Which of the following best describes the team's performance?
Show answerHide answer
Correct answer: A The team needs to adjust the planned work based on results.
Explanation
Explanation:The chart reveals a consistent and significant pattern: the planned work (orange line) remains relatively high and stable across all sprints, while the actual work completed (blue line) is consistently and substantially lower. This indicates a persistent planning problem. The team is consistently committing to more work than it can deliver. The most logical and necessary action is for the team to use its historical actual performance (its true velocity) to adjust future sprint commitments, bringing the planned work in line with what is realistically achievable.
Detailed Analysis of Incorrect Options:
B. The team’s velocity is getting better.
This is incorrect. While the actual work completed (blue line) shows some minor fluctuations, there is no clear, sustained upward trend indicating that velocity is improving. It remains consistently below the planned work without closing the gap over time.
C. The team understands its velocity and is planning in an accurate manner.
This is the opposite of what the chart shows. Accurate planning would result in the orange (planned) and blue (actual) lines being very close together. The large, consistent gap demonstrates that the team does not understand its velocity and is planning in an inaccurate, overly optimistic manner.
D. The team is doing more work than planned.
This is factually false based on the chart. The blue line (actual work) is consistently below the orange line (planned work), meaning the team is consistently completing less work than planned.
References:
1.CompTIA Project+ PK0-005 Exam Objectives:
This question tests knowledge from Domain 1.0 "Project Management Concepts," specifically Agile principles and metrics like velocity, and Domain 4.0 "Project Tools and Documentation," relating to using burndown/burnup charts for performance analysis.
2.Agile/Scrum Principles:
A core tenet of Agile is using past performance to inform future planning. The chart is a classic example of a team failing to do this. The recommended action (Answer A) is to conduct a sprint retrospective, analyze the cause of the consistent over-commitment, and use the average of the actual work completed (blue line) as a baseline for committing to work in future sprints.