Correct answer: A The Letter of Tender may be worded by the Contractor (at its discretion) so as to allow for the alternative of the Contract to become effective when the Employer issues a Letter of Acceptance.
Certified Contract Manager
Free CCM mock exam questions 41–42, each with the answer and an explanation.
20 questions · 30 minutes · free, no sign-up
Correct answer: A The Letter of Tender may be worded by the Contractor (at its discretion) so as to allow for the alternative of the Contract to become effective when the Employer issues a Letter of Acceptance.
Correct answer: B 42 days
You've seen the free 30% (42 of 140 questions). Full access unlocks every question and full-length CCM mock exams, a different mock on every attempt.