Question 1 Choose 1

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

Show answerHide answer

Correct answer: C

Explanation

Option C shows a graph that most likely represents the observed relationship in this scenario. The graph shows a learning curve, which is a graphical representation of the relationship between a learner’s performance on a task and the number of attempts or time required to complete the task. The learning curve theory proposes that a learner’s efficiency in a task improves over time the more the learner performs the task. In this case, the IT intern was able to complete more set-ups in less time as they gained more experience and proficiency over the two-week rotation12

Question 2 Choose 1

Given the information in the chart,

which of the following techniques should the project manager use to improve the project schedule in Sprint 1?

Show answerHide answer

Correct answer: B Crashing

Explanation

Crashing is the correct answer because the burndown chart shows that, during Sprint 1, the actual remaining work is above the planned line. This means the team is behind the expected schedule and has completed fewer user stories than planned. Crashing is a schedule compression technique used when a project manager needs to shorten the schedule by adding resources, increasing effort, or applying additional support to critical work. Validating is used to confirm that deliverables meet acceptance criteria, but it does not directly improve the schedule. Training may improve team capability over time, but it is not the immediate schedule compression technique shown by the scenario. Avoiding is a risk response strategy and does not address schedule recovery.

Question 3 Choose 1

Which of the following can be inferred?

Show answerHide answer

Correct answer: C Task B needs to be finished before task C starts.

Explanation

The only option that can be reliably inferred in a typical project chart/diagram context (e.g., a network diagram or dependency view) is a dependency relationship—specifically that Task B must finish before Task C can start (a Finish-to-Start relationship). In CompTIA Project+ objectives, dependency management is a core scheduling concept: identifying predecessors/successors and understanding how sequencing drives the schedule. Inference about task ordering is exactly what dependency visuals are designed to communicate.

The other options require information that is not inherently inferable without additional data. “Completed on time” (A) would require schedule baseline vs. forecast/critical path analysis. “Task D must be reworked” (B) would require quality/validation results or defect/issue information. “Over budget and behind schedule” (D) would require performance metrics such as EVM or cost/schedule variance and cannot be concluded solely from a dependency relationship.

So, the best inference is the sequencing rule: B must be completed before C begins, which is a fundamental scheduling/dependency concept emphasized in Project+ planning and schedule control practices.

Question 4 Choose 1

An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?

Show answerHide answer

Correct answer: C Request the developer provide justification.

Explanation

The project manager should first request justification from the developer because the invoice must be validated before approval, rejection, or escalation. In project procurement and vendor management, invoices should be checked against assigned work, timesheets, deliverables, contract terms, purchase orders, and approvals. Since no tasks were assigned, there may be an error, unrecorded work, emergency support, misunderstanding, or unauthorized billing. Asking for justification creates a factual basis for the next decision and protects the project from paying unsupported costs. Declining the invoice immediately may be premature if legitimate work was performed but not properly documented. Escalating to the steering committee should occur only after initial verification fails or a material dispute exists. Consulting other developers is indirect and less appropriate as the first step.

That's the last free question in Project Management Concepts

You've seen the free 30% (4 of 15 questions). Full access unlocks every question and full-length PK0-005 mock exams (90 questions, 90 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PK0-005 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PK0-005 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PK0-005 mock exam
  • 90questions per mock
  • 90 mintime limit
  • 460questions in the bank
  • Newmock on every attempt