Question 1 Choose 1

The ScrumMaster notices repeated friction between two team members in the Daily Scrum
meetings.The next step should be to:

Show answerHide answer

Correct answer: B

Schedule a meeting with them after a Daily Scrum meeting to explore and resolve the
issue.

Question 2 Choose 1

The best approach to estimate the work on a project when using story points is to have:

Show answerHide answer

Correct answer: D

The team work together to agree on estimates in a group setting.

Question 3 Choose 1

Team A is producing 61 points per iteration and Team B is producing 20 points per
iteration.Team A has more senior engineers.A manager demands that Team B match
Team A’s points in the next iteration.Based on this information, it is reasonable to tell the
manager that:

Show answerHide answer

Correct answer: A

it is impossible to compare two separate teams on points alone.

Question 4 Choose 1

When using Agile Earned Value Management (EVM), progress should be measured at
which level?

Show answerHide answer

Correct answer: D

Release

Question 5 Choose 1

Who is responsible for the“definition of done”?

Show answerHide answer

Correct answer: A

The team

Question 6 Choose 1

How is the participatory design process characterized?

Show answerHide answer

Correct answer: C

End users participate and assist in the design process from the beginning of the project.

Question 7 Choose 1

Which type of estimate refers to estimating a story based on its relationship to one or more
other stories?

Show answerHide answer

Correct answer: A

Algorithmic

Question 8 Choose 1

A ScrumMaster:

Show answerHide answer

Correct answer: C

provides leadership, guidance, and coaching.

Question 9 Choose 1

According to the Agile Manifesto, which of the following describes the more valued items? 

Show answerHide answer

Correct answer: C

Individual interactions, working software, customer collaboration, and responding to
change

Question 10 Choose 1

Risk exposure is the:

Show answerHide answer

Correct answer: A

Funds set aside to contain the risk.

Full mock exam

Sit the PMI-200 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMI-200 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMI-200 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 145questions in the bank
  • Newmock on every attempt