Scaled Agile certification · Exam SAFe-RTE

SAFe-RTE Mock Exam Page 4

SAFe Release Train Engineer (RTE)

Free SAFe-RTE mock exam questions 31–40, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Free SAFe-RTE questions

31–40 of 67 free
Question 31 Choose 1
What is ultimately intended to be supported by the use of a Program board?
Show answerHide answer

Correct answer: D Dependency review

Explanation

Explanation: The ultimate intent of using a Program board is to facilitate a Dependency review. The Program board helps visualize and manage dependencies across teams and features, thereby enabling better coordination and planning.
Question 32 Choose 1
What is one risk of eliminating an Innovation and Planning (IP) Iteration?
Show answerHide answer

Correct answer: D Technical debt can grow uncontrollably

Explanation

Explanation: Eliminating an Innovation and Planning (IP) Iteration can lead to uncontrollable growth in technical debt. The IP Iteration in SAFe provides a buffer for managing risks and unforeseen delays, ensuring a consistent and predictable delivery schedule. It also offers dedicated time for innovation, continuing education, PI Planning, and Inspect and Adapt (I&A) events1. Without this iteration, teams may miss out on opportunities for innovation due to the constant pressure of delivery, which can result in an accumulation of technical debt over time. This is because the focus remains on immediate feature delivery without the allocated time to address underlying issues or invest in system improvements2.
Question 33 Choose 1
What is the Scrum Master's role in team breakout #1?
Show answerHide answer

Correct answer: D Facilitate the coordination with other teams for dependencies

Explanation

Explanation: During team breakout #1, the Scrum Master’s role is to facilitate the coordination with other teams for dependencies. This involves ensuring that the team’s plans are aligned with those of other teams and that any dependencies are identified and managed appropriately. The Scrum Master works to prevent impediments that could arise from these dependencies and helps to foster a collaborative environment where teams can work together effectively1.
Question 34 Choose 1
What is the best way for the Release Train Engineer to show progress of work in the current Program Increment (PI) to management?
Show answerHide answer

Correct answer: A Conduct a System Demo

Explanation

Explanation: The best way for a Release Train Engineer (RTE) to show progress of work in the current Program Increment (PI) to management is to conduct a System Demo. This is supported by the SAFe documentation which states that the System Demo is an integral part of the PI, providing an opportunity to inspect and adapt the solutions being developed1. It serves as a platform to showcase the achievements of the Agile Release Train (ART) and allows stakeholders to provide feedback1. This event aligns with the principle of transparency and provides a clear, objective measure of progress1.
Question 35 Choose 3
Which three attributes summarize DevOps? (Choose three.)
Show answerHide answer

Correct answer: A, C, D A cultureA set of technical practicesA mindset

Explanation

Explanation: DevOps is a combination of cultural philosophies, practices, and tools that increases an organization’s ability to deliver applications and services at high velocity.
According to the information available on the SAFe website, DevOps is summarized by the following three attributes:

A Culture: DevOps represents a culture shift where product owners, development, QA, IT operations, and security work together towards a common goal, enabling fast flow of planned work into production while achieving stability, reliability, availability, and security1.
A Set of Technical Practices: It includes technical practices that support integration, automation, and collaboration needed to effectively develop and operate a solution, ensuring continuous delivery of value1.
A Mindset: DevOps is also a mindset that fosters a culture of collaboration and shared responsibility among the teams involved in the software development lifecycle, breaking down traditional silos and promoting a unified approach to achieving business goals1.

These attributes are essential for understanding the DevOps model as part of the Agile Product Delivery competency within the SAFe framework.
Question 36 Choose 1
What are two responsibilities of the Release Train Engineer during Program Increment (PI) execution? (Choose two.)
Show answerHide answer

Correct answer: A To facilitate the System Demo

Explanation

Explanation: During Program Increment (PI) execution, the Release Train Engineer (RTE) has several responsibilities that are crucial to the smooth operation and success of the Agile Release Train (ART). Two of these responsibilities are:

Facilitating the System Demo: The RTE is responsible for facilitating the System Demo, which is an event where the integrated solutions from all teams on the ART are demonstrated to stakeholders. This event provides an objective measure of progress and allows for feedback that can be incorporated into future iterations.
Escalating and Tracking Impediments: The RTE plays a key role in ensuring that impediments affecting the ART’s progress are addressed promptly. They are responsible for escalating these impediments to the necessary parties and tracking them until they are resolved, ensuring that the ART can continue to deliver value without unnecessary delays.

These responsibilities are aligned with the RTE’s role as a servant leader and coach within the SAFe framework, where they support the ART in delivering value and driving continuous improvement. By facilitating the System Demo, the RTE helps maintain transparency and alignment with stakeholders. Meanwhile, by managing impediments, they ensure that the teams can focus on their work with minimal blockers.
Question 37 Choose 2
What are two ways program risks can be categorized? (Choose two.)
Show answerHide answer

Correct answer: C, E DeferredOwned

Explanation

Explanation: Program risks can be categorized based on whether they are Deferred or Owned. A deferred risk is one that has been identified but is not being actively addressed at the moment, possibly due to prioritization of other risks or resource constraints. An owned risk is one that has been assigned to an individual or team who is responsible for managing and mitigating the risk. This categorization helps in tracking and accountability within the SAFe framework.
Question 38 Choose 1
Which of the following is true about the ART sync event?
Show answerHide answer

Correct answer: B It is a combination of PO-sync and Scrum of Scrums events

Explanation

Explanation: The ART Sync event is a combination of PO-sync and Scrum of Scrums events. It is used to coordinate progress across the Agile Release Train, involving Scrum Masters/Team Coaches, Product Owners, and other select team members to discuss progress, impediments, scope, and priority adjustments.
Question 39 Choose 1
The Release Train Engineer (RTE) learns the teams feel the business value needs to reflect the effort and progress. What is one technique the RTE can use to provide the Business Owners a better understanding of the value the teams have created?
Work with the team to ensure they are actively involved when the Business Owners score the business value achieved Educate teams that business value provides the Enterprise with a metric of how fast the team executed work during the PI Deliverable
Show answerHide answer

Correct answer: A Illustrate the link between business values and the market communications/release objectives tied to the three to six-month Enterprise Strategy

Explanation

Explanation: The Release Train Engineer (RTE) can employ several techniques to ensure that the business value reflects the teams’ effort and progress. One effective method is to involve the teams actively when the Business Owners score the business value achieved. This collaborative approach allows for a more accurate reflection of the value created by the teams and ensures that the Business Owners have a better understanding of the contributions made by the teams1.

During the Inspect and Adapt (I&A) event at the end of each Program Increment (PI), Business Owners collaborate with each Agile Team to score the actual business value achieved for each of their Team PI Objectives1. This scoring process is crucial as it helps quantify the efforts of the teams in terms of business value, aligning the outcomes with the enterprise’s objectives.

By facilitating this active involvement, the RTE can help bridge the gap between the teams’ perception of effort and the Business Owners’ assessment of value, leading to a more balanced and fair evaluation of the teams’ work. This technique also fosters a sense of ownership and accountability among team members, as they have a direct influence on how their work is valued and recognized within the organization.
Question 40 Choose 1
What is an example of Scrum Master servant leader behavior?
Show answerHide answer

Correct answer: D Uses persuasion instead of authority

Explanation

Explanation: In the SAFe framework, a Scrum Master exemplifies servant leadership by using persuasion rather than authority to lead the team. This approach aligns with the core principles of servant leadership, which emphasize serving the team, fostering collaboration, and empowering team members to self-organize and self-manage.

A Scrum Master who uses persuasion instead of authority:

Encourages the team to collaborate on solutions and respects their ability to selfmanage.
Helps the team to understand the ‘why’ behind decisions and actions, which promotes buy-in and commitment.
Facilitates discussions that lead to consensus and shared understanding, rather than dictating terms or solutions.
Empowers team members to take ownership of their work and the processes they follow, leading to a more engaged and motivated team.

This behavior is crucial for creating a high-performing Agile team that is capable of navigating complex challenges and delivering value effectively. By focusing on persuasion, a Scrum Master supports the team’s growth and development, ensuring that they are equipped to achieve their goals within the SAFe framework1.
Full mock exam

Sit the SAFe-RTE exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real SAFe-RTE exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full SAFe-RTE mock exam
  • 65questions per mock
  • 105 mintime limit
  • 226questions in the bank
  • Newmock on every attempt