Correct answer: A
Yes, but Contractor will do so on its own risk.
Explanation
Explanation:
Sub-Clause 8.1 [Commencement of Works] of the FIDIC Yellow Book and Silver Book (1999) states that the Contractor "shall commence the design and execution of the Works as soon as is reasonably practicable after the Commencement Date," and shall then proceed with due expedition and without delay. Critically, Clause 8 does not contain any express prohibition against the Contractor beginning design activities before the Commencement Date.
Since the Commencement Date is the contractual trigger point from which the Time for Completion starts running, and from which the Contractor's formal contractual obligations to proceed with design and execution are measured, there is nothing in the Contract preventing the Contractor from getting a head start on design work earlier, for example, to manage its own internal resource planning or to try to build in float or buffer.
If the Contractor chooses to do so:
It does so entirely at its own risk and cost. There is no contractual obligation on the Employer to recognize, pay for, or give credit for any work, design or otherwise, carried out before the Commencement Date.
If, for example, the Employer's Requirements or design basis subsequently change, via Variation or otherwise, before the official Commencement Date, any early design work done by the Contractor that becomes redundant or must be reworked is the Contractor's own loss. It cannot claim additional time or cost for abortive early design work.
The Contractor also bears the risk that formal access, third-party permits, or other preconditions for effective design or execution may not yet be in place before the Commencement Date.
Why the others are incorrect:
B. Incorrect:
This conflates design with execution, meaning physical works on Site. Even if early design work were tolerated at the Contractor's own risk, actual physical execution of the Works before the Commencement Date would typically not be practical or permitted, since the Contractor generally has no right of access to the Site under Sub-Clause 2.1 until the relevant access arrangements are available. Mobilization, insurance, and security arrangements may also be tied to the contractual commencement framework.
C. Incorrect:
Clause 8 does not contain an express prohibition on early design work. It establishes when the Contractor's formal obligation to commence begins, rather than creating a general bar on voluntary early preparatory design activity.
D. Incorrect:
This reverses the risk allocation. Any early design work undertaken by the Contractor before the Commencement Date is at the Contractor's own risk, not the Employer's, since it falls outside the formal contractual timeline for commencement.
Reference:
FIDIC Conditions of Contract for Plant and Design-Build ("Yellow Book"), 1999 Edition, Sub-Clause 8.1 [Commencement of Works].
FIDIC Conditions of Contract for EPC/Turnkey Projects ("Silver Book"), 1999 Edition, Sub-Clause 8.1 [Commencement of Works].
Sub-Clause 2.1 [Right of Access to the Site].