Question 1 Choose 1

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should
be used to check whether there is a requirement to send copies of the End Stage Report to
external interested parties.

Show answerHide answer

Correct answer: B

Communication Management Strategy

Question 2 Choose 1

Which is the base product against which the Project Board can assess progress, issues
and ongoing viability questions?

Show answerHide answer

Correct answer: B

Project Initiation Documentation

Question 3 Choose 1

Who should act as the communication channel between a project and corporate or
programme management?

Show answerHide answer

Correct answer: A

Project Board

Question 4 Choose 1

Which is an objective of the Managing Product Delivery process?

Show answerHide answer

Correct answer: D

  Ensure that work on products is authorized and agreed with the team

Question 5 Choose 1

Why is the Initiating a Project process used?

Show answerHide answer

Correct answer: B

  To fully understand how the project objectives will be achieved before committing
significant resources

Question 6 Choose 1

Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before
the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to
reflect the current status of a project.

Show answerHide answer

Correct answer: C

 Both 1 and 2 are true

Question 7 Choose 1

Which is NOT a purpose of a Benefits Review Plan?

Show answerHide answer

Correct answer: A

Define the period over which the cost-benefit analysis will be based

Question 8 Choose 1

Which is a benefit of using PRINCE2?

Show answerHide answer

Correct answer: B

Provides for the efficient and economic use of management time

Question 9 Choose 1

Which statement about the Directing a Project process is true?

Show answerHide answer

Correct answer: A

Provides a mechanism for the Project Board to assure that there is continued business
justification

Question 10 Choose 1

Which is a purpose of the Directing a Project process?

Show answerHide answer

Correct answer: D

Delegate day-to-day management of the project to the Project Manager

Full mock exam

Sit the PRINCE2 Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2 Foundation mock exam
  • 65questions per mock
  • 105 mintime limit
  • 150questions in the bank
  • Newmock on every attempt