Question 21 Choose 1

Projects are separated into phases or subprojects; these phases include:

Show answerHide answer

Correct answer: A

feasibility study, concept development, design, and prototype.

Question 22 Choose 1

In which type of contract are the performance targets established at the onset and the final
contract price determined after completion of all work based on the sellers performance?

Show answerHide answer

Correct answer: C

Fixed-Price-Incentive-Fee (FPIF)

Question 23 Choose 1

Which of the following is an input to the Develop Project Charter process?

Show answerHide answer

Correct answer: C

Business case

Question 24 Choose 1

The diagram below is an example of a:


Show answerHide answer

Correct answer: A

Risk breakdown structure (RBS).

Question 25 Choose 1

Who is responsible for initiating a project?

Show answerHide answer

Correct answer: A

Project sponsor

Question 26 Choose 1

Which type of diagram includes groups of information and shows relationships between factors,
causes, and objectives?

Show answerHide answer

Correct answer: D

Matrix

Question 27 Choose 1

Activity cost estimates are quantitative assessments of the probable costs required to:

Show answerHide answer

Correct answer: B

Complete project work.

Question 28 Choose 1

The item that provides more detailed descriptions of the components in the work breakdown
structure (WB5) is called a WBS:

Show answerHide answer

Correct answer: A

dictionary.

Question 29 Choose 1

How should a stakeholder who is classified as high power and low interest be grouped in a
power/interest grid during stakeholder analysis?

Show answerHide answer

Correct answer: A

Keep satisfied

Question 30 Choose 1

The project has a current cost performance index of 0.80. Assuming this performance wi continue,
the new estimate at completion is $1000. What was the original budget at completion for the
project?

Show answerHide answer

Correct answer: A

$800

That's the last free question in Topic 5, Volume E

You've seen the free 30% (30 of 103 questions). Full access unlocks every question and full-length CAPM mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the CAPM exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CAPM exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CAPM mock exam
  • 65questions per mock
  • 105 mintime limit
  • 785questions in the bank
  • Newmock on every attempt