Show answerHide answer
Correct answer: B Disaster recovery plan
Explanation
ExplanationThe key function described in the question is to "restore IT infrastructure operations" after an "interruption."
Disaster Recovery Plan (DRP):
Focus:
It is a detailed, technical document that focuses specifically on recovering and restoring the organization's critical IT systems and data (servers, network, applications) to a usable state after a disaster or unplanned outage.
Goal:
The explicit goal of a DRP is to minimize downtime and meet defined Recovery Time Objectives (RTOs) and Recovery Point Objectives (RPOs).
Relevance:
This plan contains the step-by-step procedures used by the technical team to bring the failed IT infrastructure back online—the exact scenario described.
Analysis of Incorrect Options:
A. Service-level agreement (SLA):
This is a contract that defines the level of service (e.g., uptime, response time) a provider guarantees to a customer. It states what recovery targets must be met, but it is not the document that contains the technical how-to steps for the restoration process.
C. Business impact analysis (BIA):
This is a preliminary document that identifies the critical business functions and systems, assesses the impact of their loss, and determines the RTOs and RPOs. It informs the DRP and BCP, but it does not contain the actual restoration steps.
D. Business continuity plan (BCP):
This is the high-level, overarching plan that focuses on keeping the entire business (personnel, processes, facilities, etc.) operational during and after a disaster. The DRP is a subset of the BCP that focuses only on the technology (IT infrastructure) component. While the BCP is activated first to manage the crisis, the DRP is the specific document used by server administrators to perform the actual restoration of the IT infrastructure.
Reference:
CompTIA Server+ (SK0-005) emphasizes the distinction between BCP (business-focused, broader scope) and DRP (IT-focused, system restoration procedures).