PMI certification · Exam CAPM

CAPM Mock Exam Page 2

Certified Associate in Project Management

Free CAPM questions on Topic 6: Volume F, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Topic 6: Volume F questions

11–20 of 25 free
Question 11 Choose 1

During the planning phase, a project manager must create a work breakdown structure
(WBS) to improve management of the project's components. What should be included in
the WBS?

Show answerHide answer

Correct answer: C

Description of work

Question 12 Choose 1

The project manager is working with some functional managers and stakeholders on the
resource management plan Which elements may be included in this plan?

Show answerHide answer

Correct answer: D

Resource requirements, resource assignments, and team performance assessments

Question 13 Choose 1

Which are inputs for the Plan Quality Management process?

Show answerHide answer

Correct answer: C

Project management plan, project documents, and organizational process assets

Question 14

Which statement is related to the project manager's sphere of influence at the
organizational level?

Show answerHide answer

Correct answer: A

A project manager interacts with other project managers to detect common interests and
impacts between their projects.

Question 15 Choose 1

When project requirements are documented in user stones then prioritized and refined just
prior to construction, which approach is being used for scheduling?

Show answerHide answer

Correct answer: A

Iterative scheduling with backlog

Question 16 Choose 1

A project stakeholder is requesting changes to the project plan. Which process group
addresses this?

Show answerHide answer

Correct answer: D

Monitoring and Controlling Process Group

Question 17 Choose 1

To which knowledge area does the Collect Requirements process belong?

Show answerHide answer

Correct answer: B

Scope Management

Question 18 Choose 1

Which of the following lists represents the outputs of the Monitor Communications process?

Show answerHide answer

Correct answer: B

Work performance information, change requests, project management plan updates,
and project documents updates

Question 19 Choose 1

Which of the following are outputs from the process of creating a work breakdown structure
(WBS)?

Show answerHide answer

Correct answer: B

Scope baseline and project documents update

Question 20 Choose 1

Which are examples of processes that may be used once or at predefined points in the
project life cycle?

Show answerHide answer

Correct answer: A

Develop Project Charter and Close Project or Phase

Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt