Enabler Epics are used to advance what in order to support upcoming Business Epics?
Show answerHide answer
Correct answer: CThe Architectural Runway
Explanation
Explanation: Enabler Epics within the SAFe framework are designed to advance the
Architectural Runway. This is crucial for supporting upcoming Business Epics by ensuring
that the necessary technical infrastructure and architecture are in place to facilitate the
smooth development and delivery of business value.
The Architectural Runway provides the necessary technical foundation that allows Agile
Release Trains (ARTs) to implement new features without excessive delays and
rework. Enabler Epics contribute to this runway by addressing technical debt, establishing
new infrastructure, and ensuring that the system’s architecture can support future business
functionality1.
By focusing on the Architectural Runway, Enabler Epics help maintain and extend the
system’s capacity to incorporate new features and capabilities, which is essential for the
long-term adaptability and scalability of the enterprise solution2.
Question 42Choose 1
Which event facilitated by the Release Train Engineer is designed to keep the Agile Release
Train on the tracks?
Show answerHide answer
Correct answer: DScrum of scrums
Explanation
Explanation: This event allows multiple teams to coordinate and work together to deliver
complex solutions1. It’s a scaled agile method that helps ensure alignment and
collaboration among the teams1.
Question 43Choose 2
Program Increment (PI) Planning is a major event that requires preparation, coordina-tion,
and communication. What are two key areas a Release Train Engineer should focus on to
support a successful PI Planning event? (Choose two.)
Show answerHide answer
Correct answer: A, DOrganizational readiness - Strategic alignment; roles, teams, and train setupFacilities readiness - Space and logistics for the event
Explanation
Explanation: The Release Train Engineer (RTE) is responsible for ensuring that the Agile
Release Train (ART) is prepared for the Program Increment (PI) Planning event. This
involves a focus on several key areas to support a successful event:
Organizational Readiness: The RTE must ensure that the organization is
strategically aligned with the goals of the PI Planning. This includes confirming that
the roles are clearly defined, teams are properly formed, and the train setup is
conducive to collaboration and communication1. Organizational readiness ensures
that everyone involved understands the context and objectives of the PI Planning,
facilitating a more efficient and effective event.
Facilities Readiness: The logistics of the PI Planning event are critical. The RTE
should ensure that the space and logistics are well-managed to support the
event1. This includes arranging the physical or virtual space where the PI Planning
will take place, ensuring that it is equipped with the necessary tools and
technology, and that it can accommodate all participants comfortably. Proper
facilities readiness helps in creating an environment that is conducive to
collaboration and minimizes disruptions during the event.
These two areas are essential for the RTE to focus on as they directly impact the ability of
the ART to effectively plan and execute the PI. Organizational readiness aligns the teams
and stakeholders, while facilities readiness ensures that the event can proceed without
logistical issues. Together, they create the foundation for a successful PI Planning event.
Question 44Choose 1
Which statement is true about scrum?
Show answerHide answer
Correct answer: Blt is a team-based framework
Explanation
Explanation: Scrum is indeed a team-based framework used to implement Agile
development. The key characteristics of Scrum include its use of cross-functional teams,
iterative development cycles called sprints, and regular reflection and adaptation
sessions. It is designed to accommodate changes in requirements and encourages close collaboration between the development team and stakeholders to deliver the highest value
product increments1.
In the context of SAFe, Scrum is integrated into the framework as one of the primary
methods for Agile teams to manage their work. SAFe expands upon the Scrum framework
by providing additional roles, events, and artifacts to support the coordination and
alignment of multiple teams within an Agile Release Train (ART). This ensures that teams
work together effectively towards common objectives, facilitating the delivery of large-scale
solutions in an enterprise environment1.
The Release Train Engineer (RTE) plays a crucial role in this process by facilitating ART
events and processes, supporting teams in delivering value, and driving relentless
improvement. The RTE helps to ensure that the Scrum framework is applied consistently
across teams and that the principles of Lean and Agile are upheld within the ART1.
Question 45Choose 1
What is one benefit of an Iteration and PI calendar?
Show answerHide answer
Correct answer: CAbility to visualize the ART cadence and synchronization
Explanation
Explanation:
The Iteration and PI (Program Increment) calendar is a tool used within the SAFe (Scaled
Agile Framework) to help visualize the timing of the iterations and PIs for an Agile Release
Train (ART). This visualization is crucial for several reasons:
1.Cadence and Synchronization: The calendar helps all teams involved in the ART to align
on a common cadence, which is the rhythm of the iterations and PIs. This alignment
ensures that all teams are working in sync, which is essential for the ART to function
effectively as a whole1.
2.Facilitating PI Planning: The Iteration and PI calendar is used during PI planning to help
teams understand when iterations will begin and end, which aids in the planning of work
and the setting of objectives2.
3.Visualizing ART Events: The calendar provides a visual representation of all the key
events in the ART’s timeline, including iterations, PIs, and IP iterations (Innovation and
Planning iterations), which are essential for continuous learning and improvement3.
4.Supporting Predictability: By visualizing the ART’s cadence and synchronization, the Iteration and PI calendar supports better predictability in delivery and helps manage
stakeholders’ expectations1.
5.Enabling Relentless Improvement: The calendar also supports the SAFe principle of
relentless improvement by making it clear when the ART will have time to reflect on the
past PI and identify areas for improvement3.
Question 46Choose 1
Which statement is true about estimating Features using Story points?
Show answerHide answer
Correct answer: AMore than one team may be involved in the estimation
Explanation
Explanation: According to the SAFe framework, when estimating features using story
points, it is true that more than one team may be involved in the estimation process. This
collaborative approach encourages teams to work together to assess the complexity and
effort required to implement a feature. The estimation process is not restricted to a single
team or solely to Product Managers; instead, it involves multiple teams that may contribute
to the feature’s development. This aligns with the principles of SAFe, which emphasize
cross-team collaboration and alignment to ensure that features are estimated accurately
and that all relevant perspectives are considered1.
Question 47Choose 1
What action can result in reduced collaboration between teams during the Program
Increment (PI) Planning event?
Show answerHide answer
Correct answer: CStart the Agile Release Train without a System Team in place
Explanation
Explanation:
Starting an Agile Release Train (ART) without a System Team in place can lead to reduced collaboration between teams during the Program Increment (PI) Planning event. The
System Team plays a vital role in supporting the ART by addressing system-level issues
and enabling integration across different teams. Without this support, teams may face
challenges in integrating their work with others, leading to silos and reduced
collaboration. The presence of a System Team is essential for facilitating effective
communication and collaboration during PI Planning, ensuring that teams can work
together efficiently and that dependencies are managed properly12.
Question 48Choose 1
What does assigning business value to a team's Pl Objectives influence?
Show answerHide answer
Correct answer: AHow teams plan the implementation
Explanation
Explanation: Assigning business value to PI Objectives influences how teams plan the
implementation of these objectives. During PI Planning, teams create PI objectives they
intend to accomplish in the upcoming PI. These objectives provide a common language for
communicating with business and technology stakeholders, create a near-term focus and
vision, enable the ART to assess its performance and the business value achieved, and
expose dependencies that require coordination. By assigning business value, teams can
prioritize their work based on the relative importance of each objective, which directly
affects how they plan their implementation efforts. This process helps to ensure alignment
with business goals and facilitates a more effective and efficient approach to achieving the
desired outcomes1.
Question 49Choose 1
In the SAFe work item hierarchy, Features are decomposed into what?
Show answerHide answer
Correct answer: AStories
Explanation
Explanation: In the SAFe work item hierarchy, Features are indeed decomposed into
Stories. This is supported by the information found in the SAFe Requirements Model, which
outlines that a Feature is described by a phrase, benefit hypothesis, and acceptance
criteria, while a Story is elaborated by a user-voice statement and acceptance criteria.
These artifacts replace the traditional system and requirements specifications with new
paradigms based on Lean-Agile development. Stories are the primary artifact used to
define system behavior in Agile and are short, simple descriptions of functionality told from
the user’s perspective and written in their language. Each implements a small, vertical slice
of system behavior. The detailed implementation work is expressed through stories, which
comprise the Team Backlog12.
Question 50Choose 1
What is the name of the event where all team members determine how much of the team's
backlog they can commit to delivering during an upcoming Iteration?
Show answerHide answer
Correct answer: Clteration planning
Explanation
Explanation: The event where all team members determine how much of the team’s
backlog they can commit to delivering during an upcoming Iteration is known as Iteration
Planning. This is a core event in the Scaled Agile Framework (SAFe) where teams select
stories from the Team Backlog and commit to executing a set of them in the upcoming
Iteration. The purpose of Iteration Planning is to organize the work and define a realistic
scope for the Iteration, ensuring that the team’s capacity and the complexity, size, and
dependencies of each story are considered1.
During Iteration Planning, the following activities take place:
The Product Owner (PO) typically starts the event by presenting high-priority
stories from the Team Backlog and any preliminary Iteration Goals.
The team then collaborates to define, organize, and commit to the work for the
next Iteration, summarizing this work as a set of committed Iteration Goals.
The Iteration Planning meeting is timeboxed to ensure focus and efficiency, and it
results in a clear commitment from the team to the Iteration Goals1.
This event is distinct from Backlog Refinement, Solution Planning, and Solution Demo,
which serve different purposes within the SAFe framework. Iteration Planning is specifically
about the commitment to the Iteration’s delivery and is the first event of the Iteration1.