PMI certification · Exam CAPM

CAPM Mock Exam Page 3

Certified Associate in Project Management

Free CAPM questions on Topic 2, Volume B, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Topic 2, Volume B questions

21–30 of 45 free
Question 21 Choose 1

A stakeholder expresses a need not known to the project manager. The project manager most
likely missed a step in which stakeholder management process?

Show answerHide answer

Correct answer: A

Plan Stakeholder Management

Question 22 Choose 1

Skills necessary for project management such as motivating to provide encouragement; listening
actively; persuading a team to perform an action; and summarizing, recapping, and identifying
next steps are known as:

Show answerHide answer

Correct answer: C

communication skills

Question 23 Choose 1

Which tools or techniques are used during the Close Project or Phase process?

Show answerHide answer

Correct answer: C

Expert judgment and analytical techniques

Question 24 Choose 1

When a project is undertaken to reduce defects in a product or service, the objective of the project
is to create a/an:

Show answerHide answer

Correct answer: A

improvement

Question 25 Choose 1

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its
risk:

Show answerHide answer

Correct answer: D

appetite

Question 26 Choose 1

The zero duration of milestones in project planning occurs because milestones:

Show answerHide answer

Correct answer: C

Represent a moment in time such as a significant project point or event.

Question 27 Choose 1

Which type of graphic is displayed below?


Show answerHide answer

Correct answer: A

 Work breakdown structure

Question 28 Choose 1

Which tool or technique used in the Control Procurements process can be conducted during the
execution of the project to verify compliance with deliverables?

Show answerHide answer

Correct answer: B

Inspection and audits

Question 29 Choose 1

Job satisfaction, challenging work, and sufficient financial compensation are values related to
which interpersonal skill?

Show answerHide answer

Correct answer: B

Motivation

Question 30 Choose 1

The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

Show answerHide answer

Correct answer: A

10

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt