Correct answer: B Perform an impact analysis.
Explanation
Explanation:When the project manager discovers that required resources are available for fewer hours than planned, this will affect the project schedule. Before making any changes to the project plan, the project manager must first analyze the impact of the issue.
An impact analysis helps determine:
How the schedule will be affected
Whether cost or scope will change
What alternative solutions might exist (e.g., reallocating resources, adjusting timelines)
This analysis provides the information needed to decide the best corrective action and to support any formal change request if necessary.
Why the Other Options Are Incorrect
A. Add a new risk
While the issue might become a risk, adding a risk does not address the immediate scheduling problem.
C. Escalate to the sponsor
Escalation should occur only after the project manager has analyzed the impact and identified possible solutions.
D. Raise a change request
A change request may eventually be needed, but the project manager should first perform an impact analysis to justify any change.
Reference
CompTIA Project+ PK0-005 – Change Management / Schedule Management