The development manager is managing the review of the responses received from bidders,
and has asked the in-house test manager to provide a review checklist for the test
management aspects of the responses. Which of the following checkpoints would be
appropriate? 2 credits
Show answerHide answer
Correct answer: D
The bidder’s project test plan depicts a phased implementation with later delivery dates
to be confirmed and states that test deliverables will be developed using IEEE 829 as a
Question No : 54 - (Topic 16)