcome of scheduling.

APM states that scheduling produces a timeline for tasks, contributing to the plan but not creating it.

The plan includes scope, cost, and risk management, making this option too broad compared to scheduling’s specific focus on work tasks.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 28 Choose 1
One of the main purposes of dividing a project into life cycle phases is to:
Show answerHide answer

Correct answer: A break the work into controllable blocks in terms of effort and size.

Explanation

Summary
Dividing a project into life cycle phases organizes the work into manageable segments, enabling better control and oversight. This structure facilitates planning, execution, and monitoring by breaking the project into smaller, defined stages. Option A is correct, as it highlights the purpose of creating controllable blocks in terms of effort and size, aligning with APM’s emphasis on structured project management, unlike the other options, which focus on unrelated aspects.

Correct Option:

A - Break the work into controllable blocks in terms of effort and size
Option A is correct as dividing a project into phases creates manageable segments for effort and size.

APM’s framework emphasizes that phases allow better control, planning, and resource allocation by structuring work into distinct stages.

This approach enhances oversight and risk management, ensuring each phase is completed effectively before progressing, making it a primary purpose of the project life cycle.

Incorrect Option:

B - Ensure the processes are properly maintained
Option B is incorrect as maintaining processes is a function of project governance, not the primary purpose of life cycle phases.

APM notes that phases focus on organizing work, not ensuring process maintenance, which is managed separately.

While processes are followed within phases, this is secondary to breaking work into controllable blocks, making Option A more accurate.

C - Ensure that the workforce is certain of their individual roles
Option C is incorrect as defining workforce roles is part of resource or team management, not life cycle phases.

APM’s guidance indicates that phases structure work for control, not role clarification, which occurs through organizational plans.

Role certainty is a secondary benefit, not the main purpose, making Option A’s focus on controllable work blocks the correct choice.

D - Provide a means of producing overall project cost estimates
Option D is incorrect as cost estimates are developed through cost management, not the purpose of life cycle phases.

APM emphasizes that phases organize work for manageability, with cost estimates produced within phases, not as their primary goal.

This option is too specific, as breaking work into controllable blocks (Option A) is the broader purpose of the life cycle structure.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 29 Choose 1
How can the project manager ensure a sound stakeholder environment?
Show answerHide answer

Correct answer: C Develop ways of understanding the needs of stakeholders.

Explanation

Summary
A sound stakeholder environment fosters collaboration and alignment with project goals through effective stakeholder management. Understanding stakeholders’ needs ensures their concerns are addressed, promoting engagement and support. Option C is correct, as developing ways to understand stakeholder needs is fundamental to building a positive environment, per APM’s framework. Other options, like excluding stakeholders or reducing influence, are counterproductive, while fully satisfying all needs is often unrealistic.

Correct Option:

C - Develop ways of understanding the needs of stakeholders
Option C is correct as understanding stakeholder needs is key to a sound stakeholder environment.

APM’s framework emphasizes analyzing stakeholder expectations to tailor communication and engagement strategies.

This approach builds trust, aligns stakeholders with project objectives, and mitigates conflicts, ensuring a collaborative environment. By identifying needs through tools like stakeholder analysis, the project manager fosters support and effective involvement.

Incorrect Option:

A - Ensure that stakeholders who oppose the project are not involved
Option A is incorrect as excluding opposing stakeholders can escalate conflicts and undermine project support.

APM advocates engaging all stakeholders, including detractors, to address concerns and gain buy-in.

Exclusion risks alienating key influencers, destabilizing the stakeholder environment, unlike Option C, which promotes understanding needs to create a collaborative and inclusive environment for project success.

B - Develop an environment where all stakeholder's needs are satisfied
Option B is incorrect as satisfying all stakeholder needs is often unrealistic due to conflicting priorities.

APM’s guidance focuses on managing, not fully satisfying, stakeholder needs through engagement and compromise.

Prioritizing understanding needs (Option C) is more practical, enabling tailored strategies to balance interests and maintain a sound environment, rather than attempting an unfeasible goal of total satisfaction.

D - Ensure that the influence stakeholders have is reduced
Option D is incorrect as reducing stakeholder influence can harm engagement and project support.

APM emphasizes leveraging stakeholder influence through effective management to align with project goals.

Understanding needs (Option C) enables the project manager to work with influential stakeholders constructively, fostering a positive environment, rather than diminishing their role, which could lead to resistance or disengagement.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Question 30 Choose 1
Which of the following can be adjusted in a timebox situation?
Show answerHide answer

Correct answer: C Scope and quality.

Explanation

Summary
In a timebox situation, the deadline and duration are fixed, requiring adjustments to other elements to meet project goals within the set timeframe. Scope and quality can be adjusted to fit the time constraints, ensuring delivery within the timebox. Option C is correct, as APM’s framework for timeboxing, often used in agile approaches, prioritizes flexibility in scope and quality over fixed deadlines, unlike the other options.

Correct Option:

C - Scope and quality
Option C is correct as timeboxing fixes the deadline and duration, allowing adjustments to scope and quality.

APM’s guidance on agile methods notes that timeboxes prioritize delivering within set timeframes by varying scope (e.g., reducing deliverables) or quality (e.g., accepting minimal viable products).

This flexibility ensures timely delivery while maintaining alignment with project objectives, unlike fixed elements like time or budget.

Incorrect Option:

A - Deadline and duration
Option A is incorrect as timeboxing fixes the deadline and duration, making them non-adjustable.

APM emphasizes that timeboxes enforce strict time constraints to drive efficiency, with scope or quality adjusted instead.

Changing deadlines or duration contradicts the timebox approach, making this option invalid compared to Option C, which correctly identifies adjustable elements.

B - Time and cost
Option B is incorrect because time is fixed in a timebox, and cost is often constrained or secondary.

APM’s framework highlights that timeboxes prioritize fixed schedules, with scope and quality adjusted to fit.

Adjusting time undermines the timebox’s purpose, and cost adjustments are less common, making Option C’s focus on scope and quality more accurate.

D - Budget and resources
Option D is incorrect as budget and resources are typically constrained in timeboxing, not the primary adjustable elements.

APM notes that timeboxes focus on delivering within fixed timeframes by varying scope or quality, not budget or resources.

Adjusting these is secondary and less flexible, making Option C’s emphasis on scope and quality the correct choice for timebox adjustments.

Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/
Full mock exam

Sit the APM-PFQ exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real APM-PFQ exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.