Show answerHide answer
Correct answer: D record of risks, their impact and the actions taken to manage them.
Explanation
SummaryA risk register is a tool used in project management to document and manage risks throughout the project lifecycle. It records details of identified risks, their potential impact, and the actions taken to mitigate or manage them. Option D is correct, as it accurately describes the risk register’s purpose as a comprehensive record of risks, their impacts, and management actions, aligning with APM’s risk management framework.
Correct Option:
D - Record of risks, their impact and the actions taken to manage them
Option D is correct as the risk register serves as a centralized document capturing identified risks, their potential impacts, and mitigation actions.
APM’s framework emphasizes that it tracks risk details, including probability, impact, and response strategies, to support effective risk management.
This ensures stakeholders have a clear overview of risks and actions, facilitating proactive management throughout the project lifecycle.
Incorrect Option:
A - Structured process for risk identification
Option A is incorrect as the risk register is not a process but a tool for recording risks.
APM notes that risk identification is part of the risk management process, while the register documents the outcomes.
It captures risks after identification, not the process itself, making this option less accurate than Option D, which correctly defines the register’s purpose.
B - Record of the ownership of risk and issue management actions
Option B is incorrect as it focuses only on ownership, which is just one element of the risk register.
APM’s guidance states that the register includes risks, impacts, and actions, not just ownership details.
While ownership is recorded, the primary purpose is broader, making Option D’s comprehensive description of risks, impacts, and actions more accurate.
C - Means of assessing the likelihood and impact of all of the risks
Option C is incorrect as the risk register records assessments, not performs them.
APM emphasizes that likelihood and impact assessments occur during risk analysis, with results documented in the register.
The register’s purpose is to store this information, not to conduct assessments, making Option D’s focus on recording risks, impacts, and actions the correct choice.
Reference:
Association for Project Management (APM). Project Management Qualification (PMQ) Study Guide. Available at: https://www.apm.org.uk/qualifications-and-training/project-management-qualification/