Question 1 Choose 2
(In a FIDIC Red Book, the Employer shall have prepared (or have prepared by a design consultant) all the design for the Works. Which of the listed documents form the basis for this design (2 correct answers apply))
Show answerHide answer

Correct answer: A, B The Bill of QuantitiesThe Specifications

Explanation

Explanation:

Under the FIDIC Red Book (Conditions of Contract for Construction), the design responsibility lies with the Employer — either prepared in-house or by the Employer's own design consultant. This is what distinguishes the Red Book from the Yellow/Silver Books, where the Contractor carries the design responsibility, driven by the "Employer's Requirements".

Under Sub-Clause 4.11 and 5.1 (design responsibility clauses) of the Red Book, the Employer's design intent and scope of work are communicated to the Contractor primarily through:

B. The Specifications:
These set out the technical requirements, standards, materials, workmanship, and performance criteria that reflect the Employer's design. The Specification is one of the two primary design-carrying documents in a Red Book contract (the other being the Drawings).

A. The Bill of Quantities:
The BOQ is prepared by the Employer (or the Engineer, on the Employer's behalf) based directly on the completed design and Drawings. It itemizes and quantifies the works exactly as designed, meaning it reflects — and is derived from — the underlying design.

Why the others are incorrect:

C. Breakdown of Lump-Sum:
This is a payment/pricing schedule (common in lump-sum contract structures), not a design document.

D. Schedule of Subcontractors:
Relates to subcontracting arrangements and approvals, unrelated to design content.

E. The Form of Contract Agreement:
This is the formal signed agreement binding the parties to the Contract; it incorporates the Contract Documents by reference but does not itself contain design content.

Note:
In practice, the Employer's design under the Red Book is most fundamentally expressed through the Specification and the Drawings together. Since "Drawings" isn't among your listed options here, the Bill of Quantities is the next-best fit as the second answer, since it is a direct numerical expression of the Employer's design once drawings are finalized. If your exam source lists "Drawings" as an option elsewhere, that would replace the BOQ as the more textbook-accurate second answer — worth double-checking against your specific FIDIC CCM study material or the Red Book's General Conditions if you have the exact clause reference handy.
Question 2 Choose 2
(Under the FIDIC Red and Yellow Books (edition 1999), which two of the following answers are correct regarding the application for Interim Payment Certificates? Choose all correct answers.)
Show answerHide answer

Correct answer: B, C The statement submitted by the Contractor shall include, if applicable, any amounts to be added for Provisional SumsEach statement must be accompanied (or preceded) by supporting documents, including the progress report specified in Sub-Clause 4.21, for the relevant period

Explanation

Explanation:

Under FIDIC 1999 Red and Yellow Books (Sub-Clause 14.3 - Application for Interim Payment Certificates), the contents of the Contractor's monthly statement are explicitly detailed.

Why B is correct:
Sub-Clause 14.3(c) explicitly includes “any amounts to be added and deducted for Provisional Sums under Sub-Clause 13.5”.

Why D is correct:
Sub-Clause 14.3(e) explicitly includes “any amounts to be added and deducted for Plant and Materials under Sub-Clause 14.5” (relating to plant/materials intended for, or delivered to, the Site).

Why the other options are incorrect:

Option A is incorrect:
Sub-Clause 14.3 states that the Contractor shall submit the Statement in six copies (not five) to the Engineer (and addressed to the Engineer, not directly to the Employer as a primary rule of submission).

Option C is incorrect:
While progress reports are mandatory under Sub-Clause 4.21, the strict contractual prerequisite for the monthly statement under standard FIDIC 1999 Sub-Clause 14.3 does not dictate that each statement must be accompanied or preceded specifically by the progress report as an embedded payment condition in that exact phrasing, making options B and D the standard direct inclusions listed under the clause breakdown.
Question 3 Choose 2
(Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)? Choose all of the correct answers (multiple possibilities).)
Show answerHide answer

Correct answer: B, D If no maximum allowable accumulated value of work subcontracted is stated in the Contract Data, the Contractor shall not be entitled to subcontract the whole of the Works without prior consent of the EngineerThe Contract Data may identify parts of the Works which the Contractor is not entitled to subcontract

Explanation

Explanation:

Under Sub-Clause 5.2 (Subcontractors) of the FIDIC 2017 Rainbow Suite (Red, Yellow, and Silver Books), the key rules are:
The Contractor shall not subcontract the whole of the Works — this is an absolute prohibition, independent of any stated maximum value.
The Contractor shall be responsible for the acts and defaults of any Subcontractor, its agents, or employees, as if they were the acts or defaults of the Contractor itself.

Consent requirements are differentiated:
No consent is needed for named Subcontractors already identified in the Contract, or for the supply of labour/materials in certain cases.
The Engineer's (not the Employer's) prior consent is required for other proposed Subcontractors.

Why B is correct:
Sub-Clause 5.2 ties the subcontracting limit to whether a maximum accumulated value is stated in the Contract Data. If no such maximum is stated, the general prohibition still applies — the Contractor cannot subcontract the whole of the Works without the Engineer's prior consent. This reflects the safeguard that even absent a specific numeric limit, wholesale subcontracting still requires oversight/consent.
Why D is correct:
The Contract Data (Red/Yellow) or Contract particulars can specifically list parts of the Works that the Contractor is restricted from subcontracting, giving the Employer/Engineer direct control over which critical portions of the work must be performed by the Contractor itself (often key structural, specialized, or sensitive elements).

Why the others are incorrect:
A — Incorrect because consent for Subcontractors is obtained from the Engineer, not jointly from the Engineer and the Employer. The Employer does not have a direct consent role in this clause.
C — Incorrect; this is the reverse of the actual rule. The Contractor remains fully responsible for the acts and defaults of its Subcontractors as if they were its own — subcontracting does not relieve the Contractor of liability under the Contract.

Reference:
FIDIC 2017 (Red/Yellow/Silver Book), Sub-Clause 5.2 – Subcontractors.
Question 4 Choose 1
The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP's)?
Show answerHide answer

Correct answer: B GP 1

Explanation

Explanation:

Context of the Process:
The scenario describes standard transparent procurement and tendering practices (as outlined in the FIDIC Procurement Procedures Guide). Clarifications and agreements made during tender negotiations are documented (e.g., via a Memorandum of Understanding), leading up to formal contract award via a Letter of Acceptance.

Why GP 1 applies:
The FIDIC Golden Principles (GPs) govern the integrity of the contract structure and processes. Golden Principle 1 (GP 1) states: "The duties, rights, obligations, roles and responsibilities of all the Contract Participants must be generally as implied in the General Conditions, taking into account the particulars of the jurisdiction."

Maintaining a clear, unaltered framework from the tendering stage through the General and Particular Conditions safeguards the core risk-allocation and operational mechanics inherent to FIDIC contracts, aligning directly with GP 1's intent to keep the fundamental rights and obligations intact.

Why other options are incorrect:
GP 2: Focuses on ensuring Particular Conditions are drafted clearly and unambiguously.
GP 3: Focuses on ensuring Particular Conditions do not change the balance of risk/reward allocated in the General Conditions.
GPA: A distractor, referring externally to agreements like the WTO Government Procurement Agreement rather than a FIDIC Golden Principle.
Question 5 Choose 1
(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)
Show answerHide answer

Correct answer: A True

Explanation

Explanation:

Under Sub-Clause 14.9 [Payment of Retention Money]
The 1999 editions provide that when the retention money becomes due for release, the Employer/Engineer may withhold certification of the estimated cost of work that remains to be executed.

The wording differs slightly by book:

Red Book 1999: If work remains to be executed under Clause 11 [Defects Liability], the Engineer is entitled to withhold certification of the estimated cost of that work until it has been executed.

Yellow Book 1999: If work remains under Clause 11 [Defects Liability] or Clause 12 [Tests after Completion], the Engineer may withhold certification of the estimated cost until that work has been executed.

Silver Book 1999: The same principle applies under Sub-Clause 14.9 [Payment of Retention Money], covering remaining work under Clauses 11 and 12.

Why this matters
The purpose is to prevent the full retention amount from being released when there is still contractual work outstanding. The amount withheld is tied to the estimated cost of the remaining work, and it is released once that work has been executed.

Exam Reference
FIDIC 1999 Editions → Sub-Clause 14.9 [Payment of Retention Money]

Book            Relevant outstanding work
Red Book 1999      Clause 11 – Defects Liability
Yellow Book 1999    Clause 11 – Defects Liability + Clause 12 – Tests after Completion
Silver Book 1999     Clause 11 – Defects Liability + Clause 12 – Tests after Completion

Final Answer: A. True ✅

Exam tip: When you see “retention money + work remains to be executed + estimated cost”, think Sub-Clause 14.9 of the 1999 FIDIC forms.
Question 6 Choose 2
Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
Show answerHide answer

Correct answer: A, B FIDIC Conditions of Contract for Construction ("Red Book").FIDIC Conditions of Contract for Plant and Design Build ("Yellow Book").

Explanation

Explanation:

Why they're correct — the certification mechanism:
Both the Red Book (Construction, 1999) and Yellow Book (Plant and Design-Build, 1999) are built around an independent "Engineer", appointed and paid by the Employer but required to act neutrally between the parties when making certain determinations.

Sub-Clause 14.3 "Application for Interim Payment Certificates" — the Contractor submits a monthly Statement to the Engineer.

Sub-Clause 14.6 "Issue of Interim Payment Certificates" — the Engineer must, within 28 days, issue an Interim Payment Certificate (IPC) stating the amount the Engineer "fairly considers to be due."

Sub-Clause 14.7 "Payment" — the Employer is contractually bound to pay the certified amount within the stated period.

Sub-Clause 3.5 "Determinations" — underpins the Engineer's duty to act fairly when certifying.

So payment in these two books flows through a formal, third-party certification step — the Engineer's certificate — before the Employer's payment obligation crystallises. The same logic applies to the Final Payment Certificate under Sub-Clause 14.13.

Reference:
FIDIC Conditions of Contract for Construction ("Red Book"), 1999 Edition, Sub-Clauses 14.3, 14.6, 14.7, 14.13, 3.5; FIDIC Conditions of Contract for Plant and Design-Build ("Yellow Book"), 1999 Edition, Sub-Clauses 14.3, 14.6, 14.7, 14.13, 3.5.

Incorrect: C (Silver Book)

Why it's wrong — no independent Engineer, no certificate:
The Silver Book (EPC/Turnkey Projects, 1999) is deliberately structured without an independent Engineer. It's designed for privately-financed, high risk-transfer projects (e.g., BOT/BOOT schemes) where the Employer wants direct control and the Contractor carries most of the risk, including design responsibility.

Key structural differences confirming no certification step:
Sub-Clause 14.3 in the Silver Book is titled "Application for Interim Payments" (not "...Payment Certificates" as in Red/Yellow) — the Contractor applies directly to the Employer.

There is no Sub-Clause equivalent to "Issue of Interim Payment Certificates." The Employer (or an Employer's Representative acting on the Employer's behalf, not as an impartial certifier) reviews the application and pays what it considers due.

Where the Employer disagrees with the amount claimed, this is resolved via Sub-Clause 3.5 [Determinations] — but by the Employer's Representative, who is explicitly not required to act as an independent certifier the way the Engineer is under the Red/Yellow Books.

This absence of independent certification is a well-recognised risk factor for Contractors under the Silver Book, since there's no neutral third party checking the Employer's payment decisions — one of the reasons the Silver Book is considered the most Employer-favourable (and Contractor-risky) of the three main 1999 forms.

Reference:
FIDIC Conditions of Contract for EPC/Turnkey Projects ("Silver Book"), 1999 Edition, Sub-Clauses 14.3, 14.7, 3.5.
Question 7 Choose 1
Which one of the following claim events does NOT allow profit?
Show answerHide answer

Correct answer: D Under the Construction Contract, the relevant authority had unnecessarily delayed the approval

Explanation

Explanation:

Under the FIDIC Red Book 1999, a claim arising from a delay by a relevant authority does not entitle the Contractor to profit. While the Contractor may be entitled to an extension of time and possibly Cost (under certain conditions), the Red Book's compensation structure for authority-related delays is limited to Cost only, excluding profit.

Why the Other Options Are Incorrect (They Do Allow Profit)

The following claim events under the FIDIC Red Book and Yellow Book do entitle the Contractor to claim Cost plus reasonable profit:

A. Interference by the Employer with Tests on Completion
Red Book Sub-Clause 10.3 expressly provides that if the Contractor suffers delay and/or incurs Cost as a result of the Employer's interference, the Contractor is entitled to Cost plus reasonable profit.

B. Engineer's Delay in Supplying Drawings or Instructions
Red Book Sub-Clause 1.9 provides that the Contractor is entitled to Cost plus reasonable profit when the Engineer fails to issue drawings or instructions within a reasonable time.

C. Employer's Failure to Give Right of Access to the Site
Red Book Sub-Clause 2.1 entitles the Contractor to Cost plus reasonable profit if the Employer fails to give access to the site within the required time.

E. Errors in the Employer's Requirements (Yellow Book)
Yellow Book Sub-Clause 1.9 explicitly provides that the Contractor is entitled to Cost plus reasonable profit where errors in the Employer's Requirements result in delay and Cost.
Question 8 Choose 2
(Which two statements are correct for the FIDIC Red Book (edition 2017)? Choose all of the correct answers (multiple possibilities).)
Show answerHide answer

Correct answer: B, D Conditions of Contract means these General Conditions as amended by Particular ConditionsContract Agreement, Letter of Acceptance and Letter of Tender are part of the Contract

Explanation

Explanation:

B is correct

Under Sub-Clause 1.1 of the FIDIC Red Book 2017 (Second Edition),

“Conditions of Contract” or “these Conditions” means the General Conditions as amended by the Particular Conditions.

The Particular Conditions themselves consist of:
Part A – Contract Data
Part B – Special Provisions

Together, the General Conditions + Particular Conditions form the “Conditions of Contract”.

D is correct

The definition of “Contract” (Sub-Clause 1.1) expressly includes:

the Contract Agreement,
the Letter of Acceptance,
the Letter of Tender,
these Conditions,
the Specification,
the Drawings,
the Schedules, and
any further documents listed in the Contract Agreement or Letter of Acceptance.

Thus, Contract Agreement, Letter of Acceptance and Letter of Tender are all constituent parts of the Contract.

Why the other options are incorrect

A is wrong. The Contract comprises far more than just the General Conditions and Particular Conditions (see the full definition of “Contract” above).

C is wrong. Contract Data forms Part A of the Particular Conditions, not part of the General Conditions.

References

FIDIC Conditions of Contract for Construction, Second Edition 2017 (Red Book), Sub-Clause 1.1 (Definitions) – especially the definitions of “Contract”, “Conditions of Contract” / “these Conditions”, and the structure of the Particular Conditions (Part A – Contract Data and Part B – Special Provisions).
Question 9 Choose 1
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.
Show answerHide answer

Correct answer: A True

Explanation

Explanation:

The relevant provision is Sub-Clause 2.4 [Employer’s Financial Arrangements].

The Employer is required to provide information concerning its financial arrangements for fulfilling its payment obligations under the Contract. If the Employer intends to make a material change to those financial arrangements that affects its ability to pay the remaining Contract Price, or is required to make such a change because of its financial situation, the Employer must immediately give Notice to the Contractor with detailed supporting particulars.

Key Elements

Material change to the Employer's financial arrangements
The change affects the Employer's ability to pay
The Employer must give Notice to the Contractor
The Notice must contain detailed supporting particulars

Reference

FIDIC Red, Yellow & Silver Books, Sub-Clause 2.4 [Employer’s Financial Arrangements]

FIDIC confirms that the 2017 Red, Yellow and Silver Books are updated editions of the corresponding 1999 forms.

Exam Tip

Remember the wording:

Material change + financial arrangements + affects ability to pay → immediate Notice + detailed supporting particulars.
Question 10 Choose 2
Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings? Choose all of the correct answers (multiple possibilities).
Show answerHide answer

Correct answer: B, D SpecificationEmployer's Requirements

Explanation

Explanation:

B. Specification
✔ Correct. The Specification is part of the Contract and may include administrative requirements such as the timetable for meetings (management, site, technical, progress). It provides detailed instructions on how the works are to be carried out, including procedural aspects like meetings.

D. Employer’s Requirements
✔ Correct. In the Yellow and Silver Books, the Employer’s Requirements document is central. It can include not only technical requirements but also administrative provisions such as planned timetables for meetings. This is especially relevant in design-build and EPC/turnkey contexts where the Employer sets out detailed expectations.

Why the Other Options Are Incorrect

A. General Conditions of Contract
✘ Incorrect. The General Conditions set out the overarching contractual framework (rights, obligations, procedures) but do not provide detailed timetables for meetings.

C. Special Conditions (Particular Conditions)
✘ Incorrect. The Particular Conditions amend or supplement the General Conditions but are not typically used to provide detailed timetables for meetings. They focus on tailoring clauses (e.g., governing law, dispute resolution, payment terms).

References
Contract administration — Specification and Employer’s Requirements as sources of procedural detail.
Full mock exam

Sit the CCM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CCM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CCM mock exam
  • —questions per mock
  • —time limit
  • 140questions in the bank
  • Newmock on every attempt
TestMayor · Independent Exam Preparation Guide

CCM Exam Syllabus: Key Subjects and Learning Objectives

FIDIC Certified Contract Manager

This guide covers FIDIC Credentialing Limited’s Certified Contract Manager programme, commonly listed as CCM or FCCM. It does not cover GAQM CCM, NCMA CCCM, healthcare credentials, or other construction-management certifications.

Use the guide to organize study across FIDIC contract selection, administration, claims, dispute resolution, and project closeout.

Exam overview

What Is the FIDIC Certified Contract Manager Exam?

The FIDIC Certified Contract Manager certification assesses experienced professionals who administer FIDIC contracts on construction and infrastructure projects. It focuses on selecting contract conditions, managing contractual mechanisms, and applying procedures throughout the project lifecycle.

Exam detailFIDIC information
CertificationFIDIC Certified Contract Manager (FCCM / CCM)
AssessmentOnline, single-phase examination
Questions100 multiple-choice questions
Duration250 minutes, completed in one sitting
FormatOpen-book assessment
Pass mark60%; FCL notes this threshold may change
Primary materialsRed, Yellow, and Silver Books (1999 and 2017); FIDIC Golden Principles (2019)
Certificate validityThree years, subject to monitoring and recertification requirements
Published syllabus weightingsNot provided in the public outline

Eligibility pathways

  • Route 1: A relevant qualification or degree, at least five years of professional experience, and at least three years managing aspects of FIDIC contracts.
  • Route 2: At least ten years of professional experience and at least three years managing aspects of FIDIC contracts.
Eligibility, application evidence, fees, and exam dates can change. Check the current FIDIC Credentialing Limited (FCL) requirements before registering.
Official Exam Blueprint

FIDIC CCM Exam Domains and Syllabus

The FIDIC Certified Contract Manager (FCCM) exam covers eight key domains related to contract management throughout the project lifecycle.

Domain 01

Project Initiation

Contract selection, project participants, risk allocation, contract conditions and procurement.

Domain 02

Pre-construction Phase

Contract agreements, commencement notices, advance payments and performance security.

Domain 03

Execution of the Works

Progress monitoring, delays, variations, suspensions and contract termination.

Domain 04

Quality Control and Assurance

Contractual quality requirements, inspections, testing and compliance.

Domain 05

Communications

Contract notices, progress meetings, reporting and communication procedures.

Domain 06

Financial Control

Payment administration, financial monitoring, final payments and discharge.

Domain 07

Claims and Dispute Resolution

Claims administration, contractual procedures and dispute management.

Domain 08

Project Closeout

Contract completion, site clearing, final obligations and return of performance security.

Exam Weightage: FIDIC does not publish individual percentage weights for these eight syllabus domains. Candidates should prepare across all domains.
Daily routine

Suggested Daily Study Schedule

A structured 5-step daily study routine featuring pentagon-shaped progression nodes for steady contract management mastery.

01

Clauses & Edition Differences

Review relevant contract clauses and edition differences.

45 minutes
02

Lifecycle Objectives

Study lifecycle objectives and procedures.

45 minutes
03

Scenario & Record Application

Apply a contract scenario or review a sample record.

30 minutes
04

Active MCQ Practice

Practice multiple-choice questions and explain each choice.

30 minutes
05

Error Log & Weak Areas

Record errors and revisit weak areas.

15 minutes
Suggested total: About 2 hours 45 minutes per study day. 165 Mins Total
TestMayor Recommendation

Suggested 30-Day CCM Study Roadmap

A clean, sequential daily revision framework designed to cover the complete FIDIC Certified Contract Manager syllabus efficiently.

Days 1–3

Project Initiation

Book selection, FIDIC Golden Principles, contract strategy, and risk allocation.

Days 4–6

Pre-construction Phase

Award, contract documents, commencement notices, advance payment, and performance security.

Days 7–12

Execution of the Works

Progress monitoring, delay damages, variation instructions, suspension, and termination procedures.

Days 13–15

Quality Control

Quality obligations, inspection protocols, testing mechanisms, and defect remedies.

Days 16–18

Communications

Notices in required form, progress meetings, monthly reporting, and project records.

Days 19–21

Financial Control

Measurement, interim payment certificates, advance payment recovery, and final account.

Days 22–25

Claims & Disputes

Claim submissions, contemporary records substantiation, DAAB adjudication, and dispute resolution.

Days 26–27

Project Closeout

Taking-over certificates, defects notification period, site clearance, and security release.

Days 28–30

Mixed Case Studies & Exam Logistics

Timed practice exam questions, scenario analysis, reviewing weak knowledge areas, 250 minutes time management practice, open-book rules review, and final exam logistics confirmation.

FIDIC CCM FAQs

Frequently Asked Questions

What is the FIDIC CCM exam? +

It assesses applied knowledge of FIDIC construction and infrastructure contract administration and the ability to handle contractual procedures across the project lifecycle.

How many questions are on the exam? +

FIDIC currently lists 100 multiple-choice questions.

How long is the exam? +

The official time allowance is 250 minutes in one sitting.

What is the required passing score? +

FCL currently lists a 60% pass mark and notes that it may change.

Which contracts should I study? +

The Red, Yellow, and Silver Books in the 1999 and 2017 editions, plus the 2019 FIDIC Golden Principles, are listed as core materials.

Does FIDIC publish percentages for each syllabus section? +

The public outline lists eight lifecycle sections but does not provide section percentages. Do not treat suggested study priorities as official exam weightings.

Is professional experience needed? +

Yes. FCL has application pathways with professional experience requirements, including experience administering aspects of FIDIC contracts. Check the current criteria before applying.

Can I prepare in 30 days? +

Thirty days is a suggested revision framework for prepared professionals, not an official minimum. Adjust it to your experience and study gaps.

How long does certification last? +

FIDIC states three years, with ongoing monitoring and recertification requirements.