In general, why is it NOT a good idea to estimate the testing effort based only on a
percentage of development effort? Identify THREE valid reasons. 1 credit
Show answerHide answer
Correct answer: A, D, E
The quality of the development estimate may be poor. Using the same percentage every time does not address the level of risk of the The maturity of the organization, e.g. the quality of the test basis, quality of development
application to be tested.
testing, configuration management, availability of test tools, also influence the effort needed
for testing.