Correct answer: C Mandatory
Explanation
Explanation:This scenario describes a Mandatory dependency, also known as a hard logic or inherent dependency. This type of dependency is inherent in the nature of the work itself and is physically or legally required.
Why C is correct: The software installation is physically impossible to perform until the desktops (the hardware it runs on) are installed and powered on. This is not a matter of preference or best practice; it is a mandatory, unavoidable sequence of events. You cannot install software on a computer that does not exist or is not operational.
Detailed Analysis of Incorrect Options:
A. External:
An external dependency involves a relationship between a project task and a factor outside the project team's direct control (e.g., a delivery from a vendor, a permit from a government agency). In this case, both the desktop installation and the software installation are tasks within the project's scope and under the team's control.
B. Internal:
An internal dependency is a relationship between two project tasks, both of which are under the project team's control. While this scenario is an internal dependency, the question is asking for the type of logical relationship. "Mandatory" is a more specific and accurate description of the nature of the dependency (it's required), whereas "Internal" simply describes who controls it. "Mandatory" is the best fit.
D. Discretionary:
A discretionary dependency (or preferred logic) is defined by the project team based on best practices, established procedures, or preference. For example, the team might decide to run all unit tests before integration tests as a matter of policy, even though it's not physically mandatory. The dependency described in the question is not discretionary; it is absolutely required.
References:
CompTIA Project+ PK0-005 Exam Objectives:
This question falls under Domain 2.0 "Project Life Cycle Phases," specifically within the scheduling and sequencing of activities. Understanding dependency types is crucial for developing a realistic project schedule.
PMBOK® Guide / Schedule Management: Dependencies are categorized into four types:
Mandatory (Hard Logic): Inherent in the nature of the work.
Discretionary (Soft Logic): Defined by the project team.
External: Involves a relationship between project and non-project activities.
Internal: Involves a precedence relationship between project activities. The given scenario is a classic example of a Mandatory dependency.