Question 51 Choose 1
Why is the problem-solving workshop more effective than traditional lessons learned documents?
Show answerHide answer

Correct answer: C It makes improvements actionable through backlog items for the next Program Increment

Explanation

Explanation: The problem-solving workshop is more effective than traditional lessons learned documents because it directly translates improvements into actionable backlog items for the next Program Increment (PI). This approach aligns with the SAFe principle of relentless improvement and the Agile Manifesto’s emphasis on collaboration and working solutions.

Actionable Outcomes: The workshop format ensures that the improvements identified are not just discussed but are also captured as backlog items, making them actionable. This contrasts with lessons learned documents, which may not always lead to immediate action or change.
Engagement and Collaboration: Workshops encourage active participation and collaboration among all ART stakeholders, which is more engaging than the passive process of writing and reading documents. This engagement leads to a deeper understanding and commitment to the improvements.
Inspect and Adapt: SAFe’s Inspect and Adapt (I&A) event includes a problemsolving workshop where the current state of the Solution is demonstrated and evaluated1. This structured approach helps identify improvement backlog items in a collaborative environment.
Continuous Learning Culture: SAFe fosters a continuous learning culture where regular reflection and adaptation are key. The problem-solving workshop is a practical application of this principle, ensuring that lessons learned are immediately incorporated into the ART’s way of working1.
Lean-Agile Principles: The workshop embodies Lean-Agile principles by promoting face-to-face communication and immediate feedback, which are more effective for problem-solving than asynchronous document reviews.

In summary, the problem-solving workshop’s effectiveness lies in its ability to foster collaboration, engage stakeholders, and produce tangible, actionable items that drive continuous improvement within the ART.
Question 52 Choose 1
What is the primary purpose of PO sync?
Show answerHide answer

Correct answer: B To assess progress of the Program Increment and adjust scope and priority as needed

Explanation

Explanation: The PO Sync is a regularly scheduled event for Product Owners (POs) and product management (PMs) with several important purposes. One of the primary purposes is to provide visibility into how well the Agile Release Train (ART) is progressing towards its Program Increment (PI) objectives. This involves assessing any scope changes to work and adjusting scope and priority as needed. The PO Sync enables the RTE, PMs, and POs to inspect and adapt the plan for the current PI, ensuring that the ART is on track to achieve its objectives and making necessary adjustments to the Program Backlog1.
Question 53 Choose 3
What are the three key items communicated on the Program Board? (Choose three.)
Show answerHide answer

Correct answer: A, D, E Feature delivery datesMilestonesDependencies between teams

Explanation

Explanation: The Program Board is a visual summary of the Program Increment (PI) planning outputs and is used to communicate key aspects of the plan to stakeholders.
According to the SAFe framework, the three key items communicated on the Program Board are:

Feature delivery dates: These indicate when features are planned to be delivered within the PI.
Milestones: These are significant events or achievements that are critical to the program’s progress and are used to track alignment and progress toward the PI objectives.
Dependencies between teams: These show the relationships and interdependencies between different teams that need to be managed and coordinated to ensure smooth delivery of features.

These items are essential for creating transparency and alignment across teams and stakeholders, helping to manage risks, and facilitating the resolution of dependencies1. The Program Board helps in visualizing the work and aids in the coordination of the ART’s efforts during the PI2.
Question 54 Choose 1
How can a Release Train Engineer help unlock intrinsic motivation?
Show answerHide answer

Correct answer: A Give tough feedback supportively and be willing to be more vulnerable

Explanation

Explanation: To unlock intrinsic motivation, a Release Train Engineer (RTE) can:

Foster an Empowering Environment: Encourage knowledge workers to develop innovative and creative solutions by fostering an empowering and supportive work environment1.
Understand the Role of Compensation: Recognize that compensation is not the primary motivator for knowledge workers. Instead, focus on intellectual freedom and self-actualization1.
Leverage Autonomy, Mastery, and Purpose: Support the development of autonomy, mastery, and purpose among team members to enhance their intrinsic motivation1.
Encourage Participation and Learning: Facilitate communication across functional boundaries, fast feedback, continuous learning, and a fulfilling solution development process1.
Practice Healthy Conflict Resolution: While not directly mentioned in the context of intrinsic motivation, practicing healthy conflict resolution can contribute to a positive work environment, which indirectly supports intrinsic motivation1.

By implementing these steps, an RTE can help team members find joy and satisfaction in their work, which is the essence of intrinsic motivation.
Question 55 Choose 1
During Pl Planning, who owns Feature priorities?
Show answerHide answer

Correct answer: C Product Management

Explanation

Explanation: During Program Increment (PI) Planning in SAFe, it is the responsibility of Product Management to own the feature priorities. Product Management is tasked with defining the features, prioritizing them, and accepting the final implementation. They play a crucial role in aligning the features with the business strategy and ensuring that the development work maximizes value delivery to stakeholders. This is in line with the SAFe principle of decentralizing decision-making and empowering those closest to the value stream to make decisions regarding the prioritization of work12.
Question 56 Choose 1
Which role should the Release Train Engineer play related to a hackathon event?
Show answerHide answer

Correct answer: C Allow the teams as much flexibility as possible to promote innovation

Explanation

Explanation: The Release Train Engineer (RTE) is a servant leader and coach for the Agile Release Train (ART). One of the key responsibilities of the RTE is to facilitate ART events and processes and assist the teams in delivering value. In the context of a hackathon event, the RTE should play a role that aligns with this responsibility by allowing the teams as much flexibility as possible to promote innovation1.

This approach is consistent with the principles of the Scaled Agile Framework (SAFe), which emphasizes fostering an environment of innovation and exploration. Hackathons are typically events that encourage creativity and out-of-the-box thinking, and the RTE’s role is to support this by not imposing strict guidelines or seeking approvals for the work to be done during the hackathon. Instead, the RTE should ensure that the teams have the freedom to explore innovative solutions without being constrained by detailed guidance or pre-approved plans.

By promoting flexibility, the RTE helps to create an environment where teams can experiment and learn rapidly, which is essential for innovation. This is in line with the SAFe principle of fostering a culture of relentless improvement and a Lean-Agile mindset1.
Question 57 Choose 2
Release Train Engineers have the opportunity to regularly practice and improve which two skills? (Choose two.)
Show answerHide answer

Correct answer: A, B Servant leadershipFacilitation

Explanation

Explanation: Release Train Engineers (RTEs) practice servant leadership as they serve their Agile Release Trains (ARTs) by facilitating events, supporting teams, and coaching them to deliver value. They focus on the growth and well-being of the teams and individuals within the ART1.
B. Facilitation: RTEs regularly improve their facilitation skills as they are responsible for conducting ART events and processes. This includes facilitating Program Increment (PI) planning, where they help prepare the ART and manage the logistics of the event. Effective facilitation is crucial for the success of these events and for ensuring that teams can deliver value efficiently1.
Question 58 Choose 1
Product Management is expected to collaborate in planning the amount of upcoming Enabler work by establishing what?
Show answerHide answer

Correct answer: B Capacity allocation

Explanation

Explanation: Product Management is responsible for defining and supporting the building of desirable, feasible, viable, and sustainable products that meet customer needs over the product-market lifecycle. To do this effectively in a SAFe environment, they must collaborate with various stakeholders to determine the capacity allocation for upcoming Enabler work.

Enabler work refers to the activities that support the development of business features, such as exploration, architecture, infrastructure, and compliance. These are necessary to advance the Solution and build its architectural runway. The capacity allocation for Enabler work is a collaborative effort between Product Management, System Architects/Engineering, and other stakeholders. This ensures that sufficient capacity is allocated for both feature and enabler work, balancing the need to address technical debt, architectural advancements, and other necessary activities that enable future delivery of value.

The SAFe framework suggests a ‘capacity allocation’ approach where a certain percentage of the team’s capacity is allocated to Enabler work. This is not a fixed number but rather a guideline to ensure that teams invest in necessary work that may not directly deliver new customer features but is essential for the long-term health and adaptability of the product. By establishing a capacity allocation for Enabler work, Product Management ensures that there is a balance between delivering new features and maintaining the technical quality and flexibility of the product to adapt to future changes. This approach helps in managing the investment in Enabler work and ensures that it is not overlooked in the pursuit of immediate feature delivery.
Question 59 Choose 1
Which statement is true about the SAFe backlog model?
Show answerHide answer

Correct answer: B Features are in the Program Backlog

Explanation

Explanation: The SAFe backlog model is structured to organize work at different levels of the framework. The Program Backlog is specifically designed to hold upcoming Features that are intended to address user needs and deliver business benefits for a single Agile Release Train (ART). It also contains Enabler features necessary to build the Architectural Runway1. On the other hand, Capabilities are typically found in the Solution Backlog, which is intended to advance the Solution and may span multiple ARTs2. Stories, which are detailed implementations of work, are part of the Team Backlog3.
Question 60 Choose 1
What hourly activity helps keep teams on track and facilitates early identification of risks during the Team Breakout portion of PI Planning?
Show answerHide answer

Correct answer: B ART planning board inspection

Explanation

Explanation: During the Team Breakout portion of PI Planning, the hourly activity that helps keep teams on track and facilitates early identification of risks is the ART planning board inspection.
This activity involves reviewing the Agile Release Train (ART) planning board, which provides a visual representation of the team’s plans and progress. It allows for the identification of dependencies and risks, and ensures that all teams are aligned with the ART’s objectives. The planning board is a central tool in SAFe for maintaining synchronization among teams and providing transparency into the work being done. It is not the Iteration Review (A), which is a separate event that occurs at the end of an iteration. Coach Sync © and Business Owner feedback meeting (D) are also important activities, but they do not specifically serve the purpose of an hourly check-in during the Team Breakout sessions to keep teams on track and identify risks early1.
Full mock exam

Sit the SAFe-RTE exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real SAFe-RTE exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full SAFe-RTE mock exam
  • 65questions per mock
  • 105 mintime limit
  • 226questions in the bank
  • Newmock on every attempt