FIDIC certification · Exam CCM

CCM Mock Exam Page 4

Certified Contract Manager

Free CCM mock exam questions 31–40, each with the answer and an explanation.

20 questions · 30 minutes · free, no sign-up

Free CCM questions

31–40 of 42 free
Question 31 Choose 1
(You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims: (1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer’s Requirements. (2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated). What is your determination for the Contractor?)
Show answerHide answer

Correct answer: B The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirements only.

Question 32 Choose 2
What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Show answerHide answer

Correct answer: A, D Notice is a defined term, while other communications are not defined as a term in the General Conditions.The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.

Question 33 Choose 1
If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?
Show answerHide answer

Correct answer: D The Party which is not liable for the cost of rectifying defects can expect the other Party to pay the cost of performing the repeated tests.

Question 34 Choose 2
Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor's Proposal. Which two of the following statements are true in this respect, after it has been submitted? Choose all of the correct answers (multiple possibilities).
Show answerHide answer

Correct answer: B, C The Contractor is not allowed to make any changes regarding the design to optimise the design, unless approved by the Engineer/EmployerThe Contractor may submit a proposal for Value Engineering

Question 35 Choose 1
(Golden Principle 2 states that "The Particular Conditions must be drafted clearly and unambiguously." Which statement best underlines this Golden Principle in relation to the FIDIC Red, Yellow, and Silver Books (both editions)?)
Show answerHide answer

Correct answer: D In the Particular Conditions, all changes to the General Conditions must be clearly identified by reference to specific Sub-Clause numbers. Additionally, the Particular Conditions Sub-Clauses must clearly indicate the relationship between the newly introduced text and the corresponding General Conditions Sub-Clauses’ original text, e.g., addition, omission, replacement, or amendment.

Question 36 Choose 2
If the Engineer is required to obtain the Employer's prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Show answerHide answer

Correct answer: C, D Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark, that it is the Employer's determination and not the Engineer's determinationInforming the Contractor of their inability of issuing the determination, in lack of the Employer's necessary approval

Question 37 Choose 2
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer – a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted? Choose all of the correct answers (multiple possibilities).
Show answerHide answer

Correct answer: B, C Specify Commencement Date in the Contract Agreement.Specify Commencement Date in the Particular Conditions

Question 38 Choose 2
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?
Show answerHide answer

Correct answer: A, C A. Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole WorksThe Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer

Question 39 Choose 1
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
Show answerHide answer

Correct answer: A True

Question 40 Choose 1
In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5: "In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction." What GP(s) is/are breached?
Show answerHide answer

Correct answer: C GP1 and GP3

Full mock exam

Sit the CCM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CCM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CCM mock exam
  • —questions per mock
  • —time limit
  • 140questions in the bank
  • Newmock on every attempt