A company manufactures a single product. The company absorbs fixed production overhead using a pre-determined rate per unit. The following data applies for month 7:
During month 7 fixed production overhead was over absorbed by $40,000. What was the actual number of units produced during month 7?
Show answerHide answer
Correct answer: A16,000
Question 42Choose 1
A decision maker that makes decisions using the minimax regret criterion would be classified as:
Show answerHide answer
Correct answer: ARisk averse
Question 43Choose 1
A company's markets are affected by fluctuating exchange rates. It is difficult to forecast more than two or three months ahead.
Which of the following budgeting systems would be most useful in this company's circumstances?
Show answerHide answer
Correct answer: ARolling budgets
Question 44Choose 1
Which of the following would cause an adverse fixed overhead volume variance?
Show answerHide answer
Correct answer: BActual output was lower than budgeted
Question 45Choose 1
Information about a company's only two products is as follows:
The revenue from the products must be in the constant mix of 2U:3V. Budgeted monthly sales revenue is $110,000.
Fixed costs are $23,095 each month.
To the nearest $10, what is the budgeted monthly margin of safety in terms of sales revenue?
Show answerHide answer
Correct answer: A$35,500
Question 46Choose 1
Which of the following statements about relevant costs is correct?
Show answerHide answer
Correct answer: CRelevant costs may not be used in external profit reporting because they do not adhere to the accruals basis of accounting.
Question 47Choose 2
Explain why sensitivity analysis is useful when dealing with uncertainty in project appraisal.
Select all the true statements.
Show answerHide answer
Correct answer: B, CSensitivity analysis enables a company to determine the effect of changes to variables on the planned outcomeIn project appraisal, an analysis can be made if all the key variables to ascertain by how much variable would need to change before the net present value (NPV) reaches zero i.e. the indifference point.
Question 48Choose 3
TP makes wedding cakes that are sold to specialist retail outlets which decorate the cakes according to the customers’ specific requirements. The standard cost per unit of its most popular cake is as follows:
The general market prices at the time of purchase for Ingredient A and Ingredient B were
$23 per kg and $20 per kg respectively. TP operates a JIT purchasing system for ingredients and a JIT production system; therefore, there was no inventory during the period.
Discuss the usefulness of the planning and operational variances calculated for TP’s management.
Select ALL the TRUE statements.
Show answerHide answer
Correct answer: A, C, EThe use of planning and operational variances will enable TP’s management to draw a distinction between variances caused by factors extraneous to the business and planning errors (planning variances) and variances caused by factors that are within the control of management (operational variances).If planning and operational variances are not distinguished, there is potential for dysfunctional behavior especially where the manager has been operating efficiently and performance is being judged by factors outside the manager’s control. In the case of TP it became evident during the period that the prevailing market prices for materials were significantly less than those set during the budget process.Standards that failed to anticipate known market trends when they were set will reflect faulty standard setting.
Question 49Choose 1
Traditional absorption costing is more suitable than activity-based costing when:
Show answerHide answer
Correct answer: Doverheads are small in comparison to direct costs.
Question 50Choose 1
A company manufactures headphones.
70% of production costs are prime costs. Production overhead costs are driven by the number of headphones produced.
Which costing system would be most appropriate for product profitablilty analysis?
Show answerHide answer
Correct answer: AAbsorption costing