A company produces trays of pre-prepared meals that are sold to restaurants and food retailers. Three varieties of meals are sold: economy, premium and deluxe.
Calculate, for the original budget, the budgeted fixed overhead costs, the budgeted variable overhead cost per tray and the budgeted total overheads costs.
Show answerHide answer
Correct answer: BThe variable cost per tray = $0.65; The fixed cost = $ 550 000
Question 52Choose 1
Company X is deciding which of Projects A, B or C to undertake. The profit earned from each of the projects is dependent on economic conditions.
The table below details the profit for each of the possible outcomes and the expected value of each of the projects.
What is the maximum amount that should be paid for perfect information about the economic conditions?
Show answerHide answer
Correct answer: C$54.50
Question 53Choose 1
PL currently earns an annual contribution of $2,880,000 from the sale of 90,000 units of product B. Fixed costs are $800,000 per annum.
The management of PL is considering reducing the selling price per unit to $48. The estimated levels of demand at the revised selling price and the probabilities of them occurring are as follows:
Calculate the probability that the profit will increase from its current level if the selling price is reduced to $48.
Show answerHide answer
Correct answer: AThe probability therefore that the contribution will exceed $2,880,000 is 90%.
Question 54Choose 1
Changing to a just-in-time, from a traditional, manufacturing environment can affect cost accounting systems.
Which of the following statements is correct?
Show answerHide answer
Correct answer: CMore frequent, smaller deliveries from suppliers must be recorded
Question 55Choose 1
A special contract requires 640 units of component T.
The inventory of 280 units of component T cost $0.20 per unit but the component is not currently used by the company.
The current market price of component T is $0.24 per unit but the inventory could be sold for $0.15 per unit.
The relevant cost of the units of component T required for the special contract is:
Show answerHide answer
Correct answer: B$128.40
Question 56Choose 3
Which of the following statements about total quality management are incorrect? Select ALL that apply.
Show answerHide answer
Correct answer: D, E, FThere is an acceptable quality level that an organisation must try to achieve.The costs of conformance are more important than the costs of non-conformance.The organisation should rely on inspection to achieve quality standards.
Question 57
TDM edits, prints and publishes three magazines, Mag A, Mag B and Mag C. The company operates an activity-based costing system.
The following information has been obtained.
What is the overhead cost attributable for each Mag A publication? Give your answer to the nearest whole cent.
Show answerHide answer
Explanation
Answer: 83 cents
Question 58
Place the correct label against each item to categorise the cost of the item within the quality cost framework.
Show answerHide answer
Explanation
Question 59Choose 1
Company LGF seeks to maximize profits and has a 'risk seeker' attitude when making decisions. The company has to choose between mutually exclusive projects. A range of possible profit outcomes has been estimated for each project along with their associated probabilities.
Company LGF would choose the project with the:
Show answerHide answer
Correct answer: ABest possible outcome irrespective of the standard deviation.
Question 60Choose 3
XY, a not-for-profit charity organization which is funded by public donations, is concerned that it is not making the best use of its available funds. It has carried out a review of its budgeting system and is considering replacing the current system with a zero-based budgeting system.
Select ALL the potential advantages AND disadvantages for the charity of a zero-based budgeting system.
Show answerHide answer
Correct answer: A, C, DIt avoids the complacency inherent in the traditional incremental approach where it is assumed that future activities will be very similar to current ones.Preparation of the decision packages will normally require the environment of many employees. This environment may produce useful ideas and promote job satisfaction.The creation of decision packages and their subsequent ranking by top management is very time consuming and costly. The charity will need to assess whether the benefits of the system outweigh the costs involved.