Question 31 Choose 1

What is the PRIMARY reason to maintain the chain of custody on evidence that has been
collected?

Show answerHide answer

Correct answer: C

To ensure that it will be admissible in court

Explanation

This is the PRIMARY reason for the chain of custody of evidence. Evidence
must be controlled every step of the way. If it is not, the evidence can be tampered with
and ruled inadmissable. The Chain of Custody will include a detailed record of:
Who obtained the evidence
What was the evidence
Where and when the evidence was obtained
Who secured the evidence
Who had control or possession of the evidence
The following answers are incorrect because :
To ensure that no evidence is lost is incorrect as it is not the PRIMARY reason.
To ensure that all possible evidence is gathered is also incorrect as it is not the PRIMARY
reason.
To ensure that incidents were handled with due care and due diligence is also incorrect as
it is also not the PRIMARY reason.
The chain of custody is a history that shows how evidence was collected, analyzed,
transported, and preserved in order to establish that it is sufficiently trustworthy to be
presented as evidence in court. Because electronic evidence can be easily modified, a
clearly defined chain of custody demonstrates that the evidence is trustworthy which would
make it admissible in court.
Reference : Shon Harris AIO v3 , Chapter-10: Law, Investigation, and Ethics , Page : 727

Question 32 Choose 1

Which of the following is biggest factor that makes Computer Crimes possible?

Show answerHide answer

Correct answer: B

Victim carelessness.

Explanation

The biggest factor that makes Computer Crimes possible is Victim
Carelessness. Awareness and education can reduce the chance of someone becomming a
victim.
The types and frequency of Computer Crimes are increasing at a rapid rate. Computer
Crime was once mainly the result of insiders or disgruntled employees. Now just about
everybody has access to the internet, professional criminals are taking advantage of this.
Specialized skills are no longer needed and a search on the internet can provide a
fraudster with a plethora of tools that can be used to perpetuate fraud.
All too often carelessness leads to someone being a victim. People often use simple
passwords or write them down in plain sight where they can be found by fraudsters. People
throwing away papers loaded with account numbers, social security numbers, or other
types of non-public personal information. There are phishing e-mail attempts where the
fraudster tries to redirect a potential victim to a bogus site that resembles a legitimate site
in an attempt to get the users' login ID and password, or other credentials. There is also
social engineering. Awareness and training can help reduce the chance of someone
becoming a victim.
The following answers are incorrect:
The fraudster obtaining advanced training and special knowledge. Is incorrect because
training and special knowledge is not required. There are many tools widely available to
fraudsters.
Collusion with others in information processing. Is incorrect because as more and more
people use computers in their daily lives, it is no longer necessary to have someone on the
inside be a party to fraud attempts.
System design flaws. Is incorrect because while System design flaws are sometimes a
factor in Computer Crimes more often then not it is victim carelessness that leads to
Computer Crimes. References:
OIG CBK Legal, Regulations, Compliance and Investigations (pages 695 - 697)

Question 33 Choose 1

What would BEST define risk management?

Show answerHide answer

Correct answer: C

The process of reducing risk to an acceptable level

Explanation

This is the basic process of risk management.
Risk is the possibility of damage happening and the ramifications of such damage should it
occur. Information risk management (IRM) is the process of identifying and assessing risk,
reducing it to an acceptable level, and implementing the right mechanisms to maintain that
level. There is no such thing as a 100 percent secure environment. Every environment has
vulnerabilities and threats to a certain degree.
The skill is in identifying these threats, assessing the probability of them actually occurring
and the damage they could cause, and then taking the right steps to reduce the overall
level of risk in the environment to what the organization identifies as acceptable.
Proper risk management requires a strong commitment from senior management, a
documented process that supports the organization's mission, an information risk
management (IRM) policy and a delegated IRM team. Once you've identified your
company's acceptable level of risk, you need to develop an information risk management
policy.
The IRM policy should be a subset of the organization's overall risk management policy
(risks to a company include more than just information security issues) and should be
mapped to the organizational security policies, which lay out the acceptable risk and the
role of security as a whole in the organization. The IRM policy is focused on risk
management while the security policy is very high-level and addresses all aspects of security. The IRM policy should address the following items:
Objectives of IRM team
Level of risk the company will accept and what is considered an acceptable risk (as defined
in the previous article)
Formal processes of risk identification
Connection between the IRM policy and the organization's strategic planning processes
Responsibilities that fall under IRM and the roles that are to fulfill them
Mapping of risk to internal controls
Approach for changing staff behaviors and resource allocation in response to risk analysis
Mapping of risks to performance targets and budgets
Key indicators to monitor the effectiveness of controls
Shon Harris provides a 10,000-foot view of the risk management process below:
A big question that companies have to deal with is, "What is enough security?" This can be
restated as, "What is our acceptable risk level?" These two questions have an inverse
relationship. You can't know what constitutes enough security unless you know your
necessary baseline risk level.
To set an enterprise-wide acceptable risk level for a company, a few things need to be
investigated and understood. A company must understand its federal and state legal
requirements, its regulatory requirements, its business drivers and objectives, and it must
carry out a risk and threat analysis. (I will dig deeper into formalized risk analysis processes
in a later article, but for now we will take a broad approach.) The result of these findings is
then used to define the company's acceptable risk level, which is then outlined in security
policies, standards, guidelines and procedures.
Although there are different methodologies for enterprise risk management, the core
components of any risk analysis is made up of the following:
Identify company assets
Assign a value to each asset
Identify each asset's vulnerabilities and associated threats
Calculate the risk for the identified assets
Once these steps are finished, then the risk analysis team can identify the necessary
countermeasures to mitigate the calculated risks, carry out cost/benefit analysis for these
countermeasures and report to senior management their findings.
When we look at information security, there are several types of risk a corporation needs to be aware of and address properly. The following items touch on the major categories:
Physical damage Fire, water, vandalism, power loss, and natural disasters
Human interaction Accidental or intentional action or inaction that can disrupt productivity
Equipment malfunction Failure of systems and peripheral devices
Inside and outside attacks Hacking, cracking, and attacking
Misuse of data Sharing trade secrets, fraud, espionage, and theft
Loss of data Intentional or unintentional loss of information through destructive means
Application error Computation errors, input errors, and buffer overflows
The following answers are incorrect:
The process of eliminating the risk is not the best answer as risk cannot be totally
eliminated.
The process of assessing the risks is also not the best answer.
The process of transferring risk is also not the best answer and is one of the ways of
handling a risk after a risk analysis has been performed.
References:
Shon Harris , AIO v3 , Chapter 3: Security Management Practices , Page: 66-68
and
http://searchsecurity.techtarget.com/tip/Understanding-risk

Question 34 Choose 1

Which of the following best describes remote journaling?

Show answerHide answer

Correct answer: D

Real time transmission of copies of the entries in the journal of transactions to an
alternate site.

Explanation

Remote Journaling is a technology to facilitate sending copies of the journal
of transaction entries from a production system to a secondary system in realtime. The
remote nature of such a connection is predicated upon having local journaling already
established. Local journaling on the production side allows each change that ensues for a
journal-eligible object e.g., database physical file, SQL table, data area, data queue, byte
stream file residing within the IFS) to be recorded and logged. It’s these local images that
flow to the remote system. Once there, the journal entries serve a variety of purposes, from
feeding a high availability software replay program or data warehouse to offering an offline,
realtime vault of the most recent database changes.
Reference(s) used for this question:
The Essential Guide to Remote Journaling by IBM
and
TIPTON, Hal, (ISC)2, Introduction to the CISSP Exam presentation.
and
KRUTZ, Ronald L. & VINES, Russel D., The CISSP Prep Guide: Mastering the Ten
Domains of Computer Security, John Wiley & Sons, 2001, Chapter 8: Business Continuity
Planning and Disaster Recovery Planning (page 286).

Question 35 Choose 1

If your property Insurance has Actual Cash Valuation (ACV) clause, your damaged
property will be compensated based on:

Show answerHide answer

Correct answer: A

Value of item on the date of loss

Explanation

This is called the Actual Cash Value (ACV) or Actual Cost Valuation (ACV) All of the other answers were only detractors. Below you have an explanation of the
different types of valuation you could use. It is VERY important for you to validate with your
insurer which one applies to you as you could have some very surprising finding the day
you have a disaster that takes place.
Replacement Cost
Property replacement cost insurance promises to replace old with new. Generally,
replacement of a building must be done on the same premises and used for the same
purpose, using materials comparable to the quality of the materials in the damaged or
destroyed property.
There are some other limitations to this promise. For example, the cost of repairs or
replacement for buildings
doesn’t include the increased cost associated with building codes or other laws controlling
how buildings must be built today. An endorsement adding coverage for the operation of
Building Codes and the increased costs associated with complying with them is available
separately — usually for additional premium.
In addition, some insurance underwriters will only cover certain property on a depreciated
value (actual cash value — ACV) basis even when attached to the building. This includes
awnings and floor coverings, appliances for refrigerating, ventilating, cooking, dishwashing,
and laundering. Depreciated value also applies to outdoor equipment or furniture.
Actual Cash Value (ACV)
The ACV is the default valuation clause for commercial property insurance. It is also known
as depreciated value, but this is not the same as accounting depreciated value. The actual
cash value is determined by first calculating the replacement value of the property. The
next step involves estimating the amount to be subtracted, which reflects the
building’s age, wear, and tear.
This amount deducted from the replacement value is known as depreciation. The amount
of depreciation is reduced by inflation (increased cost of replacing the property); regular
maintenance; and repair (new roofs, new electrical systems, etc.) because these factors
reduce the effective age of the buildings.
The amount of depreciation applicable is somewhat subjective and certainly subject to
negotiation. In fact, there is often disagreement and a degree of uncertainty over the
amount of depreciation applicable to a particular building.
Given this reality, property owners should not leave the determination of depreciation to
chance or wait until suffering a property loss to be concerned about it. Every three to five years, property owners should
obtain a professional appraisal of the replacement value and depreciated value of the
buildings.
The ACV valuation is an option for directors to consider when certain buildings are in need
of repair, or budget constraints prevent insuring all of your facilities on a replacement cost
basis. There are other valuation options for property owners to consider as well.
Functional Replacement Cost
This valuation method has been available for some time but has not been widely used. It is
beginning to show up on property insurance policies imposed by underwriters with
concerns about older, buildings. It can also be used for buildings, which are functionally
obsolete.
This method provides for the replacement of a building with similar property that performs
the same function, using less costly material. The endorsement includes coverage for
building codes automatically.
In the event of a loss, the insurance company pays the smallest of four payment options.
1. In the event of a total loss, the insurer could pay the limit of insurance on the building or
the cost to replace the building on the same (or different) site with a payment that is
“functionally equivalent.”
2. In the event of a partial loss, the insurance company could pay the cost to repair or
replace the damaged portion in the same architectural style with less costly material (if
available).
3. The insurance company could also pay the amount actually spent to demolish the
undamaged portion of the building and clear the site if necessary.
4. The fourth payment option is to pay the amount actually spent to repair, or replace the
building using less costly materials, if available (Hillman and McCracken 1997).
Unlike the replacement cost valuation method, which excluded certain fixtures and
personal property used to service the premises, this endorsement provides functional
replacement cost coverage for these items (awnings, floor coverings, appliances, etc.)
(Hillman nd McCracken 1997).
As in the standard replacement cost value option, the insured can elect not to repair or replace the property. Under these circumstances the company pays the smallest of the
following:
1. The Limit of Liability
2. The “market value” (not including the value of the land) at the time of the loss. The
endorsement defines “market value” as the price which the property might be expected to
realize if ffered for sale in fair market.”
3. A modified form of ACV (the amount to repair or replace on he same site with less costly
material and in the same architectural tyle, less depreciation) (Hillman and McCracken
1997).
Agreed Value or Agreed Amount
Agreed value or agreed amount is not a valuation method. Instead, his term refers to a
waiver of the coinsurance clause in the property insurance policy. Availability of this
coverage feature varies among insurers but, it is usually available only when the
underwriter has proof (an independent appraisal, or compliance with an insurance
company valuation model) of the value of your property.
When do I get paid?
Generally, the insurance company will not pay a replacement cost settlement until the
property that was damaged or destroyed is actually repaired or replaced as soon as
reasonably possible after the loss.
Under no circumstances will the insurance company pay more than your limit of insurance
or more than the actual amount you spend to repair or replace the damaged property if this
amount is less than the limit of insurance.
Replacement cost insurance terms give the insured the option of settling the loss on an
ACV basis. This option may be exercised if you don’t plan to replace the building or if you
are faced with a significant coinsurance penalty on a replacement cost settlement.
References:
http://www.schirickinsurance.com/resources/value2005.pdf
and
TIPTON, Harold F. & KRAUSE, MICKI
Information Security Management Handbook, 4th Edition, Volume 1
Property Insurance overview, Page 587

Question 36 Choose 1

Under United States law, an investigator's notebook may be used in court in which of the
following scenarios?

Show answerHide answer

Correct answer: C

To refresh the investigators memory while testifying.

Explanation

An investigator's notebook cannot be used as evidence is court. It can only
be used by the investigator to refresh his memory during a proceeding, but cannot be
submitted as evidence in any form.
The following answers are incorrect:
When the investigator is unwilling to testify. Is incorrect because the notebook cannot be
submitted as evidence in any form.
When other forms of physical evidence are not available. Is incorrect because the notebook
cannot be submitted as evidence in any form.
If the defense has no objections. Is incorrect because the notebook cannot be submitted as
evidence in any form.

Question 37 Choose 1

What is called an exception to the search warrant requirement that allows an officer to
conduct a search without having the warrant in-hand if probable cause is present and
destruction of the evidence is deemed imminent?

Show answerHide answer

Correct answer: B

Exigent Circumstance Doctrine

Explanation

An Exigent Circumstance is an unusual and time-sensitive circumstance that
justifies conduct that might not be permissible or lawful in other circumstances.
For example, exigent circumstances may justify actions by law enforcement officers acting
without a warrant such as a mortal danger to a young child. Examples of other exigent
circumstances include protecting evidence or property from imminent destruction.
In US v Martinez, Justice Thomas of the United States Court of Appeal used these words:
"As a general rule, we define exigent circumstances as those circumstances that would
cause a reasonable person to believe that entry was necessary to prevent physical harm to
the officers or other persons, the destruction of relevant evidence, the escape of the
suspect, or some other consequence improperly frustrating legitimate law enforcement
efforts."
In Alvarado, Justice Blackburn of the Court of Appeals of Georgia referred to exigent
circumstances in the context of a drug bust:
"The exigent circumstance doctrine provides that when probable cause has been
established to believe that evidence will be removed or destroyed before a warrant can be
obtained, a warrantless search and seizure can be justified. As many courts have noted,
the need for the exigent circumstance doctrine is particularly compelling in narcotics cases,
because contraband and records can be easily and quickly destroyed while a search is
progressing. Police officers relying on this exception must demonstrate an objectively
reasonable basis for deciding that immediate action is required."
All of the other answers were only detractors made up and not legal terms.
Reference(s) used for this question:
Source: KRUTZ, Ronald L. & VINES, Russel D., The CISSP Prep Guide: Mastering the
Ten Domains of Computer Security, 2001, John Wiley & Sons, Page 313.
and
http://www.duhaime.org/LegalDictionary/E/ExigentCircumstances.aspx

Question 38 Choose 1

What can be defined as an event that could cause harm to the information systems?

Show answerHide answer

Correct answer: B

A threat

Explanation

A threat is an event or activity that has the potential to cause harm to the
information systems. A risk is the probability that a threat will materialize. A vulnerability, or
weakness, is a lack of a safeguard, which may be exploited by a threat, causing harm to
the information systems.
Source: KRUTZ, Ronald L. & VINES, Russel D., The CISSP Prep Guide: Mastering the
Ten Domains of Computer Security, John Wiley & Sons, 2001, Chapter 1: Access Control
Systems (page 32).

Question 39 Choose 1

What is called an event or activity that has the potential to cause harm to the information
systems or networks?

Show answerHide answer

Correct answer: D

Threat

Explanation

Source: KRUTZ, Ronald L. & VINES, Russel D., The CISSP Prep Guide:
Mastering the Ten Domains of Computer Security, 2001, John Wiley & Sons, Pages 16, 32.

Question 40 Choose 1

Which of the following statements pertaining to disaster recovery is incorrect?

Show answerHide answer

Correct answer: D

When returning to the primary site, the most critical applications should be brought back
first.

Explanation

Explanation: It's interesting to note that the steps to resume normal processing operations
will be different than the steps in the recovery plan; that is, the least critical work should be
brought back first to the primary site.
My explanation:
at the point where the primary site is ready to receive operations again, less critical
systems should be brought back first because one has to make sure that everything will be
running smoothly at the primary site before returning critical systems, which are already
operating normally at the recovery site.
This will limit the possible interruption of processing to a minimum for most critical systems,
thus making it the best option.
Source: KRUTZ, Ronald L. & VINES, Russel D., The CISSP Prep Guide: Mastering the
Ten Domains of Computer Security, John Wiley & Sons, 2001, Chapter 8: Business
Continuity Planning and Disaster Recovery Planning (page 291).

Full mock exam

Sit the SSCP exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real SSCP exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full SSCP mock exam
  • 65questions per mock
  • 105 mintime limit
  • 1,048questions in the bank
  • Newmock on every attempt