Question 11 Choose 1

Which product describes the roles and responsibilities for achieving the effective
management of anticipated threats and opportunities in a project?

Show answerHide answer

Correct answer: B

Risk Management Strategy

Question 12 Choose 1

Identify the missing word(s) in the following sentence.
During a quality review meeting [ ? ] any identified defects.

Show answerHide answer

Correct answer: C

the agreed actions should be recorded for

Question 13 Choose 1

Which should be used to document any uncompleted work that needs to be done to a
project product after the project has closed?

Show answerHide answer

Correct answer: B

Follow-on action recommendations

Question 14 Choose 1

Which role is part of the project management team?

Show answerHide answer

Correct answer: A

Change Authority

Question 15 Choose 1

Which risk response type is a recommended response to both an opportunity and a threat?

Show answerHide answer

Correct answer: B

Reduce

Question 16 Choose 1

Which is a valid statement about the Project Support role?

Show answerHide answer

Correct answer: A

Can be performed by the Project Manager

Question 17 Choose 1

Which of the following statements about quality assurance and Project Assurance is true?

Show answerHide answer

Correct answer: D

Project Assurance ensures compliance to standards within the project environment;
quality assurance ensures compliance across the organization

Question 18 Choose 1

Which process is used by a Team Manager to coordinate work on one or more of the
project's products?

Show answerHide answer

Correct answer: D

ManagingProduct Delivery

Question 19 Choose 1

What product identifies the management stages and other major control points in a project?

Show answerHide answer

Correct answer: B

Project Plan

Question 20 Choose 1

Which is an objective of the Controlling a Stage process?

Show answerHide answer

Correct answer: C

Prevent scopecreep' by monitoring products for uncontrolled change

Full mock exam

Sit the Prince2-Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real Prince2-Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full Prince2-Foundation mock exam
  • 65questions per mock
  • 105 mintime limit
  • 276questions in the bank
  • Newmock on every attempt