Which input to the Manage Stakeholder Engagement process is used to document changes that
occur during the project?
Show answerHide answer
Correct answer: B
Change log
Certified Associate in Project Management
Free CAPM questions on Topic 1, Volume A, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which input to the Manage Stakeholder Engagement process is used to document changes that
occur during the project?
Correct answer: B
Change log
An input to the Plan Stakeholder Management process is:
Correct answer: D
A stakeholder register.
An input to the Plan Cost Management process is:
Correct answer: C
The project charter,
A technique used to determine the cause and degree of difference between baseline and actual
performance is:
Correct answer: B
Variance analysis.
The process of identifying and documenting project roles, responsibilities, required skills, and
reporting relationships and creating a staffing management plan is known as:
Correct answer: D
Plan Human Resource Management.
Which type of dependency is legally or contractually required or inherent in the nature of work and
often involves physical limitations?
Correct answer: A
Mandatory
During which process does a project manager review all prior information to ensure that all project
work is completed and that the project has met its objectives?
Correct answer: C
Close Project or Phase
An input to the Manage Project Team process is:
Correct answer: A
Work performance reports.
Which input provides suppliers with a clear set of goals, requirements, and outcomes?
Correct answer: A
Procurement statement of work
A large portion of a projects budget is typically expended on the processes in which Process
Group?
Correct answer: B
Planning