Show answerHide answer
Correct answer: A Planned communication will help to establish the level of interest and power a stakeholder is likely to possess.
Explanation
Summary:Effective stakeholder engagement relies on understanding each stakeholder's characteristics to tailor communication appropriately. A key part of stakeholder analysis is assessing their level of interest in the project and their power to influence its outcome. Planned communication is not just about sending information; it is a tool to both gather and validate this critical information, which in turn refines the engagement strategy.
Correct Option:
A. Planned communication will help to establish the level of interest and power a stakeholder is likely to possess.
This is correct. Initial communication is a primary method for identifying and analyzing stakeholders. Through planned interactions like interviews and workshops, the project manager can gauge a stakeholder's actual level of interest and influence, moving beyond initial assumptions to a more accurate understanding.
Incorrect Option:
B. Planned communication will increase the number of stakeholders who are likely to have an interest in the project.
Communication raises awareness, but it does not create a genuine "interest" where none existed. The stakeholder community is defined by those who are affected by or can affect the project, not simply by who is aware of it.
C. Planned communication will reduce the power of stakeholders who are likely to have an interest in the project.
Communication is a tool for influence and management, not for diminishing a stakeholder's inherent power (e.g., their authority, budget control, or legal standing). Its goal is to manage the impact of that power, not reduce it.
D. Planned communication is likely to reduce the number of valid stakeholders who have an interest in the project.
The opposite is often true. Effective communication can help identify more stakeholders who were previously unknown. It does not make valid stakeholders invalid; it ensures all relevant parties are properly recognized and managed.
Reference:
APM Body of Knowledge 7th Edition, Section 2.4 (Stakeholder Management). It describes the process of identifying stakeholders and understanding their interests and influence, which is achieved through planned communication and engagement activities.