Information transmission is greatest amongst team members who are working on:
Show answerHide answer
Correct answer: B
The same task through pair programming.
PMI Agile Certified Practitioner (PMI-ACP)�
Free PMI-200 mock exam questions 21–30, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Information transmission is greatest amongst team members who are working on:
Correct answer: B
The same task through pair programming.
In Agile risk management, a risk burndown chart is best used to:
Correct answer: D
Illustrate the project risk profile and new and changing risks.
A user story says that a product must be very fast.During the demo, the Product Owner is
dissatisfied with the speed of the product.The most likely reason that this occurred is
because the user story was:
Correct answer: C
Not testable.
A business analyst has identified a new risk in an Agile project.What is the best first step
the business analyst should take regarding this risk?
Correct answer: C
Add the risk in a clearly visible location and ensure it is discussed after the next daily
stand up.
Which of the following is part of the 12 practices defined in eXtreme Programming (XP)?
Correct answer: B
Small releases
A common estimation unit for Agile projects is:
Correct answer: C
Story points.
The smallest amount of functionality that delivers customer value is best described as a:
Correct answer: C
Minimum marketable feature.
When facilitated and managed well, the primary benefits of a project retrospective should
be to:
Correct answer: D
Allow the team to get ahead on release planning.
Scrum practices are facilitated by the:
Correct answer: A
ScrumMaster.
Project managers use velocity to determine:
Correct answer: A
If the team is committing to an appropriate amount of work for the iteration.