The following extract from a decision tree has been prepared for a decision that is to be made to choose between options P, Q and R.
What is the maximum expected value of profit at decision point Z?
Show answerHide answer
Correct answer: A$4 million
Question 72Choose 1
When classifying quality costs, which of the following is NOT likely to be an appraisal cost?
Show answerHide answer
Correct answer: ACost of product liability insurance
Question 73Choose 1
A company is considering the use of Material V in a special order.
The material is used regularly and a sufficient quantity of the material is in inventory. It could also be sold, at just below the current market price, to a local competitor.
What is the relevant cost of Material V to be used in the special contract?
Show answerHide answer
Correct answer: AThe replacement cost of the material.
Question 74Choose 1
A manager is deciding which one of four services to provide next period.
The contribution earned by each service will depend on the weather conditions as follows.
Using the maximin criterion, which service will the manager provide?
Show answerHide answer
Correct answer: DService S
Question 75Choose 1
A clinic offers two types of procedure, A and B.
The clinic uses activity-based costing. The general facility overhead cost for next year is budgeted to be $8,601,600. The cost driver is the length of patient stay.
Additional data:
What is the general facility overhead cost for each Procedure B?
Show answerHide answer
Correct answer: B$3,072
Question 76
A company currently uses a rate of $32 per machine hour to absorb its total production overheads of $960,000.
Using this system the production overhead cost per unit of product X is $160.
An activity based costing exercise has revealed that only $345,000 of the production overhead is driven by machine hours. The remainder is driven by the number of machine set ups, at a rate of $9.60 per set up. Product X requires 3 set ups per unit.
Calculate the total production overhead cost per unit of product X using an activity based costing system.
Give your answer to two decimal places.
Show answerHide answer
Explanation
Answer: $86.30
Question 77Choose 1
ABC uses an activity-based costing system.
The company manufactures three products, details of which are given below:
Total material movement costs for the period are $10,000.
The material movement cost per unit for Product Z (to the nearest $0.01) is:
Show answerHide answer
Correct answer: A$10.67
Question 78Choose 2
Petco's material price standard was £8 per kg.
When looking over their accounts you calculate that in fact they they purchased 2,000kg at £6 per kg due to an overly abundant harvest that lowered global pet food prices.
You have been asked by your manager to analyse these figures and come to a conclusion. With that in mind which of the following statements are correct? Select ALL that apply.
Show answerHide answer
Correct answer: B, DThe material price planning variance is £4,000
Management had no control over this variance
That's the last free question
You've seen the free 30% (78 of 260 questions). Full access unlocks every question and full-length P1 mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real P1 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.