Question 21 Choose 1

Information transmission is greatest amongst team members who are working on:

Show answerHide answer

Correct answer: B

The same task through pair programming.

Question 22 Choose 1

In Agile risk management, a risk burndown chart is best used to:

Show answerHide answer

Correct answer: D

Illustrate the project risk profile and new and changing risks.

Question 23 Choose 1

A user story says that a product must be very fast.During the demo, the Product Owner is
dissatisfied with the speed of the product.The most likely reason that this occurred is
because the user story was:

Show answerHide answer

Correct answer: C

Not testable.

Question 24 Choose 1

A business analyst has identified a new risk in an Agile project.What is the best first step
the business analyst should take regarding this risk?

Show answerHide answer

Correct answer: C

Add the risk in a clearly visible location and ensure it is discussed after the next daily
stand up.

Question 25 Choose 1

Which of the following is part of the 12 practices defined in eXtreme Programming (XP)?

Show answerHide answer

Correct answer: B

Small releases

Question 26 Choose 1

A common estimation unit for Agile projects is:

Show answerHide answer

Correct answer: C

Story points.

Question 27 Choose 1

The smallest amount of functionality that delivers customer value is best described as a:

Show answerHide answer

Correct answer: C

Minimum marketable feature.

Question 28 Choose 1

When facilitated and managed well, the primary benefits of a project retrospective should
be to:

Show answerHide answer

Correct answer: D

Allow the team to get ahead on release planning.

Question 29 Choose 1

Scrum practices are facilitated by the:

Show answerHide answer

Correct answer: A

ScrumMaster.

Question 30 Choose 1

Project managers use velocity to determine:

Show answerHide answer

Correct answer: A

If the team is committing to an appropriate amount of work for the iteration.

Full mock exam

Sit the PMI-200 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMI-200 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMI-200 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 145questions in the bank
  • Newmock on every attempt