Question 21 Choose 1
In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?
Show answerHide answer

Correct answer: B False

Explanation

Explanation

Contractual Basis: Under FIDIC Silver Book 1999 (Sub-Clause 8.6 – Rate of Progress), if the progress of the Works falls behind the programme or is deemed too slow to complete within the Time for Completion, the Employer (or the Employer's Representative) may instruct the Contractor to submit a revised programme showing the steps adopted to expedite progress.

Why the statement is False: The Contractor is only entitled to recover additional costs for complying with a Sub-Clause 8.6 instruction if the underlying reason for the slow progress (and the need for acceleration) is not due to a cause for which the Contractor is responsible (e.g., if it was caused by an Employer's risk or variation). Conversely, if the delay is the Contractor's fault, the Contractor must bear all their own costs of complying with the instruction to expedite.

Furthermore, the Employer's right to claim additional costs from the Contractor for the Contractor's failure to maintain adequate progress usually stems from delay damages (Liquidated Damages) or specific default provisions, rather than a blanket rule that the Employer can claim costs for an unachievable revised programme.
Question 22 Choose 2
There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances. Which two of the following statements are NOT applicable reasons? (Choose all correct answers — multiple possibilities)
Show answerHide answer

Correct answer: B, D Decrease the Contract PriceIncrease the performance of the Works when completed

Explanation

Explanation:

Why B and D are NOT applicable reasons

The FIDIC Red Book (1999 Edition), Sub-Clause 8.3 [Programme], requires each Party to advise the other and the Engineer in advance of any known or probable future events or circumstances which may:

Adversely affect the work of the Contractor's Personnel
Adversely affect the performance of the Works when completed
Increase the Contract Price
Delay the execution of the Works or a Section

Option B ("Decrease the Contract Price") is NOT an applicable reason because Sub-Clause 8.3 specifically addresses events that could increase the Contract Price (i.e., events that might result in additional costs), not decrease it.

Option D ("Increase the performance of the Works when completed") is NOT an applicable reason because the actual Sub-Clause 8.3 language refers to events that may "adversely affect the performance of the Works when completed" — meaning events that could degrade or harm the final performance, not events that could improve or increase performance.

Why A and C ARE applicable reasons

Option A ("Delay the execution of the Works or a Section") directly mirrors Sub-Clause 8.3(d), which requires advance notice of events that may "delay the execution of the Works or a Section (if any)".

Option C ("Adversely affect the work of the Contractor's Personnel") directly mirrors Sub-Clause 8.3(a), which requires advance notice of events that may "adversely affect the work of the Contractor's Personnel".

Reference

FIDIC Red Book (1999 Edition), Sub-Clause 8.3 [Programme]: "Each Party shall advise the other and the Engineer, in advance of any known or probable future events or circumstances which may (a) adversely affect the work of the Contractor's Personnel; (b) adversely affect the performance of the Works when completed; (c) increase the Contract Price; and/or (d) delay the execution of the Works or a Section (if any)."
Question 23 Choose 2
Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme? Choose all of the correct answers (multiple possibilities)
Show answerHide answer

Correct answer: B, C The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).The sequence and timing of the remedial work.

Explanation

Explanation

B. Correct: Under FIDIC 2017 Red and Yellow Books (Sub-Clause 8.3 - Programme), a revised programme must explicitly show the actual progress achieved to date on each activity, any delays that have occurred, and the resulting effects of those delays on the sequence and timing of remaining activities.

C. Correct: Sub-Clause 8.3 also requires that when a revised programme is submitted, such as after instructions for variations, remedial work, or delays, it must outline the sequence and timing of any remedial or additional work required to complete the Works.

Why the other options are incorrect:

A. Incorrect: While holidays and working hours are part of the general programming information, "internationally recognized holiday periods" as a blanket term are not specifically or uniquely mandated as a standalone element to be added to a revised programme under the text of Sub-Clause 8.3. Local statutory holidays and planned non-working days are what get factored into working schedules.

D. Incorrect: A revised programme must detail the delivery dates of relevant Plant and Materials and provide a comprehensive update of the remaining workflow. It is therefore incorrect to limit this requirement to only the delivery dates of Plant and Materials that have not yet been delivered.
Question 24 Choose 2
(Which of the following types of insurances belong to the basic (typical) scope of insurances? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).)
Show answerHide answer

Correct answer: A, C Injury to persons and damage to propertyInsurance of Goods and other things brought to Site

Explanation

Explanation

A. Injury to persons and damage to property — Correct: The Contractor is required to obtain insurance covering liability for loss, damage, death, or bodily injury to third parties/persons and damage to property, subject to the exclusions and requirements of the Contract. This is a standard and fundamental category of construction-project insurance.

C. Insurance of Goods and other things brought to Site — Correct: The Contractor is also required to insure Goods and other things brought to the Site for incorporation into the Works, as well as relevant Contractor's Equipment and other items, as specified by the Contract. Therefore, this belongs to the typical/basic insurance scope.

Why B is incorrect:
Force Majeure Insurance is not a standard/basic insurance category under the FIDIC 2017 insurance provisions. Events covered by Exceptional Events, the 2017 terminology replacing "Force Majeure", are dealt with contractually under Sub-Clause 18 [Exceptional Events]. The Contract does not establish a general requirement called "Force Majeure Insurance."

Why D is incorrect:
Insurance for non-performance of the Works is not one of the standard/basic insurance categories under the FIDIC 2017 insurance provisions. Insurance generally covers specified risks and liabilities rather than guaranteeing that the Contractor will perform the Works.

Reference:
Sub-Clause 19.2 [Insurance to be Provided by the Contractor] — FIDIC 2017.
Also relevant: Sub-Clause 19.1 [General Requirements for Insurances] and Sub-Clause 18 [Exceptional Events].

Exam Tip:
For basic FIDIC insurance questions, remember:
Persons/property + Goods/Contractor's Equipment + Works-related risks → typical insurance scope.

"Force Majeure Insurance" and "non-performance insurance" are not standard FIDIC insurance categories.

Final Answer: A and C. ✅
Question 25 Choose 1
A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?.
Show answerHide answer

Correct answer: C In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

Explanation

Explanation

Why C is NOT true (The correct choice):
Under FIDIC Silver Book 1999, Sub-Clause 8.7 [Delay Damages], the delay damages specified in the Contract are explicitly intended to be the only financial compensation due from the Contractor for the default of late completion. Once the Employer claims and recovers these agreed delay damages, they generally cannot claim additional general damages or extra administrative costs for the same period of delay, because delay damages are intended to liquidate and limit the relevant loss.

Why A is true:
If variations were ordered during the project, the Contractor must check whether extensions of time (EOT) were granted or agreed upon as part of those variations under the relevant variation provisions. Such an extension could legally excuse part or all of the 3-month overrun.

Why B is true:
Investigating the root cause of the delay is a fundamental first step in defending against a delay damages claim. This includes determining whether critical-path delays were triggered by statutory bodies, local authorities, or other events outside the Contractor's control.

Why D is true:
Under Sub-Clause 8.9 [Consequences of Suspension] and the relevant provisions of Sub-Clause 8.2, if a suspension is instructed by the Employer and is not attributable to the Contractor's default, the Contractor may be entitled to an extension of time and associated Cost. Therefore, a delay damages claim covering an excused suspension period would not be justified.

Final Answer: C. ✅
Question 26 Choose 1
(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))
Show answerHide answer

Correct answer: A Yes, but Contractor will do so on its own risk.

Explanation

Explanation:

Sub-Clause 8.1 [Commencement of Works] of the FIDIC Yellow Book and Silver Book (1999) states that the Contractor "shall commence the design and execution of the Works as soon as is reasonably practicable after the Commencement Date," and shall then proceed with due expedition and without delay. Critically, Clause 8 does not contain any express prohibition against the Contractor beginning design activities before the Commencement Date.

Since the Commencement Date is the contractual trigger point from which the Time for Completion starts running, and from which the Contractor's formal contractual obligations to proceed with design and execution are measured, there is nothing in the Contract preventing the Contractor from getting a head start on design work earlier, for example, to manage its own internal resource planning or to try to build in float or buffer.

If the Contractor chooses to do so:
It does so entirely at its own risk and cost. There is no contractual obligation on the Employer to recognize, pay for, or give credit for any work, design or otherwise, carried out before the Commencement Date.

If, for example, the Employer's Requirements or design basis subsequently change, via Variation or otherwise, before the official Commencement Date, any early design work done by the Contractor that becomes redundant or must be reworked is the Contractor's own loss. It cannot claim additional time or cost for abortive early design work.

The Contractor also bears the risk that formal access, third-party permits, or other preconditions for effective design or execution may not yet be in place before the Commencement Date.

Why the others are incorrect:

B. Incorrect:
This conflates design with execution, meaning physical works on Site. Even if early design work were tolerated at the Contractor's own risk, actual physical execution of the Works before the Commencement Date would typically not be practical or permitted, since the Contractor generally has no right of access to the Site under Sub-Clause 2.1 until the relevant access arrangements are available. Mobilization, insurance, and security arrangements may also be tied to the contractual commencement framework.

C. Incorrect:
Clause 8 does not contain an express prohibition on early design work. It establishes when the Contractor's formal obligation to commence begins, rather than creating a general bar on voluntary early preparatory design activity.

D. Incorrect:
This reverses the risk allocation. Any early design work undertaken by the Contractor before the Commencement Date is at the Contractor's own risk, not the Employer's, since it falls outside the formal contractual timeline for commencement.

Reference:
FIDIC Conditions of Contract for Plant and Design-Build ("Yellow Book"), 1999 Edition, Sub-Clause 8.1 [Commencement of Works].
FIDIC Conditions of Contract for EPC/Turnkey Projects ("Silver Book"), 1999 Edition, Sub-Clause 8.1 [Commencement of Works].
Sub-Clause 2.1 [Right of Access to the Site].
Question 27 Choose 2
Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have? Choose all of the correct answers (multiple possibilities)
Show answerHide answer

Correct answer: A, C The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor's items on the Site

Explanation

Explanation:

Why A and C are correct:

Under Sub-Clause 11.11 of the FIDIC Red Book (2017 edition), if the Contractor fails to remove its remaining equipment, surplus materials, wreckage, rubbish, or Temporary Works from the Site within 28 days after the Employer issues the Performance Certificate, the Employer has specific remedies.

Option A: The Employer may sell or otherwise dispose of any remaining items and reinstate the Site at the Contractor's cost. This matches the standard FIDIC provision, which entitles the Employer to recover costs incurred in connection with the sale or disposal and the restoration of the Site.

Option C: The Employer is entitled to the cost of reinstating, clearing the Site, and disposal cost to the extent they exceed the money received from selling the remaining Contractor's items. The provision states that any balance from the sale shall be paid to the Contractor, but if the proceeds are less than the Employer's costs, the Contractor must pay the outstanding balance to the Employer.

Why B and D are incorrect:

Option B: This is incorrect because it states that the Engineer "cannot" sell or dispose of items, which contradicts the Employer's express right to do so under Sub-Clause 11.11.

Option D: This is incorrect because it states that the Employer "cannot" reinstate and clear the Site if the Contractor fails. The Employer is expressly entitled to do so and recover the costs from the Contractor.

Reference:
FIDIC Red Book (2017 Edition), Sub-Clause 11.11 [Clearance of Site].
Question 28 Choose 1
Which one statement regarding the adjustment of the Contract Price as mentioned in Sub- Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?
Show answerHide answer

Correct answer: B The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. This can result in lower adjustments of the Contract Price than the actual changes in the costs of labour and/or Goods.

Explanation

Explanation:

In the FIDIC Silver Book (1999), Sub-Clause 13.8 [Adjustments for Changes in Cost] governs how the Contract Price may be adjusted for rises and falls in costs, including labour, materials, goods, and other applicable cost components.

The Particular Conditions may specify the formula or indices to be used for cost adjustments.

These indices may not always reflect the actual market changes in cost. As a result, the adjustment of the Contract Price may be lower or higher than the actual changes in labour, goods, or other applicable costs.

This is intentional. FIDIC allows the Employer to define a transparent and predictable adjustment mechanism, even if it does not fully compensate the Contractor for actual cost fluctuations.

Why the Other Options Are Incorrect:

A. Full compensation for all rises and falls:
Incorrect. Adjustments are based on the applicable indices and formula rather than guaranteeing full compensation for every actual increase or decrease in cost.

C. Only labour and goods costs apply:
Incorrect. Adjustments can apply to other cost categories depending on the formula and indices specified in the Particular Conditions.

D. Only Base Date applies:
Incorrect. While the Base Date is relevant to the calculation, adjustments are not limited to the Base Date. They are calculated according to the applicable formula and indices specified in the Contract.

References:
Contract administration — Sub-Clause 13.8 [Adjustments for Changes in Cost].
Question 29 Choose 1
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
Show answerHide answer

Correct answer: B False

Explanation

Explanation:

Under Sub-Clause 21.4.2 [The Parties’ obligations after the reference] of the FIDIC Red, Yellow and Silver Books 2017, the Parties are required to continue performing their contractual obligations after a Dispute has been referred to the DAAB, unless the Contract has already been abandoned or terminated.

Referring a Dispute to the DAAB does not entitle or require either Party to suspend performance. The Parties must continue to perform their obligations in accordance with the Contract while the DAAB considers the Dispute, unless the Contract has already been abandoned or terminated.

The statement is therefore false.

Reference:
FIDIC Conditions of Contract, Second Edition 2017 — Sub-Clause 21.4.2 [The Parties' obligations after the reference].
Question 30 Choose 1
(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
Show answerHide answer

Correct answer: B The Engineer has made a non-objection letter, in which it is stated that the issue/disagreement does not concern the matter that is being dealt with by the Engineer

Explanation

Explanation:

Under the FIDIC Red Book 2017, a standing DAAB can provide informal assistance to the Parties when they jointly ask for help with an issue or disagreement.

The process is intended to help the Parties resolve matters before they become a formal dispute.

A. Employer and Contractor identify an issue and agree to seek DAAB assistance — Correct:
The Parties must agree that they want the DAAB to provide informal assistance or discuss the issue and attempt to resolve the disagreement.

B. Engineer provides a non-objection letter — Incorrect:
This is the incorrect step. The Engineer does not have to issue a "non-objection" before the Employer and Contractor can request informal assistance from the DAAB.

The DAAB's informal assistance is a matter between the Employer and Contractor, and the Engineer's non-objection is not a prerequisite specified by the Contract.

C. Joint written request — Correct:
The Employer and Contractor make a joint request in writing to the DAAB before the DAAB provides the requested informal assistance.

This is an important distinction: informal assistance is not something one Party can unilaterally impose on the DAAB.

D. Both Parties should be present — Correct:
The purpose of the informal assistance is to facilitate discussion between the Parties. Both the Employer and Contractor should therefore participate when the DAAB provides its assistance.

Reference:
FIDIC Red Book 2017.
Relevant provisions include Sub-Clause 21.3 [Avoidance of Disputes] and the DAAB Procedural Rules, particularly the provisions concerning informal assistance during Site visits.

Exam Tip:
For informal DAAB assistance, remember:
Parties agree → joint written request → both Parties participate → DAAB assists.

The Engineer does not need to issue a non-objection.

Final Answer: B. ✅
Full mock exam

Sit the CCM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CCM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CCM mock exam
  • —questions per mock
  • —time limit
  • 140questions in the bank
  • Newmock on every attempt