Test script TransVal 3.1 tests transaction validation via screen TRN 003B. According to the
specification (PID ver 1.3 10b iv) the validation screen should not accept future dated
transactions. Test script TransVal 3.1 passes. Test script eod 1.4 tests end of day
processing and is run after the execution of TransVal 3.1 using data entered during that
test
Which of the following is the BEST detail on an incident report? [K3]
Show answerHide answer
Correct answer: D
Title. Screen TRN-003B validation of transaction date. Reproducible. Yes. Description.
Script eod 1.4 fails when the first transaction of the day is a future dated transaction.
Screen shot of the failure attached. Validation of transaction entry on screen TRN-003B
should not allow future dated transactions – see PID ver 1.3 para 10b iv.