Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before
the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to
reflect the current status of a project.
Select one option.
Show answerHide answer
Correct answer: C
Both 1 and 2 are true