A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:
Show answerHide answer
Correct answer: A
Historical information and the lessons-learned database.
Certified Associate in Project Management
Free CAPM questions on Topic 3, Volume C, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:
Correct answer: A
Historical information and the lessons-learned database.
Projects are undertaken by an organization to support the:
Correct answer: D
Organizational strategy
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur
is very high (0.80)?
Correct answer: C
0.70
Which of the seven basic quality tools is especially useful for gathering attributes data while
performing inspections to identify defects?
Correct answer: D
Checksheets
The most commonly used type of precedence relationship in the precedence diagramming method
(PDM) is:
Correct answer: C
finish-to-start (FS)
Work performance information and cost forecasts are outputs of which Project Cost Management
process?
Correct answer: D
Control Costs
Which technique should a project manager use in a situation in which a collaborative approach to
conflict management is not possible?
Correct answer: B
Avoidance
The procurement process that documents agreements and related documentation for future
reference is known as:
Correct answer: C
Close Procurements.
The links between the processes in the Process Groups are often:
Correct answer: B
Iterative
The scope of a project cannot be defined without some basic understanding of how to create the
specified:
Correct answer: C
product