Question 31
The following information is available about direct material T for the last period.

A JIT purchasing system is in operation.

Calculate the actual price paid per kg of material T. Give your answer to 2 decimal places.
Show answerHide answer

Explanation

Answer: $2.80
Question 32
The following 5 statements apply the principles of either, both or neither absorption costing and marginal costing.

Place the option labels against the relevant statements.

Show answerHide answer

Explanation

Question 33 Choose 1
The simplex method has been used to determine the optimum output of products P, Q, R and S with constraints on resources J, K and L.

In the final simplex tableau, the figure in the product R row and the column for slack variable K is 80.

Which of the following statements is correct?
Show answerHide answer

Correct answer: B For each additional unit of resource K available, the output of product R would increase by 80 units.

Question 34 Choose 4
RFT, an engineering company, has been asked to provide a quotation for a contract to build a new engine. The potential customer is not a current customer of RFT, but the directors of RFT are keen to try and win the contract as they believe that this may lead to more contracts in the future. As a result, they intend pricing the contract using relevant costs. The following information has been obtained from a two-hour meeting that the Production Director of RFT had with the potential customer. The Production Director is paid an annual salary equivalent to $1,200 per 8-hour day. 110 square meters of material A will be required. This is a material that is regularly used by RFT and there are 200 square meters currently in inventory. These were bought at a cost of $12 per square meter. They have a resale value of $10.50 per square meter and their current replacement cost is $12.50 per square meter. 30 liters of material B will be required. This material will have to be purchased for the contract because it is not otherwise used by RFT. The minimum order quantity from the supplier is 40 liters at a cost of $9 per liter. RFT does not expect to have any use for any of this material that remains after this contract is completed. 60 components will be required. These will be purchased from HY. The purchase price is $50 per component. A total of 235 direct labour hours will be required. The current wage rate for the appropriate grade of direct labour is $11 per hour. Currently RFT has 75 direct labour hours of spare capacity at this grade that is being paid under a guaranteed wage agreement. The additional hours would need to be obtained by either (i) overtime at a total cost of $14 per hour; or (ii) recruiting temporary staff at a cost of $12 per hour. However, if temporary staff are used they will not be as experienced as RFT’s existing workers and will require 10 hours supervision by an existing supervisor who would be paid overtime at a cost of $18 per hour for this work. 25 machine hours will be required. The machine to be used is already leased for a weekly leasing cost of $600. It has a capacity of 40 hours per week. The machine has sufficient available capacity for the contract to be completed. The variable running cost of the machine is $7 per hour. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.

Select ALL the true statements.
Show answerHide answer

Correct answer: B, C, D, G Material A was a relevant cost.Material B was a relevant cost.The components are to be purchased from HY at a cost of $50 each. This is a relevant cost because it is future expenditure that will be incurred as a result of the work being undertaken.The relevant cost is $7010

Question 35 Choose 3
Which THREE of the following are functional budgets?
Show answerHide answer

Correct answer: A, B, C Human resource budget Sales budget Research and development budget

Question 36 Choose 1
You are a trainee management accountant working for a prestigious manufacturing firm. One day you go to a business meeting a business meeting and the managing director is there. They stand up and say that the company is losing too much money through wastage and losses and so they have decided to implement a total quality management system. They go on to say this system will:
1:Allow the company to improve on a consistent and continual basis
2:Allow the company to identify and allocate quality accountability to certain departments
3:Help the company detect error and fraud Are ALL of these statements correct?
Show answerHide answer

Correct answer: A No. (2) is incorrect No. (1) is incorrect

Question 37 Choose 1
A company is preparing its annual budget and is estimating the number of units of Product W that it will sell in each quarter of year 2. Past experience has shown that the trend for sales of the product is represented by the following relationship:

Calculate the expected unit sales of Product W for each quarter of year 2, after adjusting for seasonal variations using the multiplicative model.
Show answerHide answer

Correct answer: A The sales forecast for year 2 Quarter 4 = 35,100 units

Question 38 Choose 4
Explain THREE benefits that organizations gain from using budgetary planning and control systems. Select ALL the true statements.
Show answerHide answer

Correct answer: B, D, E, G Budgeting forces an organization’s management to look ahead and set performance targets. The budget ensures actions of different parts of the organization are coordinated are reconciled otherwise managers take actions for the benefit of their own part of organization that may not benefit the organization as a whole. Another benefit of budgeting is to set targets to motivate managers and optimize their performance. It provides a standard which managers may be motivated to achieve. It can also encourage inefficiency and conflict between managers particularly if the budget is imposed from above, whereby it may act as a threat rather than as a challenge.

Question 39 Choose 2
QR uses an activity based budgeting (ABB) system to budget product costs. It manufactures two products, product Q and product R. The budget details for these two products for the forthcoming period are as follows:

The total budgeted cost of setting up the machines is $74,400.

Select TWO potential benefits of using an activity based budgeting system.
Show answerHide answer

Correct answer: A, D Activity based budgeting allows the ranking of activities and the determination of how limited resources should be allocated across competing activities.Activity based budgeting allows the identification of value added and non-value added activity and ensures that any budget cuts are made to non-value added activities.

Question 40 Choose 2
Which of the following are examples of feedforward control? Select ALL that apply.
Show answerHide answer

Correct answer: B, C The sales volume for the next quarter is forecast and compared with the planned volume. If there is a forecast shortfall action is taken to correct the difference. A target is set for the cash balance at the period end. The balance shown in the cash forecast is compared with the target and action is taken to ensure that the target balance is achieved.

Full mock exam

Sit the P1 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real P1 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full P1 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 260questions in the bank
  • Newmock on every attempt