Question 11 Choose 1

Which is a purpose of the Closing a Project process?

Show answerHide answer

Correct answer: C

 Recognize whether objectives set out in the original Project Initiation Documentation
have been achieved

Question 12 Choose 1

Identify the missing word in the following sentence. A member of the Project Board is
responsible for [ ? ] assurance.

Show answerHide answer

Correct answer: B

 supplier

Question 13 Choose 1

Which is a typical core activity within configuration management?

Show answerHide answer

Correct answer: C

Verification and audit

Question 14 Choose 1

Which does NOT reflect the PRINCE2 principle of continued business justification?

Show answerHide answer

Correct answer: C

 If a project is no longer forecast to deliver a financial benefit, it should be stopped.

Question 15 Choose 1

Which is NOT one of the PRINCE2 integrated elements?

Show answerHide answer

Correct answer: C

The products

Question 16 Choose 1

Which two roles are linked by the Managing Product Delivery process?

Show answerHide answer

Correct answer: C

Project Manager and Team Manager

Question 17 Choose 1

Which is an objective of the Initiating a Project process?

Show answerHide answer

Correct answer: C

  Summarize how the organization's project management method will be tailored for the
project

Question 18 Choose 1

Identify the missing word in the following sentence. The guiding obligations and good
practices which determine whether the project is genuinely being managed using PRINCE2
form the [ ? ] of the method.

Show answerHide answer

Correct answer: A

Principles

Question 19 Choose 1

What needs to be in place to ensure effective issue and change control?

Show answerHide answer

Correct answer: A

Configuration management system

Question 20 Choose 1

What is the collective name for individuals or groups who may be affected by a project?

Show answerHide answer

Correct answer: C

 Stakeholders

Full mock exam

Sit the PRINCE2 Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2 Foundation mock exam
  • 65questions per mock
  • 105 mintime limit
  • 150questions in the bank
  • Newmock on every attempt