The following is a network diagram for a project
The critical path for the project is how many days in duration?
Show answerHide answer
Correct answer: D
17
Certified Associate in Project Management
Free CAPM questions on Topic 2, Volume B, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
The following is a network diagram for a project
The critical path for the project is how many days in duration?
Correct answer: D
17
The component of the human resource management plan that includes ways in which team
members can obtain certifications that support their ability to benefit the project is known as:
Correct answer: D
training needs
Stakeholders can be identified in later stages of the project because the Identify Stakeholders
process should be:
Correct answer: A
Continuous
A graphic display of project team members and their reporting relationships is known as a:
Correct answer: B
Project organization chart.
Which item is a cost of conformance?
Correct answer: A
Training
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and
relying on interpersonal skills to convince others to cooperate toward common goals?
Correct answer: D
Influencing
Activity cost estimates and the project schedule are inputs to which Project Cost Management
process?
Correct answer: D
Determine Budget
In project management, a temporary project can be:
Correct answer: C
Long in duration
Which document in the project management plan can be updated in the Plan Procurement
Management process?
Correct answer: C
Requirements documentation
Which type of probability distribution is used to represent uncertain events such as the outcome of
a test or a possible scenario in a decision tree?
Correct answer: C
Discrete
Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.