If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated
to for a decision?
Show answerHide answer
Correct answer: C
Corporate/programme management
PRINCE2 Foundation Exam
Free Prince2-Foundation questions on Topic 1: Volume A, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated
to for a decision?
Correct answer: C
Corporate/programme management
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits
laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should
be referred to the Project Manager down by the Project Board.
Correct answer: C
Both 1 and 2 are true
Which is a benefit of using PRINCE2?
Correct answer: B
Provides for the efficient and economic use of management time
When considering risks, which describes an opportunity in a project?
Correct answer: B
An uncertain event that could have a favourable impact on objectives
Which of the following is the Business Case used for during the Managing a Stage
Boundary process?
Which is NOT a type of issue?
Correct answer: B
A constraint
Which is a responsibility of a risk owner?
Correct answer: C
Manage, monitor and control all aspects of an assigned risk
Which product summarizes progress and is used to decide whether to amend the project
scope or stop the project?
Correct answer: B
End Stage Report
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels
of [?] to reflect the needs of the different levels of management involved in a project,
Correct answer: B
Plan
Which is an objective of the quality review technique?
Correct answer: A
To baseline a product
You've seen the free 30% (29 of 99 questions). Full access unlocks every question and full-length Prince2-Foundation mock exams (65 questions, 105 minutes), a different mock on every attempt.
Full-length mocks with the same number of questions and the same time limit as the real Prince2-Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.
Get full Prince2-Foundation mock exam