Question 41 Choose 1
Enabler Epics are used to advance what in order to support upcoming Business Epics?
Show answerHide answer

Correct answer: C The Architectural Runway

Explanation

Explanation: Enabler Epics within the SAFe framework are designed to advance the Architectural Runway. This is crucial for supporting upcoming Business Epics by ensuring that the necessary technical infrastructure and architecture are in place to facilitate the smooth development and delivery of business value.
The Architectural Runway provides the necessary technical foundation that allows Agile Release Trains (ARTs) to implement new features without excessive delays and rework. Enabler Epics contribute to this runway by addressing technical debt, establishing new infrastructure, and ensuring that the system’s architecture can support future business functionality1.
By focusing on the Architectural Runway, Enabler Epics help maintain and extend the system’s capacity to incorporate new features and capabilities, which is essential for the long-term adaptability and scalability of the enterprise solution2.
Question 42 Choose 1
Which event facilitated by the Release Train Engineer is designed to keep the Agile Release Train on the tracks?
Show answerHide answer

Correct answer: D Scrum of scrums

Explanation

Explanation: This event allows multiple teams to coordinate and work together to deliver complex solutions1. It’s a scaled agile method that helps ensure alignment and collaboration among the teams1.
Question 43 Choose 2
Program Increment (PI) Planning is a major event that requires preparation, coordina-tion, and communication. What are two key areas a Release Train Engineer should focus on to support a successful PI Planning event? (Choose two.)
Show answerHide answer

Correct answer: A, D Organizational readiness - Strategic alignment; roles, teams, and train setupFacilities readiness - Space and logistics for the event

Explanation

Explanation: The Release Train Engineer (RTE) is responsible for ensuring that the Agile Release Train (ART) is prepared for the Program Increment (PI) Planning event. This involves a focus on several key areas to support a successful event:

Organizational Readiness: The RTE must ensure that the organization is strategically aligned with the goals of the PI Planning. This includes confirming that the roles are clearly defined, teams are properly formed, and the train setup is conducive to collaboration and communication1. Organizational readiness ensures that everyone involved understands the context and objectives of the PI Planning, facilitating a more efficient and effective event.
Facilities Readiness: The logistics of the PI Planning event are critical. The RTE should ensure that the space and logistics are well-managed to support the event1. This includes arranging the physical or virtual space where the PI Planning will take place, ensuring that it is equipped with the necessary tools and technology, and that it can accommodate all participants comfortably. Proper facilities readiness helps in creating an environment that is conducive to collaboration and minimizes disruptions during the event.

These two areas are essential for the RTE to focus on as they directly impact the ability of the ART to effectively plan and execute the PI. Organizational readiness aligns the teams and stakeholders, while facilities readiness ensures that the event can proceed without logistical issues. Together, they create the foundation for a successful PI Planning event.
Question 44 Choose 1
Which statement is true about scrum?
Show answerHide answer

Correct answer: B lt is a team-based framework

Explanation

Explanation: Scrum is indeed a team-based framework used to implement Agile development. The key characteristics of Scrum include its use of cross-functional teams, iterative development cycles called sprints, and regular reflection and adaptation sessions. It is designed to accommodate changes in requirements and encourages close collaboration between the development team and stakeholders to deliver the highest value product increments1.

In the context of SAFe, Scrum is integrated into the framework as one of the primary methods for Agile teams to manage their work. SAFe expands upon the Scrum framework by providing additional roles, events, and artifacts to support the coordination and alignment of multiple teams within an Agile Release Train (ART). This ensures that teams work together effectively towards common objectives, facilitating the delivery of large-scale solutions in an enterprise environment1.

The Release Train Engineer (RTE) plays a crucial role in this process by facilitating ART events and processes, supporting teams in delivering value, and driving relentless improvement. The RTE helps to ensure that the Scrum framework is applied consistently across teams and that the principles of Lean and Agile are upheld within the ART1.
Question 45 Choose 1
What is one benefit of an Iteration and PI calendar?
Show answerHide answer

Correct answer: C Ability to visualize the ART cadence and synchronization

Explanation

Explanation: The Iteration and PI (Program Increment) calendar is a tool used within the SAFe (Scaled Agile Framework) to help visualize the timing of the iterations and PIs for an Agile Release Train (ART). This visualization is crucial for several reasons:

1.Cadence and Synchronization: The calendar helps all teams involved in the ART to align on a common cadence, which is the rhythm of the iterations and PIs. This alignment ensures that all teams are working in sync, which is essential for the ART to function effectively as a whole1.
2.Facilitating PI Planning: The Iteration and PI calendar is used during PI planning to help teams understand when iterations will begin and end, which aids in the planning of work and the setting of objectives2.
3.Visualizing ART Events: The calendar provides a visual representation of all the key events in the ART’s timeline, including iterations, PIs, and IP iterations (Innovation and Planning iterations), which are essential for continuous learning and improvement3.
4.Supporting Predictability: By visualizing the ART’s cadence and synchronization, the Iteration and PI calendar supports better predictability in delivery and helps manage stakeholders’ expectations1.

5.Enabling Relentless Improvement: The calendar also supports the SAFe principle of relentless improvement by making it clear when the ART will have time to reflect on the past PI and identify areas for improvement3.
Question 46 Choose 1
Which statement is true about estimating Features using Story points?
Show answerHide answer

Correct answer: A More than one team may be involved in the estimation

Explanation

Explanation: According to the SAFe framework, when estimating features using story points, it is true that more than one team may be involved in the estimation process. This collaborative approach encourages teams to work together to assess the complexity and effort required to implement a feature. The estimation process is not restricted to a single team or solely to Product Managers; instead, it involves multiple teams that may contribute to the feature’s development. This aligns with the principles of SAFe, which emphasize cross-team collaboration and alignment to ensure that features are estimated accurately and that all relevant perspectives are considered1.
Question 47 Choose 1
What action can result in reduced collaboration between teams during the Program Increment (PI) Planning event?
Show answerHide answer

Correct answer: C Start the Agile Release Train without a System Team in place

Explanation

Explanation: Starting an Agile Release Train (ART) without a System Team in place can lead to reduced collaboration between teams during the Program Increment (PI) Planning event. The System Team plays a vital role in supporting the ART by addressing system-level issues and enabling integration across different teams. Without this support, teams may face challenges in integrating their work with others, leading to silos and reduced collaboration. The presence of a System Team is essential for facilitating effective communication and collaboration during PI Planning, ensuring that teams can work together efficiently and that dependencies are managed properly12.
Question 48 Choose 1
What does assigning business value to a team's Pl Objectives influence?
Show answerHide answer

Correct answer: A How teams plan the implementation

Explanation

Explanation: Assigning business value to PI Objectives influences how teams plan the implementation of these objectives. During PI Planning, teams create PI objectives they intend to accomplish in the upcoming PI. These objectives provide a common language for communicating with business and technology stakeholders, create a near-term focus and vision, enable the ART to assess its performance and the business value achieved, and expose dependencies that require coordination. By assigning business value, teams can prioritize their work based on the relative importance of each objective, which directly affects how they plan their implementation efforts. This process helps to ensure alignment with business goals and facilitates a more effective and efficient approach to achieving the desired outcomes1.
Question 49 Choose 1
In the SAFe work item hierarchy, Features are decomposed into what?
Show answerHide answer

Correct answer: A Stories

Explanation

Explanation: In the SAFe work item hierarchy, Features are indeed decomposed into Stories. This is supported by the information found in the SAFe Requirements Model, which outlines that a Feature is described by a phrase, benefit hypothesis, and acceptance criteria, while a Story is elaborated by a user-voice statement and acceptance criteria. These artifacts replace the traditional system and requirements specifications with new paradigms based on Lean-Agile development. Stories are the primary artifact used to define system behavior in Agile and are short, simple descriptions of functionality told from the user’s perspective and written in their language. Each implements a small, vertical slice of system behavior. The detailed implementation work is expressed through stories, which comprise the Team Backlog12.
Question 50 Choose 1
What is the name of the event where all team members determine how much of the team's backlog they can commit to delivering during an upcoming Iteration?
Show answerHide answer

Correct answer: C lteration planning

Explanation

Explanation: The event where all team members determine how much of the team’s backlog they can commit to delivering during an upcoming Iteration is known as Iteration Planning. This is a core event in the Scaled Agile Framework (SAFe) where teams select stories from the Team Backlog and commit to executing a set of them in the upcoming Iteration. The purpose of Iteration Planning is to organize the work and define a realistic scope for the Iteration, ensuring that the team’s capacity and the complexity, size, and dependencies of each story are considered1.
During Iteration Planning, the following activities take place:
The Product Owner (PO) typically starts the event by presenting high-priority stories from the Team Backlog and any preliminary Iteration Goals.
The team then collaborates to define, organize, and commit to the work for the next Iteration, summarizing this work as a set of committed Iteration Goals.
The Iteration Planning meeting is timeboxed to ensure focus and efficiency, and it results in a clear commitment from the team to the Iteration Goals1.
This event is distinct from Backlog Refinement, Solution Planning, and Solution Demo, which serve different purposes within the SAFe framework. Iteration Planning is specifically about the commitment to the Iteration’s delivery and is the first event of the Iteration1.
Full mock exam

Sit the SAFe-RTE exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real SAFe-RTE exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full SAFe-RTE mock exam
  • 65questions per mock
  • 105 mintime limit
  • 226questions in the bank
  • Newmock on every attempt