(You are the Contract Manager of the Employer's Representative in a Thermal Power Plant
Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:
(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01
referenced in the Employer’s Requirements.
(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data
in Site Data (water level miscalculated).
What is your determination for the Contractor?)
Show answerHide answer
Correct answer: BThe Contractor is entitled to the Claim for additional costs in relation to the piling, based
on errors in the Employer's Requirements only.
Question 32Choose 2
What are two differences between a notice and other communications under the FIDIC Red
Book (edition 2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Show answerHide answer
Correct answer: A, DNotice is a defined term, while other communications are not defined as a term in the
General Conditions.The Parties and Engineer shall be given original or copy of any Notice, Notice of
Dissatisfaction (NOD) and Certificates, which is not always the case for other
communications.
Question 33Choose 1
If defects are identified during the Tests on Completion, which one of the following options
is not available to the Parties under the Contract?
Show answerHide answer
Correct answer: DThe Party which is not liable for the cost of rectifying defects can expect the other Party
to pay the cost of performing the repeated tests.
Question 34Choose 2
Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its
design proposal through the Contractor's Proposal. Which two of the following statements
are true in this respect, after it has been submitted?
Choose all of the correct answers (multiple possibilities).
Show answerHide answer
Correct answer: B, CThe Contractor is not allowed to make any changes regarding the design to optimise the
design, unless approved by the Engineer/EmployerThe Contractor may submit a proposal for Value Engineering
Question 35Choose 1
(Golden Principle 2 states that "The Particular Conditions must be drafted clearly and
unambiguously." Which statement best underlines this Golden Principle in relation to the
FIDIC Red, Yellow, and Silver Books (both editions)?)
Show answerHide answer
Correct answer: DIn the Particular Conditions, all changes to the General Conditions must be clearly
identified by reference to specific Sub-Clause numbers. Additionally, the Particular
Conditions Sub-Clauses must clearly indicate the relationship between the newly
introduced text and the corresponding General Conditions Sub-Clauses’ original text, e.g.,
addition, omission, replacement, or amendment.
Question 36Choose 2
If the Engineer is required to obtain the Employer's prior approval to issue determinations
(including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999
Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Show answerHide answer
Correct answer: C, DIssuing the determination to the Contractor in the form and with the content agreeable to
the Employer, with a remark, that it is the Employer's determination and not the Engineer's
determinationInforming the Contractor of their inability of issuing the determination, in lack of the
Employer's necessary approval
Question 37Choose 2
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999).
You work for the Employer – a highway management agency. During the tender period,
you are informed of a specific Commencement Date required by the directors of the
agency. Which two of the following approaches to inform the tenderers of this date are
clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).
Show answerHide answer
Correct answer: B, CSpecify Commencement Date in the Contract Agreement.Specify Commencement Date in the Particular Conditions
Question 38Choose 2
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a
change of the design of a part of the Works. After expiry of 84 days of suspension, the
Contractor gave notice thereof. Following this notice, the suspension was not lifted within
28 days. What two statements are correct in such a situation?
Show answerHide answer
Correct answer: A, CA. Under the Contract the Parties cannot agree on further suspension and the Contractor
may immediately terminate the Contract if it affects the whole WorksThe Contractor may terminate the Contract if it affects the whole Works, but only after it
has given a second notice to the Engineer
Question 39Choose 1
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid
according to quantity supplied or work done, appropriate provisions must be included in the
Particular Conditions. Is this statement true or false?
Show answerHide answer
Correct answer: ATrue
Question 40Choose 1
In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to
Sub-Clause 3.5:
"In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry
out any determination regardless of a possible notice of dissatisfaction."
What GP(s) is/are breached?
Show answerHide answer
Correct answer: CGP1 and GP3