Regarding the process described above, what is the most important recommendation you
would make using IEEE 1044 as a guide? 2 credits
Show answerHide answer
Correct answer: A
No priority or severity assigned
ISTQB Certified Tester Foundation Level
Free CTFL-Foundation mock exam questions 21–30, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Regarding the process described above, what is the most important recommendation you
would make using IEEE 1044 as a guide? 2 credits
Correct answer: A
No priority or severity assigned
Given is the following defect removal chart reported at the end of system testing - showing
total defects detected and closed defects (fixed and successfully retested). A number of
open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase? 1 credit
Correct answer: D
Another system test cycle to verify defect resolution
When assembling a test team to work on an enhancement to an existing system, which of
the following has the highest level of test independence?
Correct answer: D
A contract tester who has never worked for the organization before.
In this scenario, the contract tester who has never worked for the organization before has
the highest level of test independence. The three others are less independent as they are
likely to make assumptions based on their previous knowledge of the requirements, code
and general functionality of the original system.
Note that independence does not necessarily equate to most useful. In practice most test
or project managers would recruit a permanent tester who has worked on the original
system in preference to a contract tester with no knowledge of the system. However, when
assembling a team it would be useful to have staff with varying levels of test independence
Consider the following pseudo code:
1 Begin
2 Read Time
3 If Time < 12 Then
4 Print(Time, "am")
5 Endif
6 If Time > 12 Then
7 Print(Time 12, "pm")
8 Endif
9 If Time = 12 Then
10 Print (Time, "noon")
11 Endif
12 End
How many test cases are needed to achieve 100 per cent decision coverage?
Correct answer: C
3
The three decisions are in sequence and the conditions are all mutually exclusive (if any
one is true the others must be false). Hence a test case that makes the first decision true
will make the second and third decisions false and so on.
So test case 1 (say Time = 6) would exercise the path True, False, False, test case 2 (say
Time = 15) would exercise the path False, True, False. Test case 3 would have to be Time
= 12. This combination achieves 100 per cent decision coverage because each decision
has been exercised through its true and its false outcomes.
Acceptance test cases are based on what?
Correct answer: A
Requirements
What should be the MAIN objective during development testing?
Correct answer: A
To cause as many failures as possible so that defects in the software are identified and
can be fixed
Which statement correctly describes the public and profession aspects of the code of
ethics?
Correct answer: D
Public: Certified software testers shall consider the wider public interest in their actions.
Profession: Certified software testers shall advance the integrity and reputation of their
industry consistent with the public interest.
All other answers contain an activity identified as analysis and design that is part of
implementation and test execution.
Which of the following terms is used to describe the management of software components
comprising an integrated system?
Correct answer: A
Configuration management
Incident management is the collection and processing of incidents raised when errors and
defects are discovered. Test monitoring identifies the status of the testing activity on a
continuous basis. Risk management identifies, analyses and mitigates risks to the project
and the product. Configuration management is concerned with the management of
changes to software components and their associated documentation and testware.
Which of the following pairs of test tools are likely to be most useful during the test analysis
and design stage of the fundamental test process?
(i) Test execution tool
(ii) Test data preparation tool
(iii) Test management tool
(iv) Requirements management tool
Correct answer: D
(iii) and (iv)
Which of the following is usually the test basis for integration testing?
Correct answer: C
Technical specification
Option (A) is used for unit testing.
Option (B) is used for system testing and
Option (D) is used for acceptance testing.
Full-length mocks with the same number of questions and the same time limit as the real CTFL-Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full CTFL-Foundation mock exam