Question 1 Choose 1

During a steering committee meeting, members of the meeting decide to implement several proposed suggestions. Which of the following documents should be updated first as a result of this decision?

Show answerHide answer

Correct answer: C Change log

Explanation

The change log should be updated first because the steering committee has decided to implement proposed suggestions, which means approved or pending changes must be formally recorded. A change log provides traceability for change requests, approvals, impacts, implementation status, owners, and dates. Updating it first ensures the project has an auditable record before related project documents are revised. The Gantt chart may need updates later if the changes affect schedule activities or milestones. The task board may also be revised if team work items change. The risk log is used for uncertain future events, not approved scope or execution changes. Proper change documentation supports governance, prevents confusion, and helps stakeholders understand why the project plan, schedule, budget, or scope may be adjusted.

That's the last free question in Tools and Documentation

You've seen the free 30% (1 of 2 questions). Full access unlocks every question and full-length PK0-005 mock exams (90 questions, 90 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PK0-005 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PK0-005 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PK0-005 mock exam
  • 90questions per mock
  • 90 mintime limit
  • 460questions in the bank
  • Newmock on every attempt