Question 21 Choose 1
Who provides Agile Release Train context and Vision during Pl Planning?
Show answerHide answer

Correct answer: B Product Management

Question 22 Choose 1
During Program Increment (PI) Planning, a scrum of scrums occurs just before the draft plan review. The Scrum Master from one team raises an issue that one of the Product Managers just showed up to the planning area with a priority wish list of items. These items do not align with the Feature prioritization. What is the most likely planning anti-pattern causing this sudden impediment?
Show answerHide answer

Correct answer: C Prioritization by Product Management was performed autonomously not collaboratively

Question 23 Choose 1
Which tool is useful in facilitating scrum of scrums meetings?
Show answerHide answer

Correct answer: C Program board

Question 24 Choose 1
In the SAFe work item hierarchy, Epics are decomposed into what?
Show answerHide answer

Correct answer: A Features

Question 25 Choose 1
In order to evolve the role of a leader in SAFe, which practices can the Release Train Engineer (RTE) recommend?
Show answerHide answer

Correct answer: D Encourage personal development

Explanation

Explanation: The Release Train Engineer (RTE) plays a crucial role as a servant leader and coach within the SAFe framework. To evolve the role of a leader, the RTE can recommend practices that foster personal development. This aligns with the principles of SAFe which emphasize lifelong learning and growth. Encouraging personal development helps leaders and team members to continuously improve their skills, adapt to new challenges, and contribute effectively to the organization’s goals. This approach is supported by the SAFe principle of unlocking the intrinsic motivation of knowledge workers, which includes promoting personal and career development12.
Question 26 Choose 1
The goal of Lean is to deliver the maximum customer value in the shortest sustainable lead time while providing what else?
Show answerHide answer

Correct answer: A The highest possible quality

Explanation

Explanation: The goal of Lean within the context of SAFe is to deliver the maximum customer value in the shortest sustainable lead time while maintaining the highest possible quality. This is achieved by optimizing the flow of value through the Continuous Delivery Pipeline and by ensuring that all steps in the process contribute to the creation of value. The focus on quality is integral to Lean because it ensures that the products or services delivered are not only fast and efficient but also meet the customer’s needs and expectations1234.
Question 27 Choose 1
What information is covered during the final plan review?
Show answerHide answer

Correct answer: C Changes to capacity and load, final PI Objectives, ART PI Risks, and impediments

Explanation

Explanation: During the final plan review of the Program Increment (PI) Planning, the teams cover several critical pieces of information. This includes any changes to team capacity and load, which may affect the delivery of PI Objectives. The final PI Objectives are reviewed to ensure alignment with the ART’s goals. Additionally, ART PI Risks are addressed, including any new risks identified during the planning process, and existing risks that have been ROAMed (Resolved, Owned, Accepted, Mitigated). Lastly, any impediments that could hinder the ART’s progress are discussed, ensuring that they are acknowledged and addressed appropriately. This comprehensive review is essential for the ART to commit to a set of PI Objectives that are achievable and aligned with the overall strategy1.
Question 28 Choose 1
How are the 5 Whys used?
Show answerHide answer

Correct answer: D To identify a root cause(s) of a problem

Explanation

Explanation: The “5 Whys” is a problem-solving technique used to explore the cause-and effect relationships underlying a particular problem. Its primary goal is to determine the root cause of a defect or problem by repeating the question “Why?” five times. Each answer forms the basis of the next question. In the context of SAFe 6 Release Train Engineer, the 5 Whys are utilized within the Lean-Agile principles to drive relentless improvement by identifying the root causes of impediments and issues that may be affecting the Agile Release Train’s (ART) performance. This method helps in creating a culture of transparency and continuous improvement, which is essential for the successful execution of SAFe1.
Question 29 Choose 1
In what way is a value stream map different from a process flow?
Show answerHide answer

Correct answer: B A value stream map measures the flow of value and identifies bottlenecks for improvement

Explanation

Explanation: A value stream map is a lean-management method used for analyzing the current state and designing a future state for the series of events that take a product or service from its beginning through to the customer. It differs from a process flow in several ways:

Focus on Value: A value stream map specifically measures the flow of value through a process, from start to finish. It identifies every step in a process and categorizes them into value-adding and non-value-adding activities1.
Identification of Waste: It goes beyond just mapping the steps by also identifying and quantifying waste in the process. This includes any activity that consumes resources but does not add value to the product or service1.
Bottlenecks and Improvements: The map is used to pinpoint bottlenecks and areas for improvement, which can lead to more efficient processes and reduced lead times2.
Operational and Developmental: While process flows are typically operational, showing the sequence of steps for a particular operation, value stream maps can be both operational and developmental. They can map out the flow for developing new products or services, not just the operation of existing ones1.
Solution Context: Although a value stream map can be used to define the Solution Context, which is the environment that influences the development of a solution, this is not what primarily differentiates it from a process flow2.

In summary, a value stream map is a more comprehensive tool than a process flow chart because it not only maps out the steps but also focuses on improving the flow of value by identifying and eliminating waste.
Question 30 Choose 1
Program Increment (PI) Objectives should be written in the SMART format. What does the "R" in SMART stand for?
Show answerHide answer

Correct answer: A Realistic

Explanation

Explanation: The “R” in the SMART criteria for writing Program Increment (PI) Objectives stands for “Realistic.” This means that the objectives should be set in a way that can be realistically achieved within the given time and resources. It’s important that the objectives are challenging yet attainable, as setting unrealistic goals can lead to disappointment and a lack of motivation among team members. The SMART criteria help ensure that the objectives are specific, measurable, achievable, realistic, and time-bound, which is essential for the successful execution of PI objectives within the SAFe framework.
Full mock exam

Sit the SAFe-RTE exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real SAFe-RTE exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full SAFe-RTE mock exam
  • 65questions per mock
  • 105 mintime limit
  • 226questions in the bank
  • Newmock on every attempt