Question 11 Choose 1

Which Process Group's purpose is to track, review, and regulate the progress and performance of
the project; identify any areas in which changes to the plan are required; and initiate the
corresponding changes?

Show answerHide answer

Correct answer: A

Monitoring and Controlling

Question 12 Choose 1

The formal and informal interaction with others in an organization industry, or professional
environment is known as:

Show answerHide answer

Correct answer: D

networking

Question 13 Choose 1

Which process is included in the Project Integration Management Knowledge Area?

Show answerHide answer

Correct answer: D

Direct and Manage Project Work

Question 14 Choose 1

The process of identifying and documenting the specific actions to be performed to produce the
project deliverables is known as:

Show answerHide answer

Correct answer: A

Define Activities.

Question 15 Choose 1

Which document includes the project scope, major deliverables, assumptions, and constraints?

Show answerHide answer

Correct answer: B

Project scope statement

Question 16 Choose 1

When an activity cannot be estimated with a reasonable degree of confidence, the work within the
activity is decomposed into more detail using which type of estimating?

Show answerHide answer

Correct answer: A

Bottom-up

Question 17 Choose 1

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components
of which subsidiary plan?

Show answerHide answer

Correct answer: D

Risk management plan

Question 18 Choose 1

Project or phase closure guidelines or requirements, historical information, and the lessons
learned knowledge base are examples of which input to the Close Project or Phase process?

Show answerHide answer

Correct answer: A

Organizational process assets

Question 19 Choose 1

The project manager notes that stakeholders are aware of the project and potential impacts and
are actively engaged in ensuring that the project is a success. The engagement level of the
stakeholders should be classified as:

Show answerHide answer

Correct answer: B

Leading

Question 20 Choose 1

Which of the following is a narrative description of products, services, or results to be delivered by
a project?

Show answerHide answer

Correct answer: A

Project statement of work

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt