Question 21 Choose 1

Which of the following processes audits the quality requirements and the results from quality
control measures to ensure appropriate quality standards and operational definitions are used?

Show answerHide answer

Correct answer: C

Perform Quality Assurance

Question 22 Choose 1

How is the schedule variance calculated using the earned value technique?

Show answerHide answer

Correct answer: C

EV less PV

Question 23 Choose 1

Which Perform Quality Control tool graphically represents how various elements of a system
interrelate?

Show answerHide answer

Correct answer: B

Flowchart

Question 24 Choose 1

Which type of analysis is used as a general management technique within the Plan Procurements
process?

Show answerHide answer

Correct answer: B

Make or buy analysis

Question 25 Choose 1

Which of the following tools and techniques is used in the Verify Scope process?

Show answerHide answer

Correct answer: A

Inspection

Question 26 Choose 1

Define Activities and Estimate Activity Resources are processes in which project management
Knowledge Area?

Show answerHide answer

Correct answer: A

Project Time Management

Question 27 Choose 1

Which is a communication method used in the Report Performance process?

Show answerHide answer

Correct answer: D

Status review meetings

Question 28 Choose 1

Prioritizing risks for further analysis or action by assessing and combining their probability of
occurrence and impact takes place in which process?

Show answerHide answer

Correct answer: C

Perform Qualitative Risk Analysis

Question 29 Choose 1

In which process is a project manager identified and given the authority to apply resources to
project activities?

Show answerHide answer

Correct answer: D

Develop Project Charter

Question 30 Choose 1

Which of the following documents allows the project manager to assess risks that may require
near term action?

Show answerHide answer

Correct answer: C

Risk urgency assessment

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt