Which activity involves ensuring that the composition of a projects configuration items is correct?
Show answerHide answer
Correct answer: C
Configuration Verification and Audit
Certified Associate in Project Management
Free CAPM questions on Topic 4, Volume D, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which activity involves ensuring that the composition of a projects configuration items is correct?
Correct answer: C
Configuration Verification and Audit
Change requests, project management plan updates, project document updates, and
organizational process assets updates are all outputs of which project management process?
Correct answer: B
Manage Stakeholder Expectations
Which process involves identifying and documenting the logical relationships between project
activities?
Correct answer: B
Sequence Activities
Which of the following is an example of the simplest fixed-price contract?
Correct answer: B
Purchase order
Which technique helps to determine the risks that have the most potential impact on a project?
Correct answer: D
Sensitivity analysis
Labor, materials, equipment, and supplies are examples of
Correct answer: C
Resource categories.
Analogous cost estimating relies on which of the following techniques?
Correct answer: A
Expert judgment
A method to manage stakeholder expectations in the scope statement is to clearly:
Correct answer: C
state what is out of scope.
Which type of management focuses on ensuring that projects and programs are reviewed to
prioritize resource allocation?
Correct answer: D
Portfolio
Labor, materials, equipment, and supplies are examples of:
Correct answer: C
Resource categories.