Question 11 Choose 1
Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
Show answerHide answer

Correct answer: C A disproportionate amount of risks is allocated to the Contractor under the General Conditions

Explanation

Explanation

Why statement C is NOT correct:
Under standard FIDIC philosophy—including both the 1999 and 2017 editions of the Yellow Book—the General Conditions are carefully drafted to allocate risks between the Employer and the Contractor on a fair and balanced basis (sharing risks based on which party is best able to control or bear them). Claiming that a disproportionate amount of risk is placed on the Contractor describes a non-standard or heavily amended contract (or a Silver Book-style EPC turnkey shift), but it completely contradicts the foundational design principles of the FIDIC Yellow Book General Conditions.

Why the other statements ARE correct:

A is correct: The contract typically comes into legal effect and binds the parties upon the issuance and receipt of the Letter of Acceptance (unless the contract specifies otherwise, such as requiring a contract agreement signature or conditions precedent).

B is correct: The core philosophy of FIDIC General Conditions is a fair and equitable risk-sharing mechanism between Employer and Contractor.

D is correct: Under the Yellow Book, the Contractor is responsible for plant design, engineering, and execution of the works in accordance with the Contract, which incorporates the Employer's Requirements and the Contractor's Proposal.

References
FIDIC Conditions of Contract for Plant and Design-Build (Yellow Book, 1999 & 2017 Editions): Introductory notes, General Conditions preamble, and Guidance for the Preparation of Particular Conditions regarding risk allocation and the principles of the FIDIC suite.
Question 12 Choose 1
Under the FIDIC Construction Contract, which one of the following statements is correct?
Show answerHide answer

Correct answer: E A DAB must give its decision in writing on any dispute when requested by one of the Parties.

Explanation

Explanations

A. Incorrect: The remuneration of DAB members (including retainer and daily fees) is shared equally between the Employer and the Contractor, not made the sole responsibility of the Contractor.

B. Incorrect: An ad-hoc DAB is typically constituted after a dispute has arisen, and unlike a standing DAB, an ad-hoc DAB generally does not receive a monthly retainer fee; they are usually compensated through daily fees and expenses when services are utilized.

C. Incorrect: Payments to DAB members are paid directly by the Parties (each paying their respective share or split evenly) pursuant to the Dispute Adjudication Agreement, rather than being certified as part of the Employer's interim payment certificates for the Works under the Contract.

D. Incorrect: If the Parties fail to agree on the appointment of DAB members, or if nominated members fail to take office, the mechanism relies on the specified appointing entity named in the Contract data (e.g., the President of FIDIC or a designated institution) to make the appointment, but it is governed by strict rules on default nominations rather than a blanket signing fallback.

E. Correct: Under FIDIC dispute resolution clauses, once a dispute is properly referred to the DAB by either Party, the DAB has a contractual duty to review the matter and render its decision in writing to both Parties.
Question 13 Choose 1
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?
Show answerHide answer

Correct answer: B False

Explanation

Explanation:

Under Sub-Clause 8.6 [Rate of Progress] of both the FIDIC Yellow Book and Silver Book (1999 editions), the substance of the provision is:

"If, at any time... actual progress is too slow to complete within the Time for Completion... then the Engineer [YB] / Employer [SB] may instruct the Contractor to submit... a revised programme... and a supporting report describing the revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for Completion. Unless the Engineer/Employer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in the working hours and/or in the numbers of Contractor's Personnel and/or Goods, at the risk and cost of the Contractor."

The key phrase is "at the risk and cost of the Contractor." This provision is triggered specifically by the Contractor's own slow/inadequate progress — it is a corrective mechanism to bring the Contractor back on track to meet the existing Time for Completion, not a Variation or an Employer-caused event. Because the underlying cause is the Contractor's own failure to progress the Works adequately, the Contractor bears the additional cost of expediting — there is no entitlement to extra payment, even though the Engineer/Employer accepts the revised programme showing completion within the (unchanged) Time for Completion.

This is a deliberate contrast with:

Sub-Clause 13.3 [Variation Procedure] — where Employer/Engineer-instructed changes to the Works do entitle the Contractor to additional payment; and

Sub-Clause 8.4 [Extension of Time for Completion] — where delay caused by Employer risk events entitles the Contractor to an EOT (and, in some cases, Cost).

Sub-Clause 8.6 sits in neither of those categories — it's a Contractor-risk remedial obligation, so acceptance of the revised programme by the Engineer/Employer does not trigger a right to payment of extra costs.

Reference
FIDIC Conditions of Contract for Plant and Design-Build ("Yellow Book"), 1999 Edition, Sub-Clause 8.6 [Rate of Progress]; FIDIC Conditions of Contract for EPC/Turnkey Projects ("Silver Book"), 1999 Edition, Sub-Clause 8.6 [Rate of Progress].
Question 14 Choose 1
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?
Show answerHide answer

Correct answer: A True

Explanation

Explanation:

All three FIDIC Books (Red, Yellow and Silver), in both the 1999 and 2017 editions, contain provisions dealing with nominated Subcontractors.

A nominated Subcontractor is defined as a Subcontractor who is either named as such in the Contract or whom the Engineer (Red/Yellow Books) or the Employer (Silver Book) instructs the Contractor to employ (typically under the Variations / Provisional Sums provisions).

The Contractor is not obliged to employ a nominated Subcontractor against whom the Contractor raises a reasonable objection by giving a Notice (with supporting particulars) to the Engineer/Employer.

The Sub-Clauses list examples of what constitutes a reasonable objection (e.g. insufficient competence/resources/financial strength of the proposed Subcontractor, or the absence of required indemnities in the subcontract).

If the Employer still requires the nomination after a valid objection, the Employer must agree to indemnify the Contractor against the consequences of the matter.

Key references

1999 editions:
– Red Book: Sub-Clauses 5.1 & 5.2
– Yellow Book: Sub-Clause 4.5
– Silver Book: Sub-Clause 4.5

2017 editions:
– Red Book: Sub-Clauses 5.2.1 & 5.2.2
– Yellow & Silver Books: equivalent provisions in Clause 4 / 5

The statement is therefore correct for all three Books and both editions.
Question 15 Choose 1
Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?
Show answerHide answer

Correct answer: A "The Employer obtains the best value for money" AND "Disputes should be avoided to the extent achievable."

Explanation

Explanation:

The FIDIC Golden Principles (2019) set out five key considerations to ensure contracts remain fair, balanced, and aligned with FIDIC’s philosophy. Two of these principles directly relate to the question:

The Employer obtains the best value for money

Contracts must be structured to ensure the Employer achieves efficiency, quality, and cost-effectiveness.

This reflects the principle that FIDIC contracts are designed to deliver projects that balance risk allocation and performance obligations fairly.

Disputes should be avoided to the extent achievable

FIDIC emphasizes proactive dispute avoidance through clear contract terms, good administration, and collaboration.

When disputes do arise, they should be minimized and resolved efficiently (through mechanisms like Dispute Avoidance/Adjudication Boards).

Why Other Options Are Incorrect

B. "Only the Employer should be the one to obtain the best value for money" AND "The Contractor/Subcontractor is paid adequately and timely..."
✘ Incorrect. The Golden Principles emphasize balance — not exclusivity for the Employer. Payment adequacy is correct, but the first statement is too one-sided.

C. "The Contractor/Subcontractor is paid adequately..." AND "The terms of the Contract are comprehensive and fair to primarily the Employer".
✘ Incorrect. FIDIC requires fairness to both parties, not primarily the Employer.

D. "The Contractor should take advantage of its bargaining power..." AND "Disputes are avoided/minimized/resolved efficiently."
✘ Incorrect. The first statement contradicts FIDIC’s balanced risk-sharing philosophy.

References
Risk allocation — Balanced risk sharing between Employer and Contractor.
Dispute resolution — Avoidance, minimization, and efficient resolution.
Question 16 Choose 1
You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
Show answerHide answer

Correct answer: C The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

Explanation

Explanation:

Under FIDIC Yellow Book 2017 (Sub-Clause 16.2 - Termination by Contractor), the grounds for termination by the Contractor include specific material breaches by the Employer:

Why D is correct (Does NOT allow termination)
Sub-Clause 16.2(d)(ii) explicitly grants the right to terminate if the Employer fails to comply with a binding agreement or a final and binding decision/determination of the DAAB (Dispute Avoidance/Adjudication Board), not the Engineer. While the Engineer issues determinations under Sub-Clause 3.7, a failure to comply with an Engineer's determination does not automatically trigger the specific contractual right to terminate under Sub-Clause 16.2 unless it goes through the proper dispute adjudication process.

Why A allows termination
Sub-Clause 16.2 (read with Sub-Clause 8.11) allows termination if a prolonged suspension affecting the whole of the Works exceeds 84 days (1 year well exceeds this threshold).

Why B allows termination
Sub-Clause 16.2(c) permits termination if the Contractor does not receive payment within 84 days after the payment due date (4 months is greater than 84 days).

Why C allows termination
Sub-Clause 16.2(a) allows termination if the Contractor does not receive reasonable evidence of financial arrangements within 42 days of a notice under Sub-Clause 2.4 (4 months is greater than 42 days).
Question 17 Choose 2
Giving "Notice" .... [2017 edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Show answerHide answer

Correct answer: B, D ... is always compulsory together with a clear indication of the relevant Sub-Clause under which the Notice is being served.... is intended for written communications, in full compliance with the formal requirements outlined in the dedicated Sub-Clause.

Explanation

Explanation:

Both correct statements reflect the strengthened, more formalised approach to Notices introduced in the FIDIC 2017 Rainbow Suite, governed primarily by Sub-Clause 1.3 [Notices and Other Communications].

B. Notice is always compulsory together with a clear indication of the relevant Sub-Clause under which it is being served.

Correct. One of the deliberate changes in the 2017 editions was to make the giving of Notices mandatory ("shall") wherever the Contract requires one — this is a significant tightening compared to the more informal, discretionary practice sometimes seen under the 1999 editions. Sub-Clause 1.3 expressly requires that a communication:

"shall state that it is a Notice", and
"shall refer to the Sub-Clause... under which it is given."

This is deliberate: FIDIC 2017 wanted to eliminate ambiguity about whether a given letter, email, or site instruction constituted a formal contractual Notice (which triggers time bars, entitlements, and obligations) or was merely informal correspondence.

D. Notice is intended for written communications, in full compliance with the formal requirements outlined in the dedicated Sub-Clause.

Correct. Sub-Clause 1.3 requires that a Notice:

be in writing and identifiable as a Notice;
be delivered by hand, sent by airmail/courier, or transmitted using the electronic transmission system (if stated in the Contract Data); and
comply with any other formal requirements specified (e.g., delivery to the correct address, in the ruling language).

Failure to comply with these formal requirements can mean a communication does not qualify as a valid contractual "Notice" — which matters greatly given the strict time-bar consequences tied to Notices (e.g., Sub-Clause 20.2 claims notice within 28 days).

Why the others are incorrect

A. Incorrect. This is the opposite of the actual 2017 position. Under the 1999 editions, some notice provisions were arguably more relaxed or ambiguous in enforcement; the 2017 editions deliberately reversed this by making Notices a strict, compulsory requirement (particularly reinforced by the tightened claims time-bar under Sub-Clause 20.2.1, which is expressed as a condition precedent — failure to give timely Notice can extinguish the claim entirely). It is not merely "highly recommended."

C. Incorrect. The obligation to give Notices under Sub-Clause 1.3 is not limited to the Engineer — it applies to both the Employer and the Contractor (and the Engineer, where the Engineer is required to issue Notices, e.g., a Notice of No-objection, instructions, etc.). Throughout Clauses 2–20, both Parties have numerous Notice obligations (e.g., Contractor's claim Notices under 20.2, Employer's claim Notices under 2.5/20.2, notices of dissatisfaction, notices to correct, notices of intention to terminate, etc.).

Reference
FIDIC Conditions of Contract (Red/Yellow/Silver Books), 2017 Edition, Sub-Clause 1.3 [Notices and Other Communications]; Sub-Clause 20.2 [Claims for Payment and/or EOT] (illustrating the strict time-bar/condition precedent effect tied to proper Notice-giving).
Question 18 Choose 1
(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))
Show answerHide answer

Correct answer: C Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

Explanation

Explanation:

Under Sub-Clause 13.8 of the FIDIC Red Book (1999 Edition), if the Contractor fails to complete the Works within the Time for Completion, the contract specifically addresses how price adjustments will be calculated for work performed after that deadline.

The provision states that for such late work, the adjustment shall be made using:

The index or price applicable on the date 49 days prior to the expiry of the Time for Completion, OR
The current index or price,

whichever is more favourable to the Employer.

Why the Other Options Are Incorrect

A. Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.
This option is incorrect because it presents only one of the two possible benchmarks. The contract does not mandate the use of this fixed historical date unconditionally; it requires a comparison to determine which option benefits the Employer more.

B. The current index or price.
This is incorrect because, like option A, it represents only one side of the comparison. The Engineer must evaluate both the "current" price and the "49-day prior" price to select the most advantageous one for the Employer.

D. Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever agreed by Parties.
This is incorrect because the selection is not subject to mutual agreement. The Sub-Clause explicitly sets an objective standard: "whichever is more favourable to the Employer." The Engineer determines this unilaterally based on the formula, and it is not a matter for negotiation between the Parties after the failure to complete on time has occurred.

Reference
FIDIC Red Book (1999 Edition), Sub-Clause 13.8 [Adjustments for Changes in Cost].
Question 19 Choose 1
(FIDIC Red Book (edition 2017) stipulates that the measurement shall be made as per the actual quantities executed at Site. Which one of the following statements is correct?)
Show answerHide answer

Correct answer: A The measurement shall be always made of the net actual quantity of each item of the Permanent Works.

Explanation

Explanation

Why A is correct: Under FIDIC Red Book 2017 (Sub-Clause 12.1 – Works to be Measured), the Contract specifies that the Works shall be measured net, meaning the actual physical dimensions or quantities of the Permanent Works executed on Site, in accordance with the drawings and specifications, without unauthorised additions or allowances.

Why B is incorrect: Measurements do not arbitrarily include allowances for the shrinkage, waste, or bulking of materials unless explicitly provided for in the Contract, Bill of Quantities (BOQ), or Technical Specifications.

Why C is incorrect: If an item of the Permanent Works is executed but not specified in the Bill of Quantities (i.e., a variation or unpriced item), the Contractor does not get to unilaterally choose the price. Instead, the valuation of such items is governed by the variation and valuation procedures under Clause 13 (Variations and Adjustments), typically determined or agreed upon by the Engineer.
Question 20 Choose 2
(Under FIDIC Red Book (edition 1999) a notice may be delivered to which two addresses? Choose all of the correct answers (multiple possibilities).)
Show answerHide answer

Correct answer: A, B The address stated in the Contract Data.The address provided for by the recipient of the notice.

Explanation

Explanation:

Under Sub-Clause 1.3 [Communications] of the FIDIC Red Book (1999), all approvals, certificates, consents, determinations, notices, and requests between the Parties must be delivered to a specific address, and the clause identifies two valid addresses:

A. The address stated in the Contract Data (referred to in the 1999 editions as the "Appendix to Tender") — This is the default address for communications, as nominated by each Party (Employer and Contractor) at the time of tendering/contract formation.

B. The address provided for by the recipient of the notice — Sub-Clause 1.3 expressly allows that "if the recipient gives notice of another address, communications shall thereafter be delivered accordingly." In other words, the recipient of communications can subsequently notify a different address, and once that notice is given, future communications must be sent to that newly nominated address instead of the original one in the Contract Data/Appendix to Tender.

Why the others are incorrect:

C. The address of the Site. The Site address is not, by default, a valid address for formal contractual communications under Sub-Clause 1.3, unless it happens to coincide with (or has been specifically nominated as) the address stated in the Contract Data or subsequently notified by the recipient. It is not independently listed as a permissible communications address in its own right.

D. The address of the Contractor's Representative. While the Contractor's Representative (appointed under Sub-Clause 4.3) is an important point of contact for day-to-day site management and instructions, Sub-Clause 1.3 governs formal contractual communications addressed to the Parties (Employer/Contractor) generally — not specifically to the Contractor's Representative's personal or office address, unless that happens to be the nominated address under (A) or (B) above.

Reference: FIDIC Conditions of Contract for Construction ("Red Book"), 1999 Edition, Sub-Clause 1.3 [Communications]; Appendix to Tender (nomination of addresses for communications).
Full mock exam

Sit the CCM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CCM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CCM mock exam
  • —questions per mock
  • —time limit
  • 140questions in the bank
  • Newmock on every attempt